BILL ANALYSIS                                                                                                                                                                                                    






                             SENATE JUDICIARY COMMITTEE
                           Senator Ellen M. Corbett, Chair
                              2009-2010 Regular Session


          AB 2216 (Fuentes)
          As Amended May 11, 2010
          Hearing Date: June 29, 2010
          Fiscal: No
          Urgency: No
          TW:jd
                    

                                        SUBJECT
                                           
                                Works of Improvement

                                      DESCRIPTION  

          This bill would reduce the time required for a general  
          contractor or subcontractor to pay a subcontractor, to no later  
          than seven days of receipt of each progress payment.  This bill  
          would also revise the timing requirements for a subcontractor to  
          file a surety claim. 

                                      BACKGROUND  

          In public works projects, it is not uncommon for contractors to  
          hire various subcontractors, which in turn hire various other  
          subcontractors to complete the project.  This has the effect of  
          creating various tiers of subcontractors.  Tier 1 would be  
          comprised of the first subcontractors hired by the original  
          contractor, and tier 2 would be comprised of subcontractors  
          hired by the tier 1 subcontractors.  Each additional  
          subcontractor hired may be unknown to the original contractor.   
          Upon completion of the project, there may exist subcontractors  
          hired under additional tiers that have not been paid by the  
          subcontractor who hired them.  Subsequently, when the original  
          contractor pays out on all labor and materials utilized for the  
          project, the original contractor may have to spend additional  
          money to pay the unpaid subcontractor.

          In order to create a system by which the original contractor is  
          made aware of the existence of potential claims by additional  
          subcontractors, the Legislature enacted various statutes  
          requiring the additional subcontractors to provide notice to the  
                                                                (more)



          AB 2216 (Fuentes)
          Page 2 of ?



          original contractor.  The initial notice submitted by the  
          subcontractors is the 20-day preliminary notice.  If the 20-day  
          preliminary notice is not served by the subcontractor, the  
          subcontractor may still make a claim against the public works'  
          surety bond for payment.

          Prior to 1995, California followed the federal model for  
          preliminary notice deadlines under the Miller Act (40 U.S.C.  
          3131-3134) whereby subcontractors had 90 days from the date on  
          which the claimant furnished the last labor, services,  
          equipment, or materials for which such claim was made to submit  
          a preliminary notice.   AB 3357 (Goldsmith, Ch. 974, Stats.  
          1994) reduced the 90-day preliminary notice requirement to 20  
          days.  AB 3357 was amended prior to enactment to include a  
          safeguard for bond claimants whereby, in the event the  
          subcontractors failed to submit the 20-day preliminary notice,  
          the claimant could still submit a bond claim within 15 days of  
          recordation of the notice of completion, or, if the notice of  
          completion was not recorded, within 75 days of completion of the  
          project.  

          AB 396 (Fuentes, 2009) would have required a subcontractor, who  
          had failed to submit a 20-day preliminary notice, to give  
          written notice to the surety and the bond principal before the  
          completion of the public works project or recordation of a  
          notice of completion in order to enforce a claim based on labor  
          or services rendered to a public works project.  This bill was  
          held under submission in the Assembly Appropriations Committee.

          SB 802 (Leno, 2009), among other things, contained provisions  
          that would have reduced the time required for an original  
          contractor or subcontractor to pay any subcontractor from ten  
          days to no later than seven days of receipt of each progress  
          payment and would have revised the ability of subcontractors to  
          file bond claims.  This bill was vetoed for reasons related to  
          other parts of that bill regarding reducing the amount a public  
          entity could retain from payments to general contractors.

          This bill, sponsored by Associated General Contractors of  
          California, the Construction Employers Association, and the  
          National Electric Contractors Association, would provide for the  
          same reduction in payment time as proposed by SB 802.  This bill  
          also would provide new limitations on the ability of a  
          subcontractor on public works projects to make claims against  
          the surety bond. 

                                                                      



          AB 2216 (Fuentes)
          Page 3 of ?



                                CHANGES TO EXISTING LAW
           
          1.    Existing law  requires a general contractor or subcontractor  
            to make a progress payment to a subcontractor no later than  
            ten days of receipt of each progress payment. (Bus. & Prof.  
            Code Sec. 7108.5; Pub. Contract Code Sec. 10262; Pub. Contract  
            Code Sec. 10262.5.)

             This bill  would reduce the number of days from ten days to  
            seven days within which a general contractor or subcontractor  
            is required to make a progress payment to a subcontractor.

          2.     Existing law  defines a "preliminary 20-day notice" to mean  
            a written notice from a claimant that was given prior to the  
            assertion of a claim against a payment bond, or the filing of  
            a stop notice on public work.  (Civ. Code Sec. 3098.)
             Existing law  requires a subcontractor to submit a preliminary  
            20-day notice to the general contractor and public agency no  
            later than 20 days after the subcontractor has first furnished  
            labor, services, equipment, or materials to the jobsite.   
            (Civ. Code Secs. 3098(a), 3252(a).)

             Existing law  provides that if the 20-day preliminary notice is  
            not given, the claimant is not precluded from giving notice at  
            any time thereafter, but claims against a payment bond can  
            only be made for labor, services, equipment, or materials  
            rendered within 20 days of the services of the preliminary  
            notice.  (Civ. Code Sec. 3098(d).) 
             Existing law  provides that, in the event the 20-day  
            preliminary notice was not given, the subcontractor may still  
            enforce a claim against the surety bond by submitting a bond  
            claim within 15 days after recordation of the notice of  
            project completion or 75 days after project completion if no  
            notice of completion is recorded.  (Civ. Code Sec. 3252(b).)

             This bill  , as applied to public works projects completed  
            before December 31, 2010, would continue the existing  
            provisions for bond claims made by a subcontractor in the  
            event a 20-day preliminary notice was not served.

             This bill  , as applied to public works projects completed after  
            January 1, 2011, would require a subcontractor, who failed to  
            give the 20-day preliminary notice, to submit a written claim  
            against the surety bond prior to the completion or recordation  
            of notice of completion of the project, whichever is later.

                                                                      



          AB 2216 (Fuentes)
          Page 4 of ?



             This bill  also would require every project entity in  
            connection with the public works project to provide written  
            notice of pending completion of the project to all  
            subcontractors who have submitted the 20-day preliminary  
            notice.
           
                                       COMMENT
           
          1.  Stated need for the bill  
          
          The author writes:
          
            With California's economy and case flow continuing to tighten,  
            it is important for contractors to keep close controls on  
            payments, moneys owed, as well as potential disputes.  In  
            private works, any person who provides construction services  
            or materials to a construction project has the right to file a  
            lien on the property if they are not paid; however, prior to  
            filing the lien, a 20 day preliminary lien notice must be  
            filed with the owner and general contractor identifying the  
            contractor and notifying the owner and general contractor of  
            the potential lien claim in the event payments are not paid  
            for work performed or materials provided.  In public works,  
            instead of a lien claim, there are claims that can be made  
            against the surety bond, referred to as a bond claim.
            The 20 day notice applies in public works, but provided that  
            if the notice is not filed the contractor is not penalized and  
            can make a claim up to 75 days  after  the notice of completion.  
             This area of law has been revised to state at a minimum, the  
            bond claim must be filed before the final notice of  
            completion.  This change avoids general contractors from being  
            hit by "surprise" claims from second and third tier  
            contractors at a time when all of the funds have already been  
            paid to higher tier subcontractors.

            The bill also reduces the time period a general contractor has  
            to pay his or her subcontractor after the general has been  
            paid a progress payment from the owner.  This time period is  
            reduced from 10 to 7 days.  With cash flow continuing to be an  
            issue, especially in a tight economy, it is helpful to ensure  
            that subcontractors receive their progress payments in a  
            timely manner.
          
          2.  Legislative history of preliminary notice and claims against  
            surety bonds  

                                                                      



          AB 2216 (Fuentes)
          Page 5 of ?



          In 1994, AB 3357 (Goldsmith, Ch. 974, Stats. 1994) reduced the  
          amount of time within which a subcontractor had to submit a  
          preliminary notice from 90 days to 20 days.  The sponsor of that  
          bill, Associated General Contractors of California (AGCC) (the  
          same sponsor as this bill), claimed that 90 days was too long  
          for stray claims to be submitted by subcontractors because the  
          general contractors, in wrapping up the job, would have already  
          distributed job funds.  

          This committee required an amendment to AB 3357 to protect  
          unsophisticated laborers and materials suppliers who were  
          unaware of mechanic's lien procedures.  The amendment provided  
          that subcontractors who failed to submit the 20-day preliminary  
          notice could still make a claim on the surety bond if they  
          submitted a surety claim within 15 days after recordation of  
          notice of completion or 75 days if no notice of completion is  
          recorded.  The sponsor, AGCC, agreed to this amendment to  
          protect the rights of these laborers and materials suppliers.

          In 2009, SB 802 (Leno, 2009) contained provisions similar to  
          this bill and would have reduced the time required for an  
          original contractor or subcontractor to pay any subcontractor  
          from ten days to no later than seven days of receipt of each  
          progress payment and would have revised the ability of  
          subcontractors to file bond claims.  SB 802 was viewed by  
          contractors and subcontractors as a compromise of various issues  
          and the overall package was seen to be beneficial to both sides.  
           This bill was vetoed for other reasons related to different  
          parts of that bill regarding reducing the amount a public entity  
          could retain from payments to general contractors.

          Now, AGCC wants to limit the ability of subcontractors and  
          materials suppliers to submit bond claims.  AGCC argues that  
          this bill contains the same provisions as SB 802 for payment and  
          surety claim deadlines.  While it is true that SB 802 contained  
          these provisions, SB 802 contained additional provisions that  
          were favorable to subcontractors, which this bill does not.   
          Opponents argue that SB 802 was a package of negotiated items.   
          This bill is more limited and focuses primarily on limiting the  
          time for which subcontractors may submit bond claims to before  
          completion of the project or before the notice of completion is  
          recorded.  Opponents of this bill note that many times the  
          notice of completion is not recorded, requiring the  
          subcontractors to guess at when they needed to submit a bond  
          claim.  It should be noted that other states have similar  
          preliminary notice and bond claim provisions with deadlines  
                                                                      



          AB 2216 (Fuentes)
          Page 6 of ?



          ranging from 45 days to 90 days.  Given the history of this  
          statute and the desire to protect unsophisticated  
          subcontractors, the provisions of this bill appear to be  
          contrary to legislative intent.  (See Comment 3.)

          3.  Protecting subcontractors and materials suppliers and their  
            ability to assert claims for payment  

          This bill would shorten the time within which a subcontractor or  
          materials supplier may assert a claim against the public works  
          surety bond.  This bill is similar to other attempts by the  
          sponsor to shorten or eliminate the time period within which a  
          subcontractor could file a bond claim.  (See AB 901 (Goldsmith,  
          Ch. 225, Stats. 1995); AB 2806 (Wyland, 2004); AB 411 (Yee,  
          2005); SB 738 (Calderon, 2007); AB 396 (Fuentes, 2009).)   
          Opponents argue that shortening the time within which to file a  
          bond claim has a substantially negative effect on the ability of  
          subcontractors to be paid.  American Subcontractors Association  
          of California, Inc. (ASAC), an opponent of this bill, argues as  
          follows:

            Section 3252(b) of the bill eliminates all bond claims on all  
            projects completed before this year ends provided the  
            subcontractor failed, even inadvertently, to submit a  
            preliminary bond notice within 15 days of the general  
            contractor recording a Notice of Completion (NOC), or within  
            75 days after completion if no NOC was recorded.  This is a  
            decades old public policy that acknowledges that the  
            subcontractor may not know that a project is entirely complete  
            due to the general contractor's failure to record [an] NOC.   
            The 75 day grace period was therefore established by the  
            Legislature to enable the subcontractors to get paid for their  
            work.  However, it is totally inconsistent with section (c) of  
            the bill, creating a double standard and dashing the current  
            subcontractor protections in law.

            Section 3252 (c) of the bill denies contractors relief and  
            payment for their work if they fail, even inadvertently, to  
            notify parties about their claim prior to the date of  
            completion.  This is a huge problem because subcontractors,  
            particularly early finishing trades, have no way of knowing  
            when the project will be complete and whether the project is  
            actually complete; they don't drive by and inspect it daily.   
            This is precisely why the current, equitable law has been in  
            place for so long and should not be curtailed.

                                                                      



          AB 2216 (Fuentes)
          Page 7 of ?



            ASAC submits that general contractors [GCs] should know their  
            subcontractors and suppliers as they supervise their projects  
            and should already know whether their workmanship has been  
            approved and entitled to payment.  Construction management is  
            the GC's obligation and these claims should not surprise the  
            GCs.  Cutting off the subcontractors' claim rights by some  
            less than obvious, indiscernible and arbitrary date (other  
            than recordation date) is simply unfair and reverses  
            California's long standing equitable statutory public policy.   
            (Emphasis omitted.)

          Existing law functions to provide subcontractors and materials  
          suppliers with a backup plan to receive payment for services and  
          materials rendered in the event the subcontractor who hired them  
          fails to pay.  The 20-day preliminary notice functions  
          separately from the bond claim notice.  The 20-day preliminary  
          notice puts the general contractor on notice that a "tier 1"  
          subcontractor hired a "tier 2" subcontractor which may not have  
          been paid for services or materials rendered.  The surety bond  
          claim submitted by the subcontractor or materials supplier  
          functions as a notice to the surety that an outstanding claim  
          exists.  It is important to note that a subcontractor or  
          materials supplier on a public works projects is restricted to  
          submitting bond claims for payment recovery, as opposed to  
          filing a mechanic's lien as authorized in private works  
          projects.  (See Civ. Code Sec. 3109.)  Therefore, a  
          subcontractor or materials supplier may only claim against the  
          project's bond in order to receive payment for money owed.

          Under existing law, if the 20-day preliminary notice is not  
          received by the general contractor, a surety claim may still be  
          filed by the subcontractor within 15 days after recordation of  
          project completion or within 75 days of project completion.  It  
          should be noted that there are a variety of reasons for which a  
          20-day preliminary notice was not received by the contractor.   
          Opponents of this bill are aware of many instances in which the  
          subcontractor mailed the 20-day preliminary notice to the wrong  
          address.  In this event, if the 20-day preliminary notice was  
          submitted a second time to the correct address, but mailed  
          outside the 20-day limit, the subcontractor or materials  
          supplier would have to submit a bond claim in order to perfect  
          any claim to the bond.

          Under this bill, the surety claim must be submitted prior to the  
          completion of the project or prior to the recordation of the  
          notice of project completion.  Although the sponsors tentatively  
                                                                      



          AB 2216 (Fuentes)
          Page 8 of ?



          agreed to amend the bill to provide that the project owner must  
          give notice of pending completion of the project to all  
          subcontractors and materials suppliers who had submitted a  
          20-day notice bond claim, the provisions of this bill still  
          would contain loopholes whereby the ability of subcontractors  
          and materials suppliers to file surety claims for payment of  
          services and materials rendered may be entirely cut off.  

             a.    Loophole Scenario 1:  Provisions of this bill contain no  
               deadline for contractors to submit Notice of Pending  
               Completion to subcontractors  

            This bill provides that a contractor must submit a notice of  
            pending completion to all subcontractors who have submitted a  
            20-day preliminary notice.  This bill provides that  
            subcontractors are allowed to submit a bond claim prior to  
            project completion or prior to recording the notice of  
            completion.

            As noted by the opponents of this bill, in some instances, the  
            notice of completion of the project is never recorded.  This  
            bill, which specifies no deadline prior to the completion of  
            the project by which the contractor must send notice of  
            pending completion to the subcontractors, would allow a  
            general contractor to send out the notice of pending  
            completion to subcontractors the day of project completion.   
            If the notice of completion subsequently is never recorded,  
            the subcontractors who failed to submit a 20-day preliminary  
            notice would have had to submit their bond claims on the day  
            of completion.  As the sponsor argues, submitting the 20-day  
            preliminary notice perfects the bond claim.  It is only  
            subcontractors who did not submit the 20-day preliminary  
            notice that would need to file a bond claim.  These  
            subcontractors would not be given notice pending projection  
            completion by the contractor because the contractor is unaware  
            of the existence of these contractors.  Given that most  
            subcontractors do not continually monitor job sites to see  
            when the project has been completed, subcontractors unaware of  
            the projection completion date would be potentially cut off  
            from utilizing the bond claim provision that was specifically  
            crafted into existing law and agreed upon by the sponsors when  
            the existing statute was enacted when the notice of project  
            completion is never recorded.

              b.   Loophole Scenario 2:  A subcontractor hired after the  
               Notice of Pending Completion is sent by the contractor
                                                                      



          AB 2216 (Fuentes)
          Page 9 of ?



           
            Another example of a scenario in which a subcontractor may be  
            unfairly prejudiced by the provisions under this bill is when  
            a subcontractor is hired on the last day of the project.   
            Under existing law, the subcontractor is required to file a  
            preliminary notice within 20 days of rendering labor or  
            materials.  If the subcontractor was hired on January 1, 2010,  
            the same day as the day of completion, the subcontractor would  
            have until January 21, 2010 to submit the 20-day preliminary  
            notice and thereafter is able to file a claim against the  
            surety.  On the other hand, if this subcontractor  
            inadvertently failed to submit the 20-day preliminary notice  
            on the same day it began and ended work, under existing law  
            the subcontractor could still enforce its claim against the  
            bond by giving written notice to the surety either within 15  
            days of the recordation of a notice of completion or, if no  
            notice of completion is recorded, within 75 days after  
            completion of the project.  

            Under this bill, if the project is completed on January 1,  
            2011, the subcontractor still has 20 days to submit a 20-day  
            preliminary notice.  However, if the subcontractor fails to  
            submit the 20-day preliminary notice, the subcontractor must  
            submit the written claim against the bond prior to completion  
            of the project, which, in this case, would be on the same day  
            it renders labor or materials, or it must submit the bond  
            claim before the recordation of notice of project completion.   
            Given the tight time frame, it is arguable that the contractor  
            would not provide a notice of pending completion to the  
            subcontractor because the contractor would not know in advance  
            the existence of the subcontractor hired on the final day of  
            the project.  The subcontractor would have to guess at when  
            the notice of completion would be recorded and submit the bond  
            claim before that date, which may be before the 20-day  
            preliminary notice deadline.

            Although the late-hired subcontractor can still submit a  
            20-day preliminary notice after rendering services, he or she  
            may not be paid pursuant to this notice.  This bill would cut  
            off the subcontractor's subsequent claim on the bond if the  
            subcontractor did not submit it prior to the recording of the  
            notice of completion of the project.

          To address these issues, ASAC offered an amendment which would  
          have removed the bill's provision regarding claim deadlines  
          based on project completion or recording of the notice of  
                                                                      



          AB 2216 (Fuentes)
          Page 10 of ?



          completion.  Instead, the proposed amendment would have reduced  
          the final deadline from 75 days, under existing law, to 47 days  
                                                    from project completion to submit a bond claim.  ASAC argues  
          that 47 days is the lowest number that could be applied because  
          the public entity typically has 30 days to make the final  
          payment to the general contractor, which in turn has ten days to  
          make a progress payment to the tier 1 subcontractor, which in  
          turn would have seven days, under this bill, to pay the tier 2  
          subcontractor.  If a late-hired tier 2 subcontractor completed  
          work on the last day of the job, he or she would not get paid  
          for these services until at most 47 days after project  
          completion.  If, on the 47th day, the tier 2 subcontractor  
          realized no payment was forthcoming, the tier 2 subcontractor  
          could immediately file a bond claim.  Committee staff  
          recommended rounding this number to 50 days for convenience of  
          all parties and also to provide an additional three days to file  
          the bond claim.

          Committee staff recommended an amendment which would have  
          provided, in the event a subcontractor or materials supplier did  
          not receive a 45-day notice of pending completion from the  
          project owner and the notice of completion is never recorded, a  
          subcontractor or materials supplier could submit a bond claim  
          within 50 days of project completion.  AGCC agreed to provide a  
          45-day notice of pending completion, but believed that  
          subcontractors and materials suppliers should only be allowed 30  
          days from project completion to submit a bond claim.  As  
          discussed above, 30 days is insufficient time for payments to  
          trickle down from the public entity to the subcontractor.  By  
          the time the late-hired subcontractor or materials supplier  
          realizes, on the 47th day, that they have not been paid it is  
          too late for them to submit a bond claim to protect their claim  
          for payment.

          ASAC also submitted an amendment to count the additional days  
          within which to file a bond claim from the date of completion or  
          payment of all progress payments, change orders, retentions, and  
          interest if any, by the general contractor to the subcontractor  
          to whom the claimant provided materials or services.  Given that  
          the tier 2 subcontractor or materials supplier potentially would  
          have no way to know when all progress payments were made because  
          they are not in direct contact with the general contractor or  
          public entity, a more decisive date must be established from  
          which to begin counting the days within which to file a bond  
          claim.  Committee staff recommended setting this decisive date  
          based on "completion," as defined under Section 3086 which  
                                                                      



          AB 2216 (Fuentes)
          Page 11 of ?



          provides that works of improvement which must be accepted by a  
          public entity are deemed completed on the date of acceptance.  

          Multiple attempts at compromise between the stakeholders failed.  
           The current language of this bill provides no safeguards for  
          unsophisticated and unprotected subcontractors and materials  
          suppliers as requested by this Committee when it heard AB 3357  
          (Goldsmith, Ch. 974, Stats. 1994), which created the current  
          75-day protection.  AB 3357 provided that the 90-day preliminary  
          notice would be reduced to a 20-day preliminary notice, but  
          subcontractors and materials suppliers would also be able to  
          utilize the 75-day bond claim procedure.  (See Comment 2.)  AB  
          3357 was a compromise which benefited the contractors who wanted  
          preliminary notices to be submitted faster and provided the bond  
          claim safeguard to protect payment rights of the subcontractors  
          and materials suppliers.  

          4.  Ability of contractors to effectively manage project expenses  

          This bill would require a subcontractor to submit before the  
          completion of the project or before the recordation of notice of  
          completion of the project its claim on the surety bond for  
          payment for services or material rendered.  The sponsor argues  
          that, by requiring the subcontractor to give notice of a  
          potential claim, "the general contractor will be in a position  
          to instruct the first tier subcontractor to pay the  
          subcontractor or supplier before retention proceeds are paid.   
          Under the current rule, a general contractor would pay all of  
          the subcontractors in full believing they have paid their  
          subcontractors, when in fact, they have not paid the  
          subcontractors below them who the subcontractor hired."

          General contractors need to be aware of expenses of the project  
          in order to arrange for payment and revise their budgets  
          accordingly.  Existing law requires subcontractors to file  
          20-day preliminary notices, which gives general contractors  
          information that these subcontractors are expecting payment.   
          However, existing law also provides a fall back provision  
          whereby, in the event the 20-day preliminary notice is not  
          received from the subcontractor, the subcontractor can still  
          submit a surety claim against the project bond.  

          This fall back provision has a negative effect on general  
          contractors.  The sponsor argues that, without being given  
          notice of subcontractor claims through the 20-day preliminary  
          notice requirement, the general contractor would have paid the  
                                                                      



          AB 2216 (Fuentes)
          Page 12 of ?



          first or second tier contractor for services and materials  
          rendered.  The general contractor then has no knowledge of  
          whether the first or second tier contractor actually paid the  
          third and fourth tier subcontractors that they hired.  Further,  
          the sponsor argues that existing law allows subcontractors to  
          ignore the 20-day preliminary notice and general contractors are  
          made aware of subcontractor claims long after the general  
          contractors made payments to the first tier subcontractors.  In  
          some instances, the first tier subcontractors have gone out of  
          business.  The general contractors pay once to the first or  
          second tier, then have to pay out again, based on the subsequent  
          bond claims, to cover the payments still due to the third or  
          fourth tier contractors.  

          However, pursuant to Civil Code Section 3248(b), the general  
          contractor may require the subcontractor to carry a bond to  
          reimburse the general contractor for claims made by the second  
          and third tier subcontractors.  The general contractors, while  
          claiming the burden of making first a payment to the first tier  
          subcontractor, then being hit by surprise by the second and  
          third tier subcontractor claims, have the ability to protect  
          themselves from this scenario through the first tier  
          subcontractor bond.  Committee staff does not have any  
          information as to how many claims the general contractor pays to  
          "surprise" second and third tier subcontractors which are then  
          offset by the bond payouts from first tier contractors.

          5.  Reducing the time frame for payment to subcontractors  

          This bill would reduce the amount of time a contractor or  
          subcontractor, upon receiving a progress payment, has to pay a  
          subcontractor for labor or materials rendered on a private and  
          public works projects.  This bill makes no change to the  
          provision whereby contracting parties may establish their own  
          payment deadlines.  The revision proposed by this bill is  
          beneficial to parties receiving payments for services performed  
          in that they will be paid three days earlier than under existing  
          law.  

          6.  Law Review Commission  

          The issues surrounding the ability of subcontractors and  
          materials suppliers to get paid for services and materials  
          rendered to contractors who need a better system to effectively  
          manage project monies are complex.  Given the number of bills  
          submitted on these issues since 1994, the committee should  
                                                                      



          AB 2216 (Fuentes)
          Page 13 of ?



          consider whether it would be appropriate for the Law Revision  
          Commission to study and issue a report - such a report would  
          provide guidance for how best to clarify, or if supported by a  
          thorough study, how to modify the current process for submitting  
          preliminary notices and surety bond claims.

          SHOULD THE LAW REVISION COMMISSION STUDY THE PUBLIC WORKS  
          PROJECTS PRELIMINARY NOTICE AND SURETY BOND PROCEDURES?


           Support  :  Associated General Contractors of San Diego;  
          California Legislative Conference of the Plumbing, Heating and  
          Piping Industry; National Electrical Contractors Association

           Opposition  :  American Subcontractors Association California,  
          Inc.; Construction Industry Legislative Council; Dynamic Precast  
          Co., Inc.; one individual

                                        HISTORY
           
           Source  :  Associated General Contractors of California;  
          Construction Employers Association; National Electric  
          Contractors Association

           Related Pending Legislation  :  None Known

           Prior Legislation  :  See Background; Comment 2; Comment 3.

           Prior Vote  :

          Assembly Business, Professions and Consumer Protection Committee  
          (Ayes 11, Noes 0)
          Assembly Judiciary Committee (Ayes 10, Noes 0)
          Assembly Floor (Ayes 71, Noes 0)

                                   **************