BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 545
                                                                  Page  1

          Date of Hearing:   August 19, 2009

                        ASSEMBLY COMMITTEE ON APPROPRIATIONS
                                Kevin De Leon, Chair

                    SB 545 (Cedillo) - As Amended:  June 30, 2009 

          Policy Committee:                               
          TransportationVote:10-0

          Urgency:     No                   State Mandated Local Program:  
          No     Reimbursable:               

           SUMMARY  

          This bill prohibits the Interstate 710 (I-710) freeway gap  
          closure project from being constructed as a surface or  
          above-grade highway.  Specifically, this bill.

          1)Provides that gap closure project be a subsurface  
            transportation facility, specifically a tunnel with the  
            alignment to be determined by Caltrans after completion of  
            environmental studies.

          2)Provides that cut and cover construction technology may be  
            used only at the entrance and exit portals, and the portals  
            are not to encroach upon the City of South Pasadena.  Cut and  
            cover maybe also be used where needed for tunnel ventilation  
            structures, emergency exits, and any other required mitigation  
            measures.

          3)Declares that I-710 between Valley Boulevard in the City of  
            Los Angeles and Del Mar Boulevard in the City of Pasadena will  
            not be a surface or above-grade highway.

           FISCAL EFFECT  

          A bored tunnel is likely the most costly option for constructing  
          this project (compared to a cut and cover, surface or  
          above-grade project). To the extent this bill removes the  
          possibility of using a feasible and less expensive option, this  
          bill creates cost pressures potentially in the hundreds of  
          millions of dollars.  (It should be noted, however, that  
          numerous other options have been explored and rejected over  
          several decades.)








                                                                  SB 545
                                                                  Page  2


          [Measure R, a 30-year local transportation sales tax approved by  
          Los Angeles voters last November, dedicated $780 million for the  
          freeway gap closure tunnel project.  Caltrans indicates that  
          preliminary estimates of project costs for constructing a tunnel  
          to close the I-710 gap are approximately $6 billion to $8  
          billion.]

           COMMENTS  

           1)Background  .  I-710 is a major north-south interstate freeway  
            running 23 miles through Los Angeles County-from Long Beach to  
            Alhambra, stopping short of the originally planned terminus in  
            Pasadena.  Construction of the 4.5-mile segment between  
            Alhambra and Pasadena, through South Pasadena, has been  
            delayed for decades due to community opposition. Over the past  
            40 years, alternative concepts have been proposed and  
            evaluated to complete this gap, but to date none have been  
            successful in satisfying the regional mobility needs and  
            community/environmental concerns.  In response to these  
            concerns, and to lessen the potential impact of completing the  
            I-710, a tunnel concept was proposed as a potential option to  
            the surface alternatives.

           2)Purpose  .  This bill effectively eliminates the ability of  
            Caltrans to build a surface-route project to complete the  
            freeway gap closure by defining this segment of I-710 as a  
            subsurface route, thereby effectively precluding the use of  
            state funds on a surface project.  The MTA has completed the  
            feasibility assessment of a tunnel alternative to extend the  
            I-710 from its current terminus at Valley Boulevard in the  
            City of Los Angeles to I-210 in the City of Pasadena.   
            Generally, the study concluded that the tunnel concept is  
            feasible. Potential environmental impacts were identified,  
            however, preliminary assessments concluded that these impacts  
            could be minimized, eliminated or mitigated.  The report  
            concluded that no insurmountable environmental issues were  
            identified that would preclude further consideration of the  
            tunnel alternative. 

            Based on this, proponents argue that further study is  
            warranted and that the tunnel concept should be advanced to  
            the next more detailed stage to further validate the findings  
            of this assessment and to determine whether the tunnel concept  
            can ultimately serve as the alternative to complete the I-710.  








                                                                  SB 545
                                                                  Page  3

            According to the author, he has introduced this bill to  
            fulfill "a commitment made to the City of South Pasadena that  
            would ensure that there would never be a surface-route  
            solution for 710 corridor."

           Analysis Prepared by  :    Chuck Nicol / APPR. / (916) 319-2081