BILL NUMBER: SB 802	AMENDED
	BILL TEXT

	AMENDED IN ASSEMBLY  SEPTEMBER 4, 2009

INTRODUCED BY   Senator Leno
    (   Principal coauthor:   Assembly Member
  Fuentes   ) 

                        FEBRUARY 27, 2009

    An act to amend Section 10261 of, and to add Section 7201
to, the   An act to amend Section 7108.5 of the
Business and Professions Code, to amend Section 3252 of the Civil
Code, and to amend Sections 10262 and 10262.5 of, to amend, repeal,
and add Section 10261 of, and to add and repeal Section 7201 of, the
 Public Contract Code, relating to  public contracts
  works of improvement  .



	LEGISLATIVE COUNSEL'S DIGEST


   SB 802, as amended, Leno.  Public contracts  
Works of improvement: progress payments: notice:  retention
proceeds.
   (1) Existing law  requires that, for private and public works
of improvement, and in a public works contract, a prime contractor or
subcontractor pay to any subcontractor, not later than 10 days of
receipt of each progress payment, unless otherwise agreed to in
writing, the respective amount allowed the contractor on account of
the work performed by the subcontractors, to the extent of each
contractor's interest therein, as prescribed.  
   This bill would, instead, require that those amounts be paid not
later than 7 days of receipt of each progress payment.  
   (2) Existing law requires, with regard to a contract entered into
on or after January 1, 1995, in order to enforce a claim upon any
payment bond given in connection with a public work, that a claimant
give the 20-day public works bond preliminary notice, as provided.
Existing law further authorizes a claimant, if the 20-day public
works preliminary bond notice was not given as prescribed by statute,
to enforce a claim by giving written notice to the surety and the
bond principal, as provided, within 15 days after recordation of a
notice of completion, or if no notice of completion has been
recorded, within 75 days after completion of the work of improvement.
 
   This bill would, instead, with regard to a contract entered into
on or after January 1, 2010, require that the written notice to be
given to the surety and the bond principal be given prior to the
completion, as defined, of the project, or recordation of a notice of
completion. 
    (3)     Existing law  authorizes the
Department of General Services, or any other department with
authority to enter into contracts, to contract with suppliers for
goods and services  and for public works  . Existing law
provides that in a contract  relating to the construction of a
public work of improvement  between the  public entity and
original contractor, the  original contractor and a
subcontractor, and in a contract between a subcontractor and any
subcontractor thereunder, the percentage of retention proceeds
withheld cannot exceed the percentage specified in the contract
between the public entity and the original contractor.
   This bill would instead prohibit retention proceeds  to
exceed   from exceeding  5% of the payment, as
specified, for  all   those  contracts
entered into on or after January 1, 2010, between a public entity, as
defined, and an original contractor, between an original contractor
and a subcontractor, and between all subcontractors thereunder.

   (2) 
    (4)  Existing law contains various provisions relating
to contracts for the performance of public works of improvement,
including provisions for the  payment of progress payments and
the  disbursing and withholding of retention proceeds. Existing
law  prohibits progress   payments upon these contracts
from being made in excess of 95% of the percentage of actual work
completed plus a like percentage of the value of material delivered,
as specified, and requires the Department of General Services to
withhold not less than 5% of the contract price until final
completion and acceptance of the project.
   This bill would  , until December 31, 2013, instead, prohibit
progress payments upon these contracts from being made in excess of
100%   of the percentage of actual work completed, and would
 require the Department of General Services to withhold not
more than 5% of the contract price until final completion and
acceptance of the project.
   Vote: majority. Appropriation: no. Fiscal committee: yes.
State-mandated local program: no.


THE PEOPLE OF THE STATE OF CALIFORNIA DO ENACT AS FOLLOWS:

   SECTION 1.    Section 7108.5 of the  
Business and Professions Code   is amended to read: 
   7108.5.  A prime contractor or subcontractor shall pay to any
subcontractor, not later than  10   seven 
days of receipt of each progress payment, unless otherwise agreed to
in writing, the respective amounts allowed the contractor on account
of the work performed by the subcontractors, to the extent of each
subcontractor's interest therein. In the event that there is a good
faith dispute over all or any portion of the amount due on a progress
payment from the prime contractor or subcontractor to a
subcontractor, then the prime contractor or subcontractor may
withhold no more than 150 percent of the disputed amount.
   Any violation of this section shall constitute a cause for
disciplinary action and shall subject the licensee to a penalty,
payable to the subcontractor, of 2 percent of the amount due per
month for every month that payment is not made. In any action for the
collection of funds wrongfully withheld, the prevailing party shall
be entitled to his or her attorney's fees and costs.
   The sanctions authorized under this section shall be separate
from, and in addition to, all other remedies either civil,
administrative, or criminal.
   This section applies to all private works of improvement and to
all public works of improvement, except where Section 10262 of the
Public Contract Code applies.
   SEC. 2.    Section 3252 of the   Civil Code
  is amended to read: 
   3252.  (a) With regard to a contract entered into on or after
January 1, 1995, in order to enforce a claim upon any payment bond
given in connection with a public work, a claimant shall give the
20-day public works preliminary bond notice as provided in Section
3098. 
   (b) If 
    (b)     (1)     On and
after January 1, 1995, and before January 1, 2010, if  the
20-day public work preliminary bond notice was not given as provided
in Section 3098, a claimant may enforce a claim by giving written
notice to the surety and the bond principal as provided in Section
3227 within 15 days after recordation of a notice of completion. If
no notice of completion has been recorded, the time for giving
written notice to the surety and the bond principal is extended to 75
days after completion of the work of improvement. 
   (2) On and after January 1, 2010, if the 20-day public work
preliminary bond notice was not given as provided in Section 3098, a
claimant may enforce a claim by giving written notice to the surety
and the bond principal, as provided in Section 3227, prior to
completion, as defined in Section 3086, of the project, or
recordation of a notice of completion. 
   SECTION 1.   SEC. 3.   Section 7201 is
added to the Public Contract Code, to read:
   7201.  (a) (1) This section shall apply with respect to all
contracts entered into on or after January 1, 2010, between a public
entity and an original contractor, between an original contractor and
a subcontractor, and between all subcontractors thereunder, relating
to the construction of any public work of improvement.
   (2) Under no circumstances shall any provision of this section be
construed to limit the ability of any public entity to withhold 150
percent of the value of any disputed amount of work from the final
payment, as provided for in subdivision (c) of Section 7107. In the
event of a good faith dispute, nothing in this section shall be
construed to require a public entity to pay for work that is not
approved or accepted in accordance with the proper plans or
specifications.
   (3) For purposes of this section, "public entity" means the state,
including every state agency, office, department, division, bureau,
board, or commission, the California State University, the University
of California, a city, county, city and county, including chartered
cities and chartered counties, district, special district, public
authority, political subdivision, public corporation, or nonprofit
transit corporation wholly owned by a public agency and formed to
carry out the purposes of the public agency.
   (b) (1) The retention proceeds withheld from any payment by a
public entity from the original contractor, by the original
contractor from any subcontractor, and by a subcontractor from any
subcontractor thereunder shall not exceed 5 percent of the payment.
In no event shall the total retention proceeds withheld exceed 5
percent of the contract price. In a contract between the original
contractor and a subcontractor, and in a contract between a
subcontractor and any subcontractor thereunder, the percentage of the
retention proceeds withheld shall not exceed the percentage
specified in the contract between the public entity and the original
contractor. 
   (2) This subdivision shall not apply if the contractor provides
written notice to the subcontractor, prior to or at the time that the
bid is requested, that a bond may be required and the subcontractor
subsequently is unable or refuses to furnish to the contractor a
performance or payment bond issued by an admitted surety insurer.
 
   (2) This subdivision shall not apply if the contractor provides
written notice to the subcontractor, pursuant to subdivision (c) of
Section 4108, prior to, or at, the time that the bid is requested,
that bonds may be required, and the subcontractor subsequently is
unable or refuses to furnish to the contractor a performance and
payment bond issued by an admitted surety insurer. 
   (c) A party identified in subdivision (a) shall not require any
other party to waive any provision of this section. 
   (d) This section shall remain in effect only until January 1,
2014, and as of that date is repealed. 
   SEC. 2.   SEC. 4.   Section 10261 of the
Public Contract Code is amended to read:
   10261.   (a)    Payments upon contracts shall be
made as the department prescribes upon estimates made and approved
by the department, but progress payments shall not be made in excess
of 95 percent of the percentage of actual work completed plus a like
percentage of the value of material delivered on the ground or stored
subject to or under the control of the state, and unused, except as
otherwise provided in this section. The department shall withhold not
more than 5 percent of the contract price until final completion and
acceptance of the project. However, at any time after  95
  100  percent of the work has been completed, the
department may reduce the funds withheld to an amount not less than
125 percent of the estimated value of the work yet to be completed,
as determined by the department, if the reduction has been approved,
in writing, by the surety on the performance bond and by the surety
on the payment bond. The Controller shall draw his or her warrants
upon estimates so made and approved by the department and the
Treasurer shall pay them. The funds may be released by electronic
transfer if that procedure is requested by the contractor, in
writing, and if the public entity has, in place at the time of the
request, the mechanism for the transfer. 
   (b) This section shall remain in effect only until December 31,
2013, and as of January 1, 2014 is repealed. 
   SEC. 5.    Section 10261 is added to the 
Public Contract Code   , to read:  
   10261.  (a) On and after January 1, 2014, payments upon contracts
shall be made as the department prescribes upon estimates made and
approved by the department, but progress payments shall not be made
in excess of 95 percent of the percentage of actual work completed
plus a like percentage of the value of material delivered on the
ground or stored subject to or under the control of the state, and
unused, except as otherwise provided in this section. The department
shall withhold not less than 5 percent of the contract price until
final completion and acceptance of the project. However, at any time
after 95 percent of the work has been completed, the department may
reduce the funds withheld to an amount not less than 125 percent of
the estimated value of the work yet to be completed, as determined by
the department, if the reduction has been approved, in writing, by
the surety on the performance bond and by the surety on the payment
bond. The Controller shall draw his or her warrants upon estimates so
made and approved by the department and the Treasurer shall pay
them. The funds may be released by electronic transfer if that
procedure is requested by the contractor, in writing, and if the
public entity has, in place at the time of the request, the mechanism
for the transfer.
   (b) This section shall take effect on January 1, 2014. 
   SEC. 6.    Section 10262 of the   Public
Contract Code   is amended to read: 
   10262.  The contractor shall pay to his or her subcontractors,
within  10   seven  days of receipt of each
progress payment, the respective amounts allowed the contractor on
account of the work performed by his or her subcontractors, to the
extent of each subcontractor's interest therein. The payments to
subcontractors shall be based on estimates made pursuant to Section
10261. Any diversion by the contractor of payments received for
prosecution of a contract, or failure to reasonably account for the
application or use of the payments constitutes ground for actions
proscribed in Section 10253, in addition to disciplinary action by
the Contractors' State License Board. The subcontractor shall notify,
in writing, the Contractors' State License Board and the department
of any payment less than the amount or percentage approved for the
class or item of work as set forth in Section 10261.
   SEC. 7.    Section 10262.5 of the   Public
Contract Code   is amended to read: 
   10262.5.  (a) Notwithstanding any other  provision of
 law, a prime contractor or subcontractor shall pay to any
subcontractor, not later than  10   seven 
days of receipt of each progress payment, the respective amounts
allowed the contractor on account of the work performed by the
subcontractors, to the extent of each subcontractor's interest
therein. In the event that there is a good faith dispute over all or
any portion of the amount due on a progress payment from the prime
contractor or subcontractor to a subcontractor, then the prime
contractor or subcontractor may withhold no more than 150 percent of
the disputed amount.
   Any contractor who violates this section shall pay to the
subcontractor a penalty of 2 percent of the amount due per month for
every month that payment is not made. In any action for the
collection of funds wrongfully withheld, the prevailing party shall
be entitled to his or her attorney's fees and costs.
   (b) This section shall not be construed to limit or impair any
contractual, administrative, or judicial remedies otherwise available
to a contractor or a subcontractor in the event of a dispute
involving late payment or nonpayment by a contractor or deficient
subcontract performance or nonperformance by a subcontractor.
   (c) On or before September 1 of each year, the head of each state
agency shall submit to the Legislature a report on the number and
dollar volume of written complaints received from subcontractors and
prime contractors on contracts in excess of three hundred thousand
dollars ($300,000), relating to violations of this section.