BILL ANALYSIS                                                                                                                                                                                                    �




                   Senate Appropriations Committee Fiscal Summary
                           Senator Christine Kehoe, Chair

                                          AB 294 (Portantino)
          
          Hearing Date: 07/11/2011        Amended: 05/27/2011
          Consultant: Mark McKenzie       Policy Vote: T&H 7-0
          _________________________________________________________________
          ____
          BILL SUMMARY: AB 294 would authorize the Department of 
          Transportation (Caltrans) to use the design-sequencing method of 
          procurement for up to five transportation projects until January 
          1, 2015.
          _________________________________________________________________
          ____
                            Fiscal Impact (in thousands)

           Major Provisions         2011-12      2012-13       2013-14     Fund
           Project delivery impactunknown costs related to using 
          design-Special*
                                 sequencing rather than design-bid-build,
                                 potentially offset by savings from 
          accelerated 
                                 schedule (see staff comments)
          ____________
          *State Highway Account
          _________________________________________________________________
          ____

          STAFF COMMENTS: This bill meets the criteria for referral to the 
          Suspense File.
          
          The vast majority of Caltrans-administered projects are 
          implemented using the traditional design-bid-build approach, 
          whereby complete plans and specifications are prepared prior to 
          the advertising, bidding, and awarding of any construction 
          contracts.  Design-sequencing enables the staging of design 
          activities to permit each construction phase to commence when 
          design for that phase is complete, instead of requiring the 
          entire project design to be complete before construction starts. 
           The contract for the entire project is awarded to one 
          contractor with a minimum of 30 percent complete plans.  The 
          remainder of the design is delivered to the contractor by 
          predetermined dates after start of construction.  
          Design-sequencing is intended to provide an opportunity for 
          efficiencies by allowing collaboration between the contractor 








          AB 294 (Portantino)
          Page 1


          and designers to improve and expedite project delivery.

          Previous legislation authorized Caltrans to undertake a 
          two-phase design-sequencing pilot program.  Phase I of the 
          program, authorized by AB 405 (Knox), Chapter 378 of 1999 and AB 
          2607 (Knox), Chapter 340 of 2000, included 12 projects, 10 of 
          which were awarded.  SB 1210 (Torlakson), Chapter 795 of 2004, 
          established Phase II of the pilot program, authorizing 12 
          additional projects until January 1, 2010.  Eight contracts were 
          awarded under the Phase II pilot program.  Final reports have 
          yet to be issued on either Phase I or Phase II of the pilot 
          program.

          AB 294 would re-enact the design-sequencing program by 
          authorizing Caltrans to use the procurement method for up to 
          five additional projects until January 1, 2015.  The bill would 
          also require Caltrans to compile specified project data on any 
          contracts awarded as a result of this authority and include the 
          information in any annual status reports required as a part of 
          the design-sequencing pilot program.

          Based on Caltrans' tenth annual interim report on the pilot 
          program, reflecting activities through March 31, 2010, results 
          thus far have been relatively mixed.  A preliminary analysis of 
          all completed projects in Phase I, representing $872 million in 
          capital construction costs, indicates the following results thus 
          far:
           The impact on completion times ranged from 14 months delay to 
            18 months saved with an average minimal time savings of less 
            than one month.  Some of the delays cannot be attributable to 
            the use of design-sequencing.
           Two of the ten projects experienced significant cost growth of 
            51% and 70% respectively.
           There was no significant increase or decrease in support costs 
            on closed out design-sequencing projects.

          Staff notes that a final analysis of whether design-sequencing 
          costs more or less than traditional delivery methods will not be 
          available until the final project of Phase I is closed out and 
          final capital costs are analyzed and compared to initial 
          estimates, a control set of projects, and program wide data.

          Only one of the eight projects selected for Phase II of the 
          pilot program has been completed to date, with a time savings of 








          AB 294 (Portantino)
          Page 2


          one month.  While the project was originally projected to 
          achieve 12 months in time savings, the project experienced 
          delays that were unrelated to the design-sequencing method.  
          Caltrans acknowledges the relatively mixed results of the pilot 
          program to date, including cost escalations on some projects, 
          but indicates that the time savings alone can result in cost 
          savings as a result of construction cost escalation avoidance.  
          Furthermore, Caltrans indicates that lessons learned from Phase 
          I have resulted in the adoption of procedures to assess which 
          projects are best suited for design-sequencing, and the 
          implementation of numerous changes that will yield greater time 
          savings in Phase II.  Staff notes that due to increased 
          competition in the construction markets as a result in the 
          economic downturn, construction costs have been lower than 
          expected in recent years, so there would be no near-term cost 
          escalation avoidance benefits achieved by shorter project 
          delivery times.  Caltrans believes, however, that 
          design-sequencing provides the benefit of advertising bids at 
          30% plan completion which would allow the department to take 
          advantage of the current lower construction costs by soliciting 
          bids sooner than traditional design-bid-build.

          This bill would re-authorize the use of design-sequencing for a 
          limited period and number of projects to provide Caltrans with 
          the ability to continue using this procurement method until 
          final reports are issued that provide a full assessment of the 
          pilot program.  Caltrans estimates that the final report on 
          Phase I projects will be completed this year.  To date, only one 
          project from Phase II has been completed, and a final report 
          won't be issued until at least 2013-14.  The Committee may wish 
          to consider whether the program should be re-authorized prior to 
          the issuance of final reports that fully evaluate any benefits 
          and shortcomings related to design-sequencing.

          Staff notes that this bill is nearly identical to AB 1760 
          (Blumenfield), which was vetoed by Governor Schwarzenegger last 
          year with the following message:

               I am not convinced of the overall effectiveness of the 
               design-sequencing contracting method.  Upon the completion 
               of previously authorized design-sequencing contracts, the 
               California Department of Transportation will analyze this 
               contracting method and produce a final report on the 
               effectiveness of this method.  I believe any further 








          AB 294 (Portantino)
          Page 3


               authorizations of this contracting method should wait until 
               this report has been released and the effectiveness 
               determined.