BILL ANALYSIS                                                                                                                                                                                                    




                   Senate Appropriations Committee Fiscal Summary
                           Senator Christine Kehoe, Chair

                                           1954 (Skinner)
          
          Hearing Date:  08/02/2010           Amended: 07/15/2010
          Consultant:  Brendan McCarthy   Policy Vote: EU&C 9-0














































          AB 1954 (Skinner), Page 2


          _________________________________________________________________ 
          ____
          BILL SUMMARY: AB 1954 authorizes the Public Utilities Commission  
          to approve in advance the recovery through electricity rates of  
          the costs of a transmission proposed to meet the state's  
          Renewable Portfolio Standard goals. The bill sets the "de  
          minimus" amount of non-renewable energy that may be used by a  
          renewable energy facility at two percent, and authorizes the  
          Energy Commission to adjust that level up to five percent on a  
          case by case basis.
          _________________________________________________________________ 
          ____
                            Fiscal Impact (in thousands)

           Major Provisions         2010-11      2011-12       2012-13     Fund
           
          PUC transmission oversight        Minor and absorbable  
          costsSpecial *

          Energy Commission      $110                             Special  
          **                     
             renewable energy oversight     

          * Public Utilities Commission Utility Reimbursement Account.
          ** Renewable Resources Trust Fund.
          _________________________________________________________________ 
          ____

          STAFF COMMENTS: 
          
          Current law requires the state's investor owned electricity  
          utilities and load serving entities to increase their  
          procurement of renewable energy by one percent per year, such  
          that twenty percent of their total electricity load comes from  
          renewable resources by December 31, 2010. This requirement is  
          referred to as the Renewable Portfolio Standard. All three of  
          the state's investor owned utilities are behind in their  
          procurement of renewable resources, in part because of a lack of  
          transmission infrastructure from areas with potential renewable  
          resources.

          Also under current state and federal law, utilities are allowed  
          to recover the costs of permitting and constructing transmission  
          lines through electricity rates. The Federal Energy Regulatory  
          Commission generally sets the cost recovery rates for  
          transmission. If the federal government does not authorize cost  







          AB 1954 (Skinner), Page 2


          recovery for a project, the Public Utilities Commission is  
          authorized in statute to allow cost recovery. Determinations  
          about cost recovery are done once the project has been  
          completed.

          AB 1954 authorizes the Public Utilities Commission to approve an  
          advice letter from an investor owned utility seeking  
          pre-approval of cost recovery through electricity rates for a  
          transmission project that will facilitate achievement of the  
          Renewable Portfolio Standard. The bill provides that ultimate  
          rate recovery is still subject to review by the Public Utilities  
          Commission to ensure that the utility incurred the costs  
          reasonably and prudently.

          The Public Utilities Commission indicates that the costs to  
          review advice letters under the bill can be absorbed within  
          existing resources dedicated to transmission planning and rate  
          design. Staff does not anticipate any significant costs to rate  
          payers under the bill, as the Public Utilities Commission is  
          only authorized to pre-approve costs recovery for projects  
          designed to meet the existing Renewable Portfolio Standard  
          requirements in law.

          Some renewable energy providers use small amounts of  
          non-renewable fuels as part of their renewable energy  
          production. Current law allows a "de minimus" amount of  
          non-renewable energy production to be included with renewable  
          energy sources for purposes of meeting the state's Renewable  
          Portfolio Standard. The Energy Commission is required to  
          determine the "de minimus" amount. (The Energy Commission has  
          defined the "de minimus" amount as less than two percent of  
          total fuel use.)

          AB 1954 directs the Energy Commission to set the "de minimus"  
          amount of non-renewable energy that may be included with  
          renewable energy at no more than two percent of total fuel use.  
          The bill also authorizes the Energy Commission to allow up to  
          five percent to come from non-renewable fuels, on a case-by-case  
          basis, if the Energy Commission finds that the additional use of  
          non-renewable fuels will lead to an increase in overall  
          renewable energy generation and reduce variability in  
          generation.

          The Energy Commission indicates that it will need one additional  
          position to review existing renewable generation facilities to  
          ensure that they comply with the new "de minimus" standard.  







          AB 1954 (Skinner), Page 2


          (Some facilities may have been authorized a higher level of  
          fossil fuel use.) The additional position will also be  
          responsibly for establishing criteria to determine whether  
          additional non-renewable fuel use will lead to additional  
          renewable energy and reduce variability.

          AB 1954 will only become operative if SB 722 (Simitian) is  
          enacted. SB 722 increases the state's Renewable Portfolio  
          Standard to 33 percent by 2020 and makes several other changes  
          to the program. SB 722 is in the Assembly Appropriations  
          Committee.


          Staff recommends the bill be amended to adopt an amendment  
          inadvertently left out when the bill was amended in the Senate  
          Energy, Utilities & Communications Committee. The proposed  
          amendment specifies that in order to qualify for more than two  
          percent non-renewable fuel use, the non-renewable fuel must come  
          from either natural gas or hydrogen derived by reformation of a  
          fossil fuel.