BILL ANALYSIS                                                                                                                                                                                                    




                   Senate Appropriations Committee Fiscal Summary
                           Senator Christine Kehoe, Chair

                                           2216 (Fuentes)
          
          Hearing Date:  8/2/2010         Amended: 7/15/2010
          Consultant:  Bob Franzoia       Policy Vote: Judiciary 3-1
          _________________________________________________________________ 
          ____
          BILL SUMMARY: AB 2216 would do the following:
           - Require that for private and public works of improvement, a  
          prime contractor or subcontractor pay to any subcontractor, not  
          later than seven days (currently ten days) after receipt of each  
          progress payment, the respective amount allowed the contractor  
          on account of the work performed by the subcontractors.
           - Require, with regard to a contract entered into on or after  
          January 1, 2011, that written notice given to the surety and the  
          bond principal be given prior to the completion of the project,  
          or recordation of a notice of completion, as specified. 
          - Prohibit retention proceeds from exceeding five percent of the  
          payment for those contracts entered into on or after January 1,  
          2011, between a public entity, as defined, and an original  
          contractor, between an original contractor and a subcontractor,  
          and between all subcontractors.  This section would be repealed  
          as of January 1, 2105.
          - Prohibit progress payments upon public works contracts from  
          being made in excess of 100 percent (currently 95 percent) of  
          the percentage of actual work completed, and would require the  
          Department of General Services (DGS) to withhold not more than 5  
          percent (currently not less) of the contract price until final  
          completion and acceptance of the project.  This section would  
          return to current law after January 1, 2015.
          _________________________________________________________________ 
          ____
                            Fiscal Impact (in thousands)

           Major Provisions         2010-11      2011-12       2012-13     Fund
           Change in limits on    Unknown, likely minor, if any, new  
          costs;General/
          retention proceeds     potential reduction in project costsBond/
          and progress payments                                   Special
          _________________________________________________________________ 
          ____

          STAFF COMMENTS: Retention proceeds represent a percentage of the  
          amount of a contract that is withheld by the public entity or  










          the original contractor.  By withholding a percentage of a  
          contract, the public entity or the original contractor maintains  
          a degree of financial control over a project.  In general, the  
          public entity or the original contractor withholds at least five  
          percent of payment until the contract is completed to the  
          satisfaction of the public entity or original contractor.  (When  
          a project is within five percent of completion, the public  
          entity or original contractor may reduce the five percent to a  
          minimum of 125 percent of the value of the remaining work.)   
          Reducing the percentage of a contract that can be withheld would  
          not result in new project costs though it may increase the  
          likelihood that a contractor or subcontractor would fail to  
          complete contracted work, thereby leading to delays and added  
          costs.

          The monetary impact of a contract dispute is generally not  
          related to the amounts that can be withheld or retained by the  
          state.  DGS notes the use of a retention amount greater than  
          five percent is used generally only on smaller projects.  A  
          reduction in the retention level should increase the number of  
          contractor bidding on a project.
          Page 2
          AB 2216 (Fuentes)

          The federal government has implemented a zero percent  
          withholding policy and requires any project which receives  
          federal funds do the same.  As a result of the federal policy  
          Caltrans, which contracts projects involving federal funds, has  
          practical experience with more restrictive contract retention  
          requirements.  At this time, staff is unaware of any increase in  
          contract costs to Caltrans as a result of having to manage  
          contacts with zero or limited retention.  Though the provisions  
          of the bill do not apply to the University of California (UC),  
          it is useful to note that since July 2006 the UC has adopted a  
          policy of limiting retention to five percent.  Previously, UC  
          retained ten percent of payments.

          Under current law, a contractor on a public works project is  
          required to file a performance bond in specified amounts  
          depending on the value of the contract.  By restricting the size  
          of retention proceeds, the bill would increase the likelihood  
          that a contractor will receive a greater percentage of the  
          contract payments upon completion 
          of a project.  By doing so, however, the bill would place  
          greater pressure on the performance bond to make the public  
          entity or the original contractor financially whole in










          the event of a contract dispute.

          Local projects generally are administered such that, at any time  
          after 50 percent of a project is complete and there is a finding  
          that satisfactory progress is being made, the local government  
          may reduce or eliminate further withholding.  Local governments,  
          which appear to make greater use of retention amounts in excess  
          of five percent, may experience greater difficulty in ensuring  
          their public works contracts are fully executed.

          This bill is similar to SB 802 (Leno) 2009 which was vetoed with  
          the following message:

          Under current law, public entities, at a minimum, must retain  
          five percent of a payment to a contractor completing a public  
          works project.  This bill would restrict the state's ability to  
          retain more than five percent of payment and no more than five  
          percent of the public work contract price.

          When a contractor fails to complete a public works project, the  
          public entity needs recourse to ensure that the project gets  
          completed.  Public works contracts have a higher level of risk  
          as public entities usually have to accept the low bidder.   
          Though there are options available to the state to go after a  
          contractor who fails to complete the terms of a public works  
          contract, retaining portions of payment to the contractor  
          provides incentive for the contractor to complete the project.   
          While I am sympathetic with the concerns of subcontractors, the  
          state's responsibility is to protect the taxpayer to make  
          certain that public works projects are completed correctly and  
          within budget; limiting the retention amount hampers the state's  
          ability to do that.