BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 2216
                                                                  Page  1

          Date of Hearing:   April 6, 2010

                   ASSEMBLY COMMITTEE ON BUSINESS AND PROFESSIONS
                                 Mary Hayashi, Chair
                AB 2216 (Fuentes) - As Introduced:  February 18, 2010
          
          SUBJECT  :   Works of improvement.

           SUMMARY  :   Reduces the time available to a claimant to give  
          written notice that he or she is enforcing a claim against a  
          bond for a public works project, and decreases the time period  
          during which a contractor must pay his or her subcontractors.    
          Specifically,  this bill  :  

          1)Decreases, from 10 to 7, the number of days within which a  
            prime contractor or subcontractor must pay a subcontractor  
            after receiving a progress payment, unless otherwise agreed to  
            in writing.

          2)Requires a claimant to give written notice to the surety and  
            bond principal that he or she is enforcing a claim prior to  
            completion, or recordation of notice of completion, of the  
            project, commencing January 1, 2011.   

           EXISTING LAW:  

          1)Requires that, for private and public works of improvement,  
            and in a public works contract, a prime contractor or  
            subcontractor pay to any subcontractor, not later than 10 days  
            after receipt of each progress payment, unless otherwise  
            agreed to in writing, the respective amount allowed the  
            contractor on account of the work performed by the  
            subcontractors, to the extent of each contractor's interest  
            therein, as prescribed.

          2)Requires, with regard to a contract entered into on or after  
            January 1, 1995, that in order to enforce a claim upon any  
            payment bond given in connection with a public work, that a  
            claimant give the 20-day public works bond preliminary notice,  
            as provided.  Existing law further authorizes a claimant, if  
            the 20-day public works preliminary bond notice was not given  
            as prescribed by statute, to enforce a claim by giving written  
            notice to the surety and the bond principal, as provided,  
            within 15 days after recordation of a notice of completion, or  
            if no notice of completion has been recorded, within 75 days  








                                                                  AB 2216
                                                                  Page  2

            after completion of the work of improvement. 

           FISCAL EFFECT  :   Unknown.  This bill is keyed non-fiscal.

           COMMENTS  :   

           Purpose of the bill  .  According to the author's office, "With  
          California's economy and cash flow continuing to tighten, it is  
          important for contractors to keep close controls on payments,  
          moneys owed, as well as potential disputes." 

           Background  .  In private works, any person who provides  
          construction services or materials to a construction project has  
          the right to file a lien on the property if they are not paid;  
          however, prior to filing the lien, a 20-day preliminary lien  
          notice must be filed with the owner and general  contractor  
          identifying the contractor and notifying the owner and general  
          contractor of the potential lien claim.  This must be done  
          within 20 days from first furnishing labor or materials.  After  
          an owner files a notice of completion, a contractor has 60 days  
          to record a lien and a subcontractor or materials supplier has  
          30 days.   

          In public works, instead of a lien claim, there are claims that  
          can be made against the surety bond, referred to as a bond  
          claim.  The 20-day notice applies in public works, but even if  
          the notice is not filed, the contractor can make a claim within  
          15 days after recordation of a notice of completion, or if no  
          notice of completion has been recorded, up to 75 days after the  
          notice of completion.  This bill revises this timeline to  
          require the bond claim be filed before the final notice of  
          completion.  The author's office argues that this change avoids  
          general contractors from being hit by "surprise" claims.  

          This bill also reduces the time period a general contractor has  
          to pay his or her subcontractor after the general has been paid  
          a progress payment from the owner.  This time period is reduced  
          from 10 to 7 days.  It is unclear what percentage of payments  
          occur in the last 3 days of this window, and whether the  
          reduction to 7 days will have any significant impact.   

           Arguments in support  .  California Legislative Conference of the  
          Plumbing, Heating and Piping Industry and the National  
          Electrical Contractors Association writes, "AB 2216 represents a  
          good faith effort between members of the construction industry  








                                                                  AB 2216
                                                                  Page  3

          in California to agree on terms and conditions related to  
          construction contracts, bonds and payment periods.

          "With California's economy and cash flow continuing to tighten,  
          it is important for contractors to keep close controls on  
          payments, money owed, as well as potential disputes.  This  
          measure will resolve payment related issues and help struggling  
          contracts with cash flow problems.  The solution is a balanced  
          approach that will expedite progress payments and ensure that  
          anyone that provides material and labor to public works projects  
          get paid for work performed and approved when they provide  
          notice of that work prior to the job being completed."

           Arguments in opposition  .  American Subcontractors Association  
          California, Inc. (ASAC) writes, "[The elimination of the 75-day  
          grace period for filing a claim] is a decades old public policy  
          that acknowledges that the subcontractor may not know that a  
          project is entirely complete due to the general contractor's  
          failure to record a notice of completion.  The 75-day grace  
          period was therefore established by the Legislature to enable  
          the subcontractors to get paid for their work."  ASAC is also  
          opposed to section 3252 (c) of the bill, which "denies  
          subcontractors relief and payment for their work if they fail,  
          even inadvertently, to notify parties about their claim prior to  
          the date of completion.  This is a huge problem because  
          subcontractors, particularly early finishing trades, have no way  
          of knowing when the project will be complete wand whether the  
          project is actually complete?. Construction management is the  
          general contractor's obligation."   

           Related legislation  .  AB 396 (Fuentes), 2009, reduced the time  
          available for a claimant to make a claim against a bond by  
          providing that if a claimant has not provided a 20-day public  
          work preliminary bond notice as specified, the claimant may  
          enforce a claim by giving written notice to the surety and bond  
          principal prior to the completion of the project or recordation  
          of a notice of completion.  This bill died in Assembly  
          Appropriations Committee. 

          SB 802 (Leno), 2009, would have reduced the time required for a  
          prime contractor or subcontractor to pay any subcontractor, to  
          no later than seven days of receipt of each progress payment,  
          among other amendments.  This bill was vetoed by the Governor,  
          who only addressed the issue of retention amounts in his veto  
          message.  








                                                                  AB 2216
                                                                  Page  4


           Double-referred  .  This bill is double-referred to Assembly  
          Judiciary Committee.

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Associated General Contractors of California (sponsor)
          California Legislative Conference of the Plumbing, Heating and  
          Piping Industry
          National Electrical Contractors Association 

           Opposition 
           
          American Subcontractors Association California, Inc.
           
          Analysis Prepared by  :    Sarah Weaver / B. & P. / (916) 319-3301