BILL ANALYSIS �
AB 512
Page 1
Date of Hearing: May 4, 2011
ASSEMBLY COMMITTEE ON APPROPRIATIONS
Felipe Fuentes, Chair
AB 512 (Gordon) - As Introduced: February 15, 2011
Policy Committee:
UtilitiesVote:15-0
Urgency: 15-0 State Mandated Local Program:
No Reimbursable:
SUMMARY
This bill increases, from one megawatt (MW) to five MWs, the
capacity of a renewable energy powerplant eligible for an
existing program allowing a municipality to generate excess
electricity at one site owned by the municipality in order to
offset usage at another municipal-owned site.
FISCAL EFFECT
Negligible fiscal impact to the PUC.
COMMENTS
1)Background . AB 2466 (Laird)/Chapter 540 of 2008 allowed a
local governmental entity to locate a small renewable
electricity generating facility (up to 1 MW) in one location
and have the utility credit the output of that facility
against electricity the local government consumes at another
location. (A 1 MW generation facility can serve about 750
single-family homes.) The intent was to allow government
entities that had many different electricity meters (and thus
many accounts with a utility) to produce renewable power at a
location where they had very little demand, and then to use
the electricity to benefit another of the entity's buildings
with high demand but an unsuitable site for renewable
generation. For example, a city could locate solar panels over
a remote parking lot, and use the solar-generated electricity
to benefit city hall. AB 1031 (Blumenfield)/Chapter 380 of
2009, expanded program eligibility to include public college
and university campuses.
AB 512
Page 2
2)Purpose . According to the author, this bill is intended to
implement a recommendation from a November 2010 report of the
Assembly Select Committee on California's Green Economy, which
noted that the City of Fresno and other local governments have
expressed frustration with the limitations placed on their
ability to produce their own renewable energy. In particular,
the City of Fresno considered generating more of their own
energy through renewable projects, but determined they were
not feasible due to the current 1 MW limit. The report
recommended increasing the allowable limit to 5 MW.
According to PG&E, no entity has used the AB 2466 program,
which was established with the 1 MW capacity cap as a trial to
determine if the distribution system could handle large surges
in electricity coming from facilities onto wires that were
only intended to serve one-way electricity deliveries.
Analysis Prepared by : Chuck Nicol / APPR. / (916) 319-2081