BILL ANALYSIS                                                                                                                                                                                                    



                                                                       



           ------------------------------------------------------------ 
          |SENATE RULES COMMITTEE            |                  AB 2216|
          |Office of Senate Floor Analyses   |                         |
          |1020 N Street, Suite 524          |                         |
          |(916) 651-1520         Fax: (916) |                         |
          |327-4478                          |                         |
           ------------------------------------------------------------ 
           
                                         
                                 THIRD READING


          Bill No:  AB 2216
          Author:   Fuentes (D)
          Amended:  7/15/10 in Senate
          Vote:     21

           
           SENATE JUDICIARY COMMITTEE  :  3-1, 6/29/10
          AYES:  Corbett, Hancock, Leno
          NOES:  Harman
          NO VOTE RECORDED:  Walters

           SENATE APPROPRIATIONS COMMITTEE  :  7-0, 8/2/10
          AYES:  Kehoe, Alquist, Ashburn, Corbett, Price, Wolk, Yee
          NO VOTE RECORDED:  Emmerson, Leno, Walters, Wyland
           
          ASSEMBLY FLOOR  :  71-0, 5/20/10 - See last page for vote


           SUBJECT  :    Works of improvement:  progress payments:   
          notice: 
                      retention proceeds

           SOURCE  :     Associated General Contractors of California
                      Construction Employers Association
                      National Electric Contractors Association


           DIGEST  :    This bill (1) requires that for private and  
          public works of improvement, a prime contractor or  
          subcontractor pay to any subcontractor, not later than  
          seven days (currently ten days) after receipt of each  
          progress payment, the respective amount allowed the  
          contractor on account of the work performed by the  
                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          2

          subcontractors; (2) requires, with regard to a contract  
          entered into on or after January 1, 2011, that written  
          notice given to the surety and the bond principal be given  
          prior to the completion of the project, or recordation of a  
          notice of completion, as specified; (3) prohibits retention  
          proceeds from exceeding five percent of the payment for  
          those contracts entered into on or after January 1, 2011,  
          between a public entity, as defined, and an original  
          contractor, between an original contractor and a  
          subcontractor, and between all subcontractors.  This  
          section would be repealed as of January 1, 2105; and (4)  
          prohibits progress payments upon public works contracts  
          from being made in excess of 100 percent (currently 95  
          percent) of the percentage of actual work completed, and  
          would require the Department of General Services to  
          withhold not more than five percent (currently not less) of  
          the contract price until final completion and acceptance of  
          the project.  This section would return to current law  
          after January 1, 2015.

           ANALYSIS  :    Existing law requires that, for private and  
          public works of improvement, and in a public works  
          contract, a prime contractor or subcontractor pay to any  
          subcontractor, not later than 10 days after receipt of each  
          progress payment, unless otherwise agreed to in writing,  
          the respective amount allowed the contractor on account of  
          the work performed by the subcontractors, to the extent of  
          each contractor's interest therein, as prescribed.

          This bill, instead, requires that those amounts be paid not  
          later than seven days after receipt of each progress  
          payment.

          Existing law requires, with regard to a contract entered  
          into on or after January 1, 1995, in order to enforce a  
          claim upon any payment bond given in connection with a  
          public work, that a claimant give the 20-day public works  
          bond preliminary notice, as provided.  Existing law further  
          authorizes a claimant, if the 20-day public works  
          preliminary bond notice was not given as prescribed by  
          statute, to enforce a claim by giving written notice to the  
          surety and the bond principal, as provided, within 15 days  
          after recordation of a notice of completion, or if no  
          notice of completion has been recorded, within 75 days  

                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          3

          after completion of the work of improvement.

          This bill, instead, with regard to a contract entered into  
          on or after January 1, 2011, requires that the written  
          notice to be given to the surety and the bond principal be  
          given prior to the completion, as defined, of the project,  
          or recordation of a notice of completion.

          Existing law authorizes the Department of General Services  
          (DGS), or any other department with authority to enter into  
          contracts, to contract with suppliers for goods and  
          services and for public works. Existing law provides that  
          in a contract relating to the construction of a public work  
          of improvement between the public entity and original  
          contractor, the original contractor and a subcontractor,  
          and in a contract between a subcontractor and any  
          subcontractor thereunder, the percentage of retention  
          proceeds withheld cannot exceed the percentage specified in  
          the contract between the public entity and the original  
          contractor.

          This bill, instead, prohibits retention proceeds from  
          exceeding five percent of the payment, as specified, for  
          those contracts entered into on or after January 1, 2011,  
          between a public entity, as defined, and an original  
          contractor, between an original contractor and a  
          subcontractor, and between all subcontractors thereunder.

          Existing law contains various provisions relating to  
          contracts for the performance of public works of  
          improvement, including provisions for the payment of  
          progress payments and the disbursing and withholding of  
          retention proceeds.  Existing law prohibits progress  
          payments upon these contracts from being made in excess of  
          95 percent of the percentage of actual work completed plus  
          a like percentage of the value of material delivered, as  
          specified, and requires DGS to withhold not less than five  
          percent of the contract price until final completion and  
          acceptance of the project.

          This bill, until January 1, 2015, instead, prohibits  
          progress payments upon these contracts from being made in  
          excess of 100 percent of the percentage of actual work  
          completed, and requires DGS to withhold not more than five  

                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          4

          percent of the contract price until final completion and  
          acceptance of the project.

           FISCAL EFFECT  :    Appropriation:  No   Fiscal Com.:  Yes    
          Local:  No

          According to the Senate Appropriations Committee:

                          Fiscal Impact (in thousands)

           Major Provisions               2010-11      2011-12        
           2012-13             Fund  

          Change in limits on          Unknown, likely minor, if any,  
          new costs;        General/
          retention proceeds           potential reduction in project  
          costs             Bond/
          and progress payments                                 
          Special
           
           SUPPORT  :   (Verified  8/11/10)

          Associated General Contractors of California (co-source) 
          Construction Employers Association (co-source) 
          National Electric Contractors Association (co-source)
          Associated General Contractors of San Diego
           California Legislative Conference of the Plumbing, Heating  
            and Piping Industry
          National Electrical Contractors Association

           OPPOSITION  :    (Verified  8/11/10)

          American Subcontractors Association California, Inc.

           ARGUMENTS IN SUPPORT  :    The author writes:

            "With California's economy and case flow continuing to  
            tighten, it is important for contractors to keep close  
            controls on payments, moneys owed, as well as potential  
            disputes.  In private works, any person who provides  
            construction services or materials to a construction  
            project has the right to file a lien on the property if  
            they are not paid; however, prior to filing the lien, a  
            20 day preliminary lien notice must be filed with the  

                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          5

            owner and general contractor identifying the contractor  
            and notifying the owner and general contractor of the  
            potential lien claim in the event payments are not paid  
            for work performed or materials provided.  In public  
            works, instead of a lien claim, there are claims that can  
            be made against the surety bond, referred to as a bond  
            claim.

            "The 20 day notice applies in public works, but provided  
            that if the notice is not filed the contractor is not  
            penalized and can make a claim up to 75 days after the  
            notice of completion.  This area of law has been revised  
            to state at a minimum, the bond claim must be filed  
            before the final notice of completion.  This change  
            avoids general contractors from being hit by 'surprise'  
            claims from second and third tier contractors at a time  
            when all of the funds have already been paid to higher  
            tier subcontractors."

           ARGUMENTS IN OPPOSITION  :    The American Subcontractors  
          Association California, Inc. states:

            "The 75 day grace period for claiming payment for work  
            and materials is a right that was statutorily bestowed  
            upon subcontractors and suppliers in 1994, yet AB 2216  
            boldly, and without verified data proving harm, repeals  
            that long standing and mutually agreed upon public  
            policy.  As such, AB 2216 is a very contentious  
            winner-take-all bill that has split the construction  
            industry.  The politics behind this bill are significant  
            and should be removed from the debate.

            "This 'right-to-payment' issue is both broad and complex  
            and should definitely be assigned to the CA Law Revision  
            Commission where it will be very carefully and fairy  
            considered.  ASAC and you, as the Senate Member to the  
            CLRC, can trust that it would invite all stakeholders to  
            the table including material suppliers and surety  
            companies, both of whom have curiously not yet been heard  
            from.

            "The CLRC's non-adversarial forum would allow for  
            collection of facts and data regarding alleged problems  
            with current law. ? facts that to date have not been in  

                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          6

            evidence.  The CLRC just completed a huge project  
            concerning mechanic liens which is contained in SB 189  
            (Lowenthal).  This topic of payment rights should have  
            been brought forward during that process but the sponsors  
            of AB 2216 thought that the legislative approach would be  
            more beneficial to them.

            "In addition, AB 2216 was surprisingly amended during  
            recess on July 15, adding non-germane payment retention  
            cap language from SB 802 (Leno) which was vetoed.  This  
            was presumably done to lessen our opposition and because  
            they believe it would be better received by the Governor  
            this time, despite huge fiscal hurdles at the State and  
            local levels.

            "Lastly, the recess amendments to AB 2216 ratify the  
            recent appellate ruling in the Martin case (1) which  
            cements the vague statutory term 'disputed work' in favor  
            of project owners and general contractors, to the severe  
            detriment of subcontractors.

            "Martin deals with a subcontractor's claims to a general  
            contractor.  If a paying party in 'good faith' disputes  
            claims for extra work or change orders, the paying party  
            may withhold from retention the claimed amount plus 50%  
            until the matter is resolved or judgment is entered,  
            essentially giving the paying party an interest-free loan  
            for an extended period of time.  Unfortunately, the  
            current statute allowing this withholding has no  
            objective standard to determine whether the withholding  
            is in 'good faith', and the Martin Brothers case sets a  
            very low standard by essentially allowing the paying  
            party to withhold for any reason.

            "If AB 2216 is enacted, a litigant could argue that  
            because the Legislature knew of Martin before passing the  
            bill it would stand as new public policy...without open  
            discussion, debate and legislative scrutiny.

            "In conclusion, I am respectfully requesting that you  
            take steps to assign this matter to the CLRC."


           ASSEMBLY FLOOR  : 

                                                           CONTINUED





                                                               AB 2216
                                                                Page  
          7

          AYES:  Adams, Ammiano, Anderson, Arambula, Bass, Beall,  
            Bill Berryhill, Tom Berryhill, Blakeslee, Block,  
            Blumenfield, Bradford, Brownley, Buchanan, Caballero,  
            Charles Calderon, Carter, Chesbro, Conway, Cook, Coto,  
            Davis, De Leon, DeVore, Emmerson, Eng, Feuer, Fong,  
            Fuentes, Fuller, Furutani, Gaines, Galgiani, Garrick,  
            Gilmore, Hagman, Hall, Hayashi, Hernandez, Hill, Huber,  
            Huffman, Jeffries, Jones, Knight, Lieu, Logue, Bonnie  
            Lowenthal, Ma, Mendoza, Miller, Monning, Nestande,  
            Niello, Nielsen, V. Manuel Perez, Portantino, Ruskin,  
            Salas, Saldana, Silva, Skinner, Smyth, Solorio, Audra  
            Strickland, Swanson, Torlakson, Torres, Torrico, Tran,  
            Yamada
          NO VOTE RECORDED:  De La Torre, Evans, Fletcher, Harkey,  
            Nava, Norby, Villines, John A. Perez, Vacancy


          RJG:mw  8/11/10   Senate Floor Analyses 

                         SUPPORT/OPPOSITION:  SEE ABOVE

                                ****  END  ****























                                                           CONTINUED