BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 43
                                                                  Page  1

          Date of Hearing:  July 8, 2009

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                             Anna Marie Caballero, Chair
                     SB 43 (Alquist) - As Amended:  June 30, 2009

           SENATE VOTE  :  Vote not relevant
           
          SUBJECT  :  Joint powers agencies: City of Santa Clara.

           SUMMARY  :  Authorizes the City of Santa Clara (City) and the  
          Redevelopment Agency of Santa Clara (Agency) as a joint powers  
          agency (JPA) to construct, operate, or maintain a stadium for  
          use by a professional football team using a specified  
          design-build authority.  Specifically,  this bill  :   

          1)Authorizes the JPA between the City and the Agency to award a  
            design-build contract related to the stadium to a qualified  
            design-build contractor without utilizing an otherwise  
            applicable competitive bid process, provided the governing  
            body of the JPA determines the cost of the contract is  
            reasonable and the award of the contract without utilizing the  
            competitive bid process is in the best interest of the JPA.

          2)Prohibits the JPA from awarding a design-build contract  
            related to the stadium unless:

             a)   The design-build contract does not require an  
               expenditure of money from the City's general fund;

             b)   The obligation of the Agency to contribute funding  
               toward the amount due under the design-build contract is  
               limited to a specified maximum amount, provided the  
               specified maximum amount need not apply to debt service and  
               other financing costs; and,

             c)   A private party is responsible for any construction cost  
               overruns.

          3)Requires a design-build contract awarded by the JPA to require  
            all subcontract work be awarded through a competitive process  
            established by the JPA.

          4)Authorizes the JPA to specify the payment bond for a  
            design-build contract be in a sum not less than half the  








                                                                  SB 43
                                                                  Page  2

            contract price or $300,000,000, whichever is less.

           EXISTING LAW  :

          1)Authorizes, under the Joint Exercise of Powers Act, two or  
            more public agencies (i.e., federal government, any state, any  
            state department or agency, county, county board of education,  
            county superintendent of schools, city, public corporation,  
            public district, and regional transportation commission in any  
            state) to enter into a joint powers authority to exercise  
            jointly any power common to the contracting agencies and to  
            form a separate JPA at their option.

          2)Requires local officials, under the Local Agency Public  
            Construction Act, to invite bids for construction projects and  
            then award contracts to the lowest responsible bidder under  
            the traditional design-bid-build project delivery system.

          3)Authorizes cities to use the design-build method for projects  
            costing more than $1 million.

          4)Authorizes redevelopment agencies, until January 1, 2016, to  
            use the design-build method for infrastructure projects  
            costing more than $1 million, provided the State Public Works  
            Board approves the project as one of 10 design-build projects  
            statewide.

           FISCAL EFFECT  :  None

           COMMENTS  :   

          1)The author states the San Francisco 49ers (49ers) professional  
            football team would like to use the design-build method to  
            construct a new $937-million stadium in an existing  
            redevelopment project area in the City.  Because the City's  
            charter mandates all public contracts be awarded to the lowest  
            bidder, the City is unable to take advantage of the state's  
            design-build authorization that has been extended to all  
            cities.

          According to the author, on June 2, 2009, the Santa Clara City  
            Council and the 49ers approved a proposal that outlines the  
            financing for the stadium construction.  To assist this  
            project, SB 43 will give the City a legislative option to  
            award a design-build contract through the newly created JPA.








                                                                  SB 43
                                                                 Page  3


          On June 23, 2009, the City established a Charter Review  
            Commission to consider amending its charter to allow for  
            design-build authority.  The author says the City would like  
            to have the ability to consider a design-build option other  
            than having to amend its charter.  The author says a  
            design-build method will allow for greater project  
            collaboration, cost control, faster construction, and a  
            streamlined construction process for a stadium that is  
            projected to be completed in 2014 provided the City's  
            residents in spring 2010 approve the charter amendment  
            allowing the City to utilize design-build.

          2)By entering into a joint powers authority with the Agency, the  
            City will have access to the Agency's tax-increment revenue in  
            the Bayshore North Development Project Area.  The use of the  
            Agency's funds, however, will be limited to a specified  
            maximum amount provided the specified maximum amount need not  
            apply to debt service and other financing costs.  The author  
            states that, in the City's agreement with the 49ers, the  
            Agency will contribute $59 million in redevelopment funds.   
            The rest of the $114 million in public contributions for the  
            $939 million needed for the stadium construction will be $20  
            million from a utility fund for a substation relocation and  
            $35 million from a Mello-Roos tax imposed on the surrounding  
            hotels.  In addition, the 49ers have agreed to be responsible  
            for any cost overruns.

          3)The design-build language in current law is based on a  
            compromise struck in 2000 among local officials, labor groups,  
            and contractors.  Local officials wanted the flexibility and  
            potential cost savings offered by design-build contracts.   
            Labor unions wanted to ensure that counties pre-qualify  
            employers to protect workers' interests.  Contractors wanted  
            to be sure they had fair access to county contracts.  Further  
            changes to the language, consistent with the principles of the  
            2000 compromise were made by SB 287 (Cox), Chapter 376,  
            Statutes of 2005; SB 416 (Ashburn), Chapter 585, Statutes  
            2007, which extended this authority to use design-build  
            contracting for the construction of buildings and directly  
            related improvements to all 58 counties in the state; SB 642  
            (Wolk), Chapter 314, Statues 2008, which extended this  
            authority to use design-build contracting for the construction  
            of buildings and directly related improvements to all cities  
            in the state; SB 1699 (Wiggins), Chapter 415, Statutes 2008,  








                                                                  SB 43
                                                                  Page  4

            which extended this authority to use design-build contracting  
            for the construction of buildings and improvements in excess  
            of $2.5 million directly related to a Sonoma Valley Health  
            Care District hospital or health facility building; and SB 4xx  
            (Cogdill), Chapter 2, Statutes 2009-10 Second Extraordinary  
            Session, which extended this authority to use design-build  
            contracting for infrastructure projects in excess of $1  
            million to redevelopment agencies, provided the State Public  
            Works Board approves the project as one of 10 design-build  
            projects statewide.

          SB 43 would breach the carefully crafted compromised reached in  
            2000 between all interested stakeholders by not including any  
            of the language included in every other design-build  
            authorization law.  There is not a single cross-reference to  
            existing design-build laws.  SB 43 even states that all  
            existing design-build laws are legally inapplicable in this  
            situation.  Furthermore, SB 43 goes another step beyond  
            existing design-build laws and allows the JPA to decide how  
            subcontractors will be hired.  According to the author, the  
            City and 49ers have already agreed 80% to 85% of all  
            subcontracting work will be required to be done with local  
            union labor.  The Committee may wish to consider whether it  
            wishes to diverge from the well-established precedent of the  
            2000 compromise language.

          4)Furthermore, SB 43 grants design-build authority to a JPA, the  
            first time this has been done.  In addition, SB 43 grants the  
            design-build authority to a JPA whose public agency members do  
            not have the authority to use the design-build contracting  
            method on their own (the City is limited by its charter to  
            using only competitive bidding and the Agency is authorized by  
            state law to use design-build only for infrastructure projects  
            in limited circumstances).  The Committee may wish to consider  
            whether it wants to authorize a JPA to use the design-build  
            method without requiring a report back to the Legislature on  
            its use, as has been done most recently with redevelopment  
            agencies on infrastructure projects.

           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          Patricia Mahan, Mayor of the City of Santa Clara
          Santa Clara and San Benito Counties Building & Construction  








                                                                  SB 43
                                                                  Page  5

          Trades Council
          San Francisco 49ers 
           
            Opposition 
           
          Individual letters (10)

           Analysis Prepared by  :    Jennifer R. Klein / L. GOV. / (916)  
          319-3958