BILL ANALYSIS                                                                                                                                                                                                    



                                                                  SB 837
                                                                  Page  1

           REPLACE  - 08/26/10 Changes per consultant.
          
          SENATE THIRD READING
          SB 837 (Florez)
          As Amended  August 20, 2010
          Majority vote

           SENATE VOTE  :   Vote not relevant
           
           UTILITIES & COMMERCE            APPROPRIATIONS                  
                    (vote not relevant)           (vote not relevant)

          SUMMARY  authorizes the Corcoran District Hospital, upon approval  
          of the board of directors of the hospital, to use a design-build  
          procedure when assigning contracts to the construction of a  
          building or improvements directly related to the construction of  
          an outpatient facility building at the hospital.  

           EXISTING LAW  :

          1)Requires local officials, under the Local Agency Public  
            Construction Act, to invite bids 
          for construction projects and then award contracts to the lowest  
            responsible bidder under the traditional design-build project  
            delivery system.

          2)Defines "design-build" as a procurement process in which both  
            the design and construction of a project are procured from a  
            single entity.

          3)Defines "best-value" as a value determined by objective  
            criteria related to price, features, functions, and life cycle  
            costs.

          4)Defines "project" as the construction of a building and  
            improvements directly related to the construction of a  
            building, and specifies that construction of other  
            infrastructure, including, but not limited to, streets and  
            highways, public rail transit, or water resources facilities  
            and infrastructure are not to be considered "projects."

          5)Authorizes counties to use the design-build method for  
            projects costing more than 
          $2.5 million.  









                                                                  SB 837
                                                                  Page  2

          6)Authorizes cities to use the design-build method for projects  
            costing more than $1 million.

          7)Authorizes the Sonoma Valley Health Care District to use  
            design-build contracting for the construction of buildings and  
            improvements in excess of $2.5 million directly related to a  
            hospital or health facility building, which is required to be  
            reviewed and inspected according to the standards of the  
            Alfred E. Alquist Hospital Facilities Seismic Safety Act of  
            1983.

          8)Authorizes the Orange County Sanitation District to use  
            design-build contracting for projects, including, but not  
            limited to, public wastewater facilities, in excess of $6  
            million.

          9)Authorizes the Santa Clara Valley Water District to use  
            design-build contracting for building contracts.
          10)Authorizes redevelopment agencies to use design-build  
            contracting for 10 public improvement projects in excess of $1  
            million subject to approval by the State Public Works Board.

          11)Requires local officials to prepare documents describing the  
            project and its specifications; 
          to prepare a detailed request for proposals that invites  
            competitive bids; to establish a detailed procedure to  
            pre-qualify design-build entities; and, to establish the  
            procedures to select the design-build entity.

          12)Requires the legislative body to establish and enforce labor  
            compliance programs.

          13)Requires local officials to collect specified types of  
            information when pre-qualifying design-build entities.

          14)Requires a prospective design-build entity to list its  
            proposed mechanical subcontractors and licenses; report past  
            worker safety violations, contracting problems, contract  
            defaults, license violations, payroll violations, and  
            bankruptcies; and, verify this information under oath.

          15)Requires local officials to select the design-build entity by  
            using either a competitive bidding process in which the award  
            goes to the lowest responsible bidder or a best value  
            competition in which local officials set the criteria.








                                                                  SB 837
                                                                  Page  3


          16)Requires that price, expertise, life cycle costs, skilled  
            labor force availability, and safety records account for at  
            least 10% each of the total weight of consideration of all  
            best value factors.

          17)Requires the local agency to rank the top three responsive  
            bidders; award the contract to the responsible bidder whose  
            proposal county or city officials rank as "the most  
            advantageous;" and, identify the second- and third-ranked  
            bidders after it publicly announces the award.

          18)Requires that skilled labor force availability be determined  
            by the existence of an agreement with a registered and  
            approved apprenticeship program.

          19)Requires the winning design-build entity to be bonded and  
            carry errors-and-omissions insurance to cover its design and  
            architectural services.

          20)Requires the entity to adhere to the local agency's  
            performance criteria and design standards and obtain the local  
            agency's written consent for any deviations from these  
            standards, and authorizes the local agency to hire a design  
            professional to ensure compliance.

          21)Authorizes the winning design-build entity to use  
            subcontractors not listed in its original bid, but requires  
            the entity to award these subcontracts by following a process  
            set by the local agency, including publishing notices and  
            setting deadlines.

          22)Permits the local agency to retain no more than 5% of the  
            contract if the local agency's bid request required the  
            design-build entity to carry a performance and payment bond.

          23)Requires any local agency that uses design-build contracting  
            to submit a report to the Legislative Analyst's Office (LAO)  
            containing specified information that includes, but is not  
            limited to, a description of the Labor Force Compliance  
            Program and an assessment of the project impact of "skilled  
            labor force availability."

          24)Repeals the authorization for counties, the Orange County  
            Sanitation District, the Santa Clara Valley Water District,  








                                                                  SB 837
                                                                  Page  4

            and the Sonoma Valley Health Care District to use design-build  
            contracts on January 1, 2011.  

          25)Repeals the authorization for cities and redevelopment  
            agencies to use design-build contracts on January 1, 2016.

           FISCAL EFFECT  :  None

           COMMENTS  :  The Local Agency Public Construction Act requires  
          local officials to invite bids for construction projects and  
          then award contracts to the lowest responsible bidder.  This  
          design-bid-build method is the traditional approach to public  
          works construction.

          Private companies often use the design-build method for  
          construction projects.  Under the design-build method, a single  
          contract covers the design and construction of a project with a  
          single company or consortium that acts as both the project  
          designer and builder.  The design-build entity arranges all  
          architectural, engineering, and construction services, and is  
          responsible for delivering the project at a guaranteed price and  
          schedule based upon performance criteria set by the public  
          agency.  The design-build method can be set by the public  
          agency.  The design-build method can be faster, and therefore,  
          cheaper, than the design-bid-build method, but it requires a  
          higher level of management sophistication since design and  
          construction may occur simultaneously.

          Advocates for the design-build method of contracting for public  
          works contend that project schedule savings can be realized  
          because only a single request for proposals is needed to select  
          the project's designer and builder.  The more traditional  
          design-bid-build project approach requires the separate  
          selection of the design consultant or contractor, completion 
          of design, and then advertising for bids and selection of the  
          construction contractor.  Proponents add that design-build  
          allows the overlap of design and construction activities,  
          resulting in additional time savings and lower project costs.   
          By avoiding the delays and change orders that result from the  
          traditional design-bid-build method of contracting, proponents  
          argue that officials can deliver public works faster and  
          cheaper.

          The design-build language in current law is based on a  
          compromise struck in 2000 among local officials, labor groups,  








                                                                  SB 837
                                                                  Page  5

          and contractors.  Local officials wanted the flexibility and  
          potential cost savings offered by design-build contracts.  Labor  
          unions wanted to ensure that counties pre-qualify employers to  
          protect workers' interests.  Contractors wanted to be sure they  
          had fair access to county contracts.  Further changes to the  
          language, consistent with the principles of the 2000 compromise  
          were made by SB 287 (Cox), Chapter 376, Statutes of 2005; SB 416  
          (Ashburn), Chapter 585, Statutes 2007, which extended this  
          authority to use design-build contracting for the construction  
          of buildings and directly related improvements to all 58  
          counties in the state; AB 642 (Wolk), Chapter 314, Statues 2008,  
          which extended this authority to use design-build contracting  
          for the construction of buildings and directly related  
          improvements to all cities in the state; SB 1699 (Wiggins),  
          Chapter 415, Statutes of 2008, which extended this authority to  
          use design-build contracting for the construction of buildings  
          and improvements in excess of $2.5 million directly related to a  
          Sonoma Valley Health Care District hospital or health facility  
          building; and, SB 4xx (Cogdill), Chapter 2, Statutes of 2009,  
          which extended this authority to use design-build contracting  
          for 10 redevelopment projects in excess of $1 million subject to  
          approval by the State Public Works Board.

          The LAO issued a report to the Legislature on February 3, 2005,  
          titled "Design-Build: An Alternative Construction System."   
          After analyzing the claims of proponents and opponents and  
          reviewing the experience of counties that were authorized to use  
          design-build at the time, LAO recommended "the Legislature grant  
          design-build authority only to buildings and directly related  
          infrastructure.  There are more complex issues associated with  
          other public works projects such as transportation, public  
          transit, and water resources facilities.  Evaluation of  
          design-build as a construction delivery option for these other  
          infrastructure facilities is beyond the scope of this report."

          California currently has 80 health care districts.  Health care  
          districts were known as hospital districts prior to 1994.   
          Health care districts are formed to "establish, maintain, and  
          operate health care facilities," including, but not limited to,  
          hospitals.  Health care districts are governed by elected boards  
          of directors.  Health care districts throughout the state need  
          to retrofit existing buildings or build new facilities in order  
          to comply with the state's seismic safety law.  These districts  
          are faced with escalating construction costs and are looking for  
          the most cost-efficient ways to meet seismic standards and  








                                                                 SB 837
                                                                  Page  6

          provide well-designed and built state-of-the-art facilities to  
          provide health care to the people of the state.  One of these is  
          design-build contracting.

          This bill extends the design-build authorization currently  
          granted to the Sonoma Valley Health Care District to the  
          Corcoran District Hospital.  Because this authorization only  
          extends to the construction of buildings, it does not exceed the  
          scope recommended by the LAO report.

          Support arguments:  Supporters believe that district hospitals  
          are the only hospitals, both private and public, without this  
          authority.  Supporters believe that the design build process, if  
          used by district hospitals, would help hold down the cost of  
          seismic safety construction and expedite the design and  
          construction process which would save taxpayers money. 

          Opposition arguments:  Opposition may argue that design build is  
          not suited for constructing hospitals. Due to the complexity of  
          hospital capitol outlay projects - such as health monitoring  
          systems and life support functions - the traditional competitive  
          bidding process is better designed to take into account the very  
          specific needs of emergency medical personnel, doctors, and  
          support staff.


           Analysis Prepared by  :    Jennifer R. Klein / L. GOV. / (916)  
          319-3958 


                                                               FN:  0006575