BILL ANALYSIS                                                                                                                                                                                                    



                                                                       



           ------------------------------------------------------------ 
          |SENATE RULES COMMITTEE            |                   SB 879|
          |Office of Senate Floor Analyses   |                         |
          |1020 N Street, Suite 524          |                         |
          |(916) 651-1520         Fax: (916) |                         |
          |327-4478                          |                         |
           ------------------------------------------------------------ 
           
                                         
                              UNFINISHED BUSINESS


          Bill No:  SB 879
          Author:   Cox (R)
          Amended:  8/16/10
          Vote:     21

           
           SENATE LOCAL GOVERNMENT COMMITTEE  :  3-2, 4/19/10
          AYES:  Cox, Aanestad, Kehoe
          NOES:  DeSaulnier, Price

           SENATE APPROPRIATIONS COMMITTEE  :  6-3, 5/10/10
          AYES:  Kehoe, Cox, Alquist, Walters, Wolk, Wyland
          NOES:  Leno, Price, Yee
          NO VOTE RECORDED:  Corbett, Denham

           SENATE FLOOR  :  24-8, 6/1/10
          AYES:  Aanestad, Alquist, Ashburn, Cogdill, Correa, Cox,  
            Denham, Ducheny, Dutton, Florez, Harman, Hollingsworth,  
            Huff, Kehoe, Liu, Lowenthal, Price, Runner, Simitian,  
            Steinberg, Strickland, Wolk, Wright, Wyland
          NOES:  Calderon, Cedillo, Corbett, DeSaulnier, Hancock,  
            Leno, Pavley, Yee
          NO VOTE RECORDED:  Negrete McLeod, Oropeza, Padilla,  
            Romero, Walters, Wiggins, Vacancy, Vacancy

           ASSEMBLY FLOOR  :  62-6, 8/18/10 - See last page for vote


           SUBJECT  :    Construction projects:  alternative bidding  
          procedures: 
                      design-build

           SOURCE  :     Author
                                                           CONTINUED





                                                                SB 879
                                                                Page  
          2



           DIGEST :    This bill extends the sunset for the use of  
          design-build by counties from January 1, 2011, to July 1,  
          2014, and aligns the design-build statutes for cities and  
          counties. 

           Assembly Amendments  delete the language to lower the  
          threshold for counties from $2.5 million to $1 million,  
          change the reporting deadline from December 1, 2014 to  
          September 1, 2013 for each county that uses design-build  
          method to submit to the Legislative Analyst's Office (LAO),  
          reduce the extended sunset date from January 1, 2016 to  
          July 1, 2014, and add a requirement that the LAO submit a  
          report to the Legislature by January 1, 2014.

           ANALYSIS  :    The Local Agency Public Construction (LAPC)  
          Act requires local officials to invite bids for  
          construction projects and then award contracts to the  
          lowest responsible bidder.  This design-bid-build method is  
          the traditional approach to public works construction.  By  
          contrast, the design-build method allows local officials to  
          procure both design and construction services from a single  
          company before the development of complete plans and  
          specifications.

          Counties can use the design-build method for projects worth  
          more than $2.5 million.  The counties' authority sunsets on  
          January 1, 2011 (SB 416 [Ashburn], Chapter 585, Statutes of  
          2007).  Cities can use the design-build method on projects  
          worth more than $1 million.  The cities' design-build  
          statute sunsets on January 1, 2016 (AB 642 [Wolk], Chapter  
          314, Statutes of 2008).

          This bill extends the sunset for the use of design-build by  
          counties from January 1, 2011, to July 1, 2014, and aligns  
          the design-build statutes for cities and counties.   
          Specifically, this bill:

          1. Requires the design-build standard questionnaire issued  
             by cities or counties to include any instance in which  
             the entity, or any of its members, owners, officers, or  
             managing employees was, during the five years preceding  
             submission of a bid pursuant to this section, determined  







                                                                SB 879
                                                                Page  
          3

             by a court of competent jurisdiction to have submitted,  
             or legally admitted for purposes of a criminal plea to  
             have submitted any claim in violation of the federal  
             False Claims Act or the state False Claims Act. 

          2. Requires for city and county design-build projects,  
             lists of subcontractors, bidders, and bid awards  
             relating to the project to be submitted by the  
             design-build entity to the awarding body within 14 days  
             of the award. These documents are deemed to be public  
             records and are required to be available for public  
             inspection pursuant to this chapter and the Public  
             Records Act. 

          3. Removes the requirement that certain specified minimum  
             factors be weighted equally when cities are evaluating  
             competitive proposals. 

          4. Requires each county that uses the design-build method  
             on a public works project to submit to the LAO before  
             September 1, 2013, a report containing a description of  
             each public works project procured through the  
             design-build process and completed after November 1,  
             2009, and before August 1, 2013. 

          5. Requires a county to also include in its report to the  
             LAO information on whether the project was met or  
             altered and the number and amount of the project change  
             orders. 

          6. Requires the LAO, by January 1, 2014, to do another  
             report to the Legislature on a fact based analysis on  
             the use of design-build at the county level. 

          7. Requires the LAO to complete a fact-based analysis on  
             the use of design-build method by counties, utilizing  
             the information provided and any independent information  
             provided by the public or interested parties. 

          8. Requires the LAO to select a representative sample of  
             projects and review available public records and  
             reports, media reports, and related information in its  
             analysis. 








                                                                SB 879
                                                                Page  
          4

          9. Requires the LAO to compile the information to be  
             analyzed in a report which shall be submitted to the  
             Legislature. 

          10.Requires the report to include conclusions describing  
             the actual cost of projects procured through the  
             design-build method, whether the project schedule was  
             met or altered, and whether projects needed or used  
             project change orders. 

          11.Requires cities that elect to use design-build to report  
             to the LAO the estimated and actual length of time to  
             complete the project. 

           Comments  

          The LAPC Act requires local officials to invite bids for  
          construction projects and then award contracts to the  
          lowest responsible bidder.  This design-bid-build method is  
          the traditional approach to public works construction. 
          Private companies often use the design-build method for  
          construction projects.  Under the design-build method, a  
          single contract covers the design and construction of a  
          project with a single company or consortium that acts as  
          both the project designer and builder.  The design-build  
          entity arranges all architectural, engineering, and  
          construction services, and is responsible for delivering  
          the project at a guaranteed price and schedule based upon  
          performance criteria set by the public agency.  The  
          design-build method can be set by the public agency.  The  
          design-build method can be faster, and therefore, cheaper,  
          than the design-bid-build method, but it requires a higher  
          level of management sophistication since design and  
          construction may occur simultaneously. 

          Advocates for the design-build method of contracting for  
          public works contend that project schedule savings can be  
          realized because only a single request for proposals is  
          needed to select the project's designer and builder. The  
          more traditional design-bid-build project approach requires  
          the separate selection of the design consultant or  
          contractor, completion of design, and then advertising for  
          bids and selection of the construction contractor.  
          Proponents add that design-build allows the overlap of  







                                                                SB 879
                                                                Page  
          5

          design and construction activities, resulting in additional  
          time savings and lower project costs. By avoiding the  
          delays and change orders that result from the traditional  
          design-bid-build method of contracting, proponents argue  
          that officials can deliver public works faster and cheaper.  


          The design-build language in current law is based on a  
          compromise struck in 2000 among local officials, labor  
          groups, and contractors.  Local officials wanted the  
          flexibility and potential cost savings offered by  
          design-build contracts. Labor unions wanted to ensure that  
          counties pre-qualify employers to protect workers'  
          interests.  Contractors wanted to be sure they had fair  
          access to county contracts.  Further changes to the  
          language, consistent with the principles of the 2000  
          compromise were made by SB 287 (Cox), Chapter 376, Statutes  
          of 2005; SB 416 (Ashburn), Chapter 585, Statutes 2007,  
          which extended this authority to use design-build  
          contracting for the construction of buildings and directly  
          related improvements to all 58 counties in the state; AB  
          642 (Wolk), Chapter 314, Statues 2008, which extended this  
          authority to use design-build contracting for the  
          construction of buildings and directly related improvements  
          to all cities in the state; and, SB 1699 (Wiggins), Chapter  
          415, Statutes of 2008, which extended this authority to use  
          design-build contracting for the construction of buildings  
          and improvements in excess of $2.5 million directly related  
          to a Sonoma Valley Health Care District hospital or health  
          facility building.  The LAO issued a report to the  
          Legislature on February 3, 2005, titled "Design-Build: An  
          Alternative Construction System." After analyzing the  
          claims of proponents and opponents and reviewing the  
          experience of counties that were authorized to use  
          design-build at the time, LAO recommended "the Legislature  
          grant design-build authority only to buildings and directly  
          related infrastructure.  There are more complex issues  
          associated with other public works projects such as  
          transportation, public transit, and water resources  
          facilities.  Evaluation of design-build as a construction  
          delivery option for these other infrastructure facilities  
          is beyond the scope of this report." 

          In January of this year the LAO issued a second report,  







                                                                SB 879
                                                                Page  
          6

          this time updating the Legislature on the use of  
          design-build by counties in California, based on data  
          received from counties who utilized this methodology.  In  
          the report, LAO states that "although it was difficult to  
          draw conclusions from the reports received about the  
          effectiveness of design-build compared to other project  
          delivery methods, we do not think that the reports provide  
          any evidence that would discourage the Legislature from  
          granting design-build authority to local agencies on an  
          ongoing basis.  In doing so, however, we recommend the  
          Legislature consider some changes such as creating uniform  
          design-build statute, eliminating cost limitations, and  
          requiring project cost to be a larger factor in awarding  
          the design-build contract." 

           FISCAL EFFECT  :    Appropriation:  Yes   Fiscal Com.:  Yes    
          Local:  No

          According to the Assembly Appropriations Committee: 

          1. Unknown, probably minor costs to LAO to conduct review  
             and analyze public documents associated with sample of  
             design-build projects used by counties. 

          2. Minor and absorbable costs to the Department of  
             Industrial Relations, which is responsible for enforcing  
             prevailing wage and related labor compliance programs  
             associated with design-build contracts. 

          3. Potential fiscal benefits to counties, to the extent  
             that use of design-build contracting results in faster  
             project and/or greater certainty about costs. 

           SUPPORT  :   (Verified  8/18/10)

          American Institute of Architects, California Council
          California Chamber of Commerce
          California Special Districts Association
          California State Association of Counties
          California State Sheriff's Association
          CH2M HILL
          Counties of Imperial, Orange, Sacramento, and San Diego 
          Design-Build Institute of America, Western Pacific Region
          Greater Riverside Chamber of Commerce







                                                                SB 879
                                                                Page  
          7

          Regional Council of Rural Counties
          Santa Clara Valley Water District
           

           ASSEMBLY FLOOR  : 
          AYES:  Adams, Ammiano, Arambula, Bass, Beall, Bill  
            Berryhill, Tom Berryhill, Block, Blumenfield, Buchanan,  
            Caballero, Carter, Chesbro, Conway, Cook, Coto, Davis, De  
            La Torre, De Leon, Eng, Feuer, Fletcher, Fuentes,  
            Galgiani, Garrick, Gatto, Gilmore, Hagman, Hall, Harkey,  
            Hayashi, Hernandez, Hill, Huber, Huffman, Jones, Knight,  
            Lieu, Bonnie Lowenthal, Ma, Mendoza, Miller, Monning,  
            Nestande, Niello, Nielsen, Norby, V. Manuel Perez,  
            Portantino, Ruskin, Salas, Saldana, Silva, Smyth,  
            Solorio, Audra Strickland, Torlakson, Torres, Torrico,  
            Tran, Villines, John A. Perez
          NOES:  Anderson, Bradford, DeVore, Gaines, Skinner, Swanson
          NO VOTE RECORDED:  Blakeslee, Brownley, Charles Calderon,  
            Evans, Fong, Fuller, Furutani, Jeffries, Logue, Nava,  
            Yamada, Vacancy


          AGB:mw  8/18/10   Senate Floor Analyses 

                         SUPPORT/OPPOSITION:  SEE ABOVE

                                ****  END  ****