BILL ANALYSIS                                                                                                                                                                                                    



                                                                  AB 2216
                                                                  Page  1


          ASSEMBLY THIRD READING
          AB 2216 (Fuentes)
          As Amended  May 11, 2010
          Majority vote 

           BUSINESS & PROFESSIONS  11-0    JUDICIARY           10-0        
           
           ----------------------------------------------------------------- 
          |Ayes:|Hayashi, Emmerson,        |Ayes:|Feuer, Tran, Brownley,    |
          |     |Conway, Eng, Hernandez,   |     |Evans, Hagman, Jones,     |
          |     |Hill, Ma, Nava, Niello,   |     |Knight, Monning, Nava,    |
          |     |Ruskin, Smyth             |     |Skinner                   |
           ----------------------------------------------------------------- 

           SUMMARY  :   Decreases the time period during which a contractor  
          must pay his or her subcontractors, requires a project entity to  
          provide written notice of pending completion, and reduces the  
          time available for a claimant to enforce a bond claim.    
          Specifically,  this bill  :  

          1)Decreases, from 10 to 7, the number of days within which a  
            prime contractor or subcontractor must pay a subcontractor  
            after receiving a progress payment, unless otherwise agreed to  
            in writing.

          2)Requires, prior to completion or recordation of a notice of  
            completion, every project entity to provide written notice of  
            pending completion to each subcontractor who has provided a  
            20-day preliminary bond notice, as specified.

          3)Permits, if the 20-day public works preliminary bond notice  
            was not given, a claimant to enforce a claim by giving written  
            notice to the surety and bond principal prior to a project's  
            completion or recordation of a notice of completion, whichever  
            is later.  

           EXISTING LAW  requires:

          1)That, for private and public works of improvement, and in a  
            public works contract, a prime contractor or subcontractor pay  
            to any subcontractor, not later than 10 days after receipt of  
            each progress payment, unless otherwise agreed to in writing,  
            the respective amount allowed the contractor on account of the  
            work performed by the subcontractors, to the extent of each  








                                                                  AB 2216
                                                                  Page  2


            contractor's interest therein, as prescribed.

          2)With regard to a contract entered into on or after January 1,  
            1995, that in order to enforce a claim upon any payment bond  
            given in connection with a public work, that a claimant give  
            the 20-day public works bond preliminary notice, as provided.   
            Existing law further authorizes a claimant, if the 20-day  
            public works preliminary bond notice was not given as  
            prescribed by statute, to enforce a claim by giving written  
            notice to the surety and the bond principal, as provided,  
            within 15 days after recordation of a notice of completion, or  
            if no notice of completion has been recorded, within 75 days  
            after completion of the work of improvement. 

           FISCAL EFFECT  :   Unknown.  This bill is keyed non-fiscal.

           COMMENTS  :  In private works, any person who provides  
          construction services or materials to a construction project has  
          the right to file a lien on the property if they are not paid;  
          however, prior to filing the lien, a 20-day preliminary lien  
          notice must be filed with the owner and general  contractor  
          identifying the contractor and notifying the owner and general  
          contractor of the potential lien claim.  This must be done  
          within 20 days from first furnishing labor or materials.  After  
          an owner files a notice of completion, a contractor has 60 days  
          to record a lien and a subcontractor or materials supplier has  
          30 days.   

          In public works, instead of a lien claim, there are claims that  
          can be made against the surety bond, referred to as a bond  
          claim.  The 20-day notice applies in public works, but even if  
          the notice is not filed, the contractor can make a claim within  
          15 days after recordation of a notice of completion, or if no  
          notice of completion has been recorded, up to 75 days after the  
          notice of completion.  This bill requires, prior to completion  
          or recordation of a notice of completion, every project entity  
          to provide written notice of pending completion to each  
          subcontractor who has provided a 20-day preliminary bond notice.  
           This bill then revises the claim timeline to require the bond  
          claim be filed before the project's completion, or the final  
          notice of completion, whichever is later.  The author's office  
          argues that this change avoids general contractors from being  
          hit by "surprise" claims.  









                                                                  AB 2216
                                                                  Page  3


          This bill also reduces the time period a general contractor has  
          to pay his or her subcontractor after the general has been paid  
          a progress payment from the owner.  This time period is reduced  
          from 10 to 7 days.  It is unclear what percentage of payments  
          occur in the last 3 days of this window, and whether the  
          reduction to 7 days will have any significant impact.   

          California Legislative Conference of the Plumbing, Heating and  
          Piping Industry and the National Electrical Contractors  
          Association writes in support, "AB 2216 represents a good faith  
          effort between members of the construction industry in  
          California to agree on terms and conditions related to  
          construction contracts, bonds and payment periods.

          "With California's economy and cash flow continuing to tighten,  
          it is important for contractors to keep close controls on  
          payments, money owed, as well as potential disputes.  This  
          measure will resolve payment related issues and help struggling  
          contracts with cash flow problems.  The solution is a balanced  
          approach that will expedite progress payments and ensure that  
          anyone that provides material and labor to public works projects  
          get paid for work performed and approved when they provide  
          notice of that work prior to the job being completed."

          American Subcontractors Association California, Inc. (ASAC)  
          writes in opposition, "[The elimination of the 75-day grace  
          period for filing a claim] is a decades old public policy that  
          acknowledges that the subcontractor may not know that a project  
          is entirely complete due to the general contractor's failure to  
          record a notice of completion.  The 75-day grace period was  
          therefore established by the Legislature to enable the  
          subcontractors to get paid for their work."  ASAC is also  
          opposed to section 3252(c) of the bill, which "denies  
          subcontractors relief and payment for their work if they fail,  
          even inadvertently, to notify parties about their claim prior to  
          the date of completion.  This is a huge problem because  
          subcontractors, particularly early finishing trades, have no way  
          of knowing when the project will be complete wand whether the  
          project is actually complete?. Construction management is the  
          general contractor's obligation."   

           
          Analysis Prepared by  :    Sarah Weaver / B. & P. / (916) 319-3301  









                                                                  AB 2216
                                                                  Page  4




                                                               FN:  0004283