BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 1073
                                                                  Page  1

          CONCURRENCE  IN SENATE AMENDMENTS
          Date of Hearing:   May 7, 2012

                       ASSEMBLY COMMITTEE ON NATURAL RESOURCES
                                 Wes Chesbro, Chair
                  AB 1073 (Fuentes) - As Amended:  February 23, 2012

           ----------------------------------------------------------------- 
          |ASSEMBLY:  |     |(May 19, 2011)  |SENATE: |28-2 |(March 26,     |
          |           |     |                |        |     |2012)          |
           ----------------------------------------------------------------- 
                    (vote not relevant)
           
           Original Committee Reference:   U. & C.  

           SUBJECT  :  Energy:  solar thermal powerplants:  conversion to 
          solar photovoltaic technology

           SUMMARY  :  Permits the proposed Calico solar project in San 
          Bernardino County, which was approved by the California Energy 
          Commission (CEC) in 2010 as a solar thermal project, to re-file 
          for approval by the CEC as a photovoltaic (non-thermal) project, 
          rather than following the ordinary permitting process for 
          photovoltaic powerplants under current law �i.e., local and/or 
          state agency review under the California Environmental Quality 
          Act (CEQA)].

           EXISTING LAW  :

          1)Pursuant to the Warren-Alquist Act of 1974, grants the CEC 
            exclusive authority to license thermal powerplants 50 
            megawatts and larger (including related facilities such as 
            fuel supply lines, water pipelines and transmission lines that 
            tie the plant to the grid).  The CEC must consult with 
            specified agencies, including the Department of Fish and Game 
            (DFG), but the CEC may override any contrary state or local 
            decision.  The CEC process is a certified regulatory program 
            (determined by the Resources Secretary to be the functional 
            equivalent of CEQA), so the CEC is exempt from having to 
            prepare an environmental impact report.  Its certified 
            program, however, does require environmental analysis of the 
            project, including an analysis of alternatives and mitigation 
            measures to minimize any significant adverse effect the 
            project may have on the environment.  Judicial review of a CEC 
            power plant license decision is limited to the California 








                                                                  AB 1073
                                                                  Page  2

            Supreme Court.  The Act specifically excludes photovoltaic 
            (PV) facilities of any size from CEC jurisdiction.

          2)Pursuant to SB 226 (Simitian) of 2011: 

             a)   Permits a solar thermal powerplant approved by the CEC 
               and the federal government between 2007 and 2011 to 
               petition the CEC not later than June 30, 2012 to review an 
               amendment to convert the facility, in whole or in part, 
               from solar thermal technology to PV technology, without the 
               need to file an entirely new application, provided that the 
               CEC prepares supplemental environmental review 
               documentation, provides for public notice and comment on 
               the supplemental environmental review, and holds at least 
               one public hearing.

             b)   Requires the CEC to incorporate all feasible mitigation 
               measures identified by DFG and the State Water Resources 
               Control Board.

             c)   Requires the CEC to process the application as a 
               post-certification amendment to the existing application, 
               rather than as a new application for certification.

             d)   Provides that these provisions do not apply to any 
               project that was timely challenged in the California 
               Supreme Court under the Warren-Alquist Act's judicial 
               review procedures (i.e., the Calico solar project).

          3)Pursuant to SB1X 2 (Simitian) of 2011, requires investor-owned 
            utilities (IOUs), publicly-owned utilities (POUs) and certain 
            other retail sellers of electricity, in order to fulfill unmet 
            long-term resource needs, to procure eligible renewable energy 
            resources to meet the following portfolio targets:

             a)   20 percent on average from January 1, 2011 to December 
               31, 2013.

             b)   25 percent by December 31, 2016.

             c)   33 percent by December 31, 2020 and each year 
               thereafter.

          4)Pursuant to the California Endangered Species Act (CESA) of 
            1984, prohibits the take of any endangered or threatened 








                                                                  AB 1073
                                                                  Page  3

            species unless the take is authorized by DFG.  DFG may issue 
            an incidental take permit authorizing the take of endangered 
            or threatened species if certain conditions are met, including 
            that the take is incidental to an otherwise lawful activity, 
            and the impacts of the authorized take are minimized and fully 
            mitigated.  CESA requires applicants to ensure adequate 
            funding to implement mitigation measures, including for 
            monitoring.

          5)Pursuant to the Natural Community Conservation Planning (NCCP) 
            Act of 1991, authorizes DFG to permit the taking of any 
            covered species whose conservation and management is provided 
            for in a NCCP approved by DFG.

          6)Pursuant to SBX8 34 (Padilla) of 2010 and AB1X 13 (V. Manuel 
            Perez) of 2011, authorizes DFG, in consultation with the CEC, 
            to develop mitigation actions, including advance mitigation 
            and interim mitigation strategies, to fully mitigate the 
            impacts on endangered and threatened species of renewable 
            energy projects proposed for siting within the Desert 
            Renewable Energy Conservation Plan (DRECP) planning area.  
            Eligible project developers are authorized to meet their 
            mitigation obligations by voluntarily paying fees into a fund 
            to be used by DFG to complete the mitigation actions.

           THIS BILL  amends the section added by SB 226 to provide that a 
          project challenged in the California Supreme Court is eligible 
          if the challenge was subsequently dismissed, in effect removing 
          the exclusion of the Calico solar project.

           FISCAL EFFECT  :  According to the Senate Appropriations 
          Committee, likely one-time costs of at least $150,000 for 
          additional project application review due to project design 
          changes, from the Energy Resources Programs Account, which can 
          be used for General Fund purposes

           COMMENTS  :

           1)The DRECP is the template for addressing renewable 
            energy/species conflicts going forward.   The DRECP, which 
            covers renewable resource lands in the Mojave and Colorado 
            deserts, is intended to serve as a NCCP for development of 
            renewable energy projects in the California desert region.  As 
            such, lands designated for development and lands designated 
            for conservation purposes will be identified and dedicated to 








                                                                  AB 1073
                                                                  Page  4

            those purposes consistent with the terms of the NCCP Act and 
            other applicable provisions of law.  The DRECP will also serve 
            as the basis for one or more habitat conservation plans (HCPs) 
            under the Federal Endangered Species Act. 

            SBX8 34 and ABX1 13 permit solar, wind and geotherrmal energy 
            project developers to pay in-lieu fees that will be used by 
            DFG to acquire and restore habitat lands for species affected 
            by projects within the DRECP.  This provision is an 
            alternative to developers mitigating impacts on an individual, 
            per project basis.  This approach also allows DFG to 
            coordinate the mitigation and to avoid piecemeal mitigation.  
            Under SBX8 34, DFG received a loan of $10 million for this 
            purpose and was required to develop an interim mitigation 
            strategy that would establish conservation benchmarks for the 
            DRECP and to identify high priority lands that should be 
            acquired.

            To oversee the implementation of the DRECP, a Renewable Energy 
            Action Team (REAT) was formed consisting of the CEC, DFG, 
            Bureau of Land Management, and the U.S. Fish and Wildlife 
            Service.  Other REAT participants include the Public Utilities 
            Commission, California Independent System Operator, National 
            Parks Service, U.S. Environmental Protection Agency and the 
            Department of Defense. 

            Four major products are being developed under the direction of 
            the REAT: 

               a)     Best Management Practices and Guidance Manual for 
                 Desert Renewable Energy Projects.

               b)     Draft Conservation Strategy that clearly identifies 
                 and maps areas for renewable energy project development 
                 and areas intended for long-term natural resource 
                 conservation as a foundation for the DRECP.

               c)     The DRECP itself - a joint state and federal NCCP 
                 and part of one or more HCPs.

               d)     DRECP Draft and Final joint state and federal 
                 Environmental Impact Report/Environmental Impact 
                 Statement.

            The previous CEC review and approval of the Calico project 








                                                                  AB 1073
                                                                  Page  5

            predates the DRECP process.

           2)Solar economics and federal funding deadlines led to SB 226's 
            PV conversion provision.   Solar thermal generation uses 
            mirrors or lenses to concentrate sunlight, or solar thermal 
            energy, onto a small area.  Electrical power is produced when 
            the concentrated light is converted to heat, which drives a 
            heat engine (usually a steam turbine) connected to an 
            electrical power generator.  Since 2007 the CEC has received 
            project applications from developers of 16 solar thermal 
            plants collectively totaling over 5,700 MW of generation 
            primarily located in the Mojave and Colorado deserts.  
            However, as the siting process neared completion for some of 
            these projects, and in some instances after an application had 
            been certified by the CEC, market prices for solar PV dropped 
            so precipitously that some solar thermal project developers 
            desired to change technologies seeking a lower cost of power 
            generated from the plant.  
             
             The provision which is the subject of this bill (Public 
            Resources Code Section 25500.1) was added to SB 226 in 
            Assembly Appropriations Committee on September 8, 2011.  The 
            justification offered at the time for this provision was that 
            it would allow several non-controversial solar projects to 
            convert to PV in time to meet federal funding deadlines.  On 
            September 9, the last day of session, SB 226 passed the 
            Assembly and Senate, and was later signed by the Governor.  
            Section 25500.1 provides the CEC with limited jurisdiction 
            over PV projects which were filed after August 15, 2007 and 
            approved by the CEC and for projects on federal land where a 
            decision had been issued by the Bureau of Land Management 
            before September 1, 2011.  The one caveat was that a project 
            would not qualify for the exception if the project had been 
            challenged in court.  

            On September 9, Senator Simitian submitted the following 
            letter to the Senate Journal:

               Dear Mr. Schmidt:
                    I am submitting this letter to the Senate Journal to 
               provide clarity as to the intent of a provision in Senate 
               Bill 226 related to project challenges at the California 
               Energy Commission.
                    Senate Bill 226 adds Public Resources Code �25500.1, 
               relating to applications for certifications for projects at 








                                                                  AB 1073
                                                                  Page  6

               the California Energy Commission. It is not my intention 
               that subdivision (e) of this section be applicable to a 
               project whose certificate was challenged and subsequently 
               dismissed by the California Supreme Court.
                    Further, it is not my intent to abrogate any parties 
               rights to challenge a project's certificate pursuant to 
               �25531 or any other provision of law.
                    To the extent there is any ambiguity about the intent 
               of this provision, I will pursue clarity through additional 
               legislation at the earliest opportunity.
                    Sincerely,
                    S. JOSEPH SIMITIAN
                    Eleventh Senate District

            According to the CEC, one eligible solar project has indicated 
            interest, but no project has petitioned the CEC to review a 
            PV-conversion amendment pursuant to SB 226.

           3)A brief history of the Calico project.   In December 2008, 
            Stirling Energy Systems applied to the CEC to construct and 
            operate the Solar One Project, a solar dish Stirling systems 
            project in San Bernardino County, California.  In January 
            2010, the project formally changed its name to the Calico 
            Solar Project. The applicant was re-named Calico Solar, which 
            was then a subsidiary of Tessera Solar.  
             
            As originally proposed, the Calico project was to be a 
            850-megawatt (MW) Stirling engine project.  The primary 
            equipment for the generating facility was to be approximately 
            30,000 25-kilowatt solar dish Stirling systems (referred to as 
            SunCatchers), their associated equipment and systems, and 
            their support infrastructure.  The original project was 
            planned on an approximate 8,230-acre site located in San 
            Bernardino County, approximately 37 miles east of Barstow.

            The Calico solar thermal project received its final approved 
            from CEC on December 1, 2010.  The CEC approval identified 
            numerous significant environmental effects and included 
            mitigation measures which, among other things, reduced the 
            project footprint.  During state and federal permitting, 
            Calico underwent successive rounds of project modifications in 
            response to agencies' and environmental groups' concerns.  The 
            original project site of 8,230 acres was reduced to 4,613 
            acres in a series of reductions intended to (1) minimize use 
            of donated lands; (2) create desert tortoise movement corridor 








                                                                  AB 1073
                                                                  Page  7

            along north and east of site, avoid concentrations of 
            sensitive plants, and avoid cultural resources; and (3) 
            minimize impacts on desert tortoise.  These area reductions 
            also reduced overall planned capacity from 850 MW to 663.5 MW.

            The original solar thermal developer entered a power purchase 
            agreement with Southern California Edison in 2005.  However, 
            Edison announced the cancelation of this contract on December 
            23, 2010, just three weeks after the project was approved by 
            the CEC.  On December 28, K Road Power announced acquisition 
            of the project from Tessera and plans to convert to PV.  And 
            on December 30, Sierra Club and California Unions for Reliable 
            Energy (CURE) filed separate lawsuits in the California 
            Supreme Court challenging the CEC's approval of the project.  
            On April 13, 2011, both petitions were denied by the Supreme 
            Court without a hearing.  As noted above, CEC powerplant 
            licenses are reviewable only by the Supreme Court.  The Court 
            has denied every petition for review.

            In June 2011, Calico and CURE announced they had reached an 
            agreement resolving the environmental issues raised by CURE in 
            the CEC process.  On August 5, 2011, CURE announced a 
            partnership with Calico, including a project labor agreement.  
            On March 26, 2012, Defenders of Wildlife, the Natural 
            Resources Defense Council and the Sierra Club filed a federal 
            lawsuit challenging BLM's approval of the Calico project.  The 
            environmental plaintiffs seek to move the project to a 
            location without major environmental conflicts.  This lawsuit 
            is pending, though it's so recent that the federal agencies 
            and other parties have not responded and no trial has been 
            set.

            The Calico project currently does not have a power purchase 
            agreement, federal funding or a definitive construction date.

           4)Impacts on threatened desert tortoise are chief among 
            environmental issues with desert solar projects in general, 
            and Calico project in particular.   The desert tortoise is the 
            state reptile of California (designated in 1972) and a 
            threatened species under state and federal endangered species 
            acts.  Ravens, gila monsters, Kit foxes, badgers, roadrunners, 
            coyotes and fire ants are all natural predators of the desert 
            tortoise.  They prey on eggs, juveniles, which are 2-3 inches 
            long with a thin, delicate shell, or in some cases adults.  
            Ravens are hypothesized to cause significant levels of 








                                                                  AB 1073
                                                                  Page  8

            juvenile tortoise predation in some areas of the Mojave Desert 
            - frequently near urbanized areas.  The most significant 
            threats to tortoises include urbanization, disease, habitat 
            destruction and fragmentation, illegal collection and 
            vandalism by humans, and habitat conversion from invasive 
            plant species.  Desert tortoise populations in some areas have 
            declined by as much as 90% since the 1980s and the Mojave 
            population is listed as threatened.  It is unlawful to touch, 
            harm, harass or collect wild desert tortoises.  

           5)Up or down.   This bill was substantially amended in the Senate 
            on February 23 and the Assembly-approved provisions of this 
            bill were deleted.  The bill has been referred to the Assembly 
            Natural Resources and Appropriations Committees to review the 
            Senate amendments, pursuant to Assembly Rule 77.2.  As the 
            bill is on concurrence, it cannot be amended in the Assembly.  
            The committee may recommend concurrence or non-concurrence in 
            the Senate amendments or to hold the bill in committee (Joint 
            Rule 26.5).  If the committee holds the bill, it is possible 
            to then withdraw the bill to the Senate for amendments or send 
            the bill to a conference committee to reconcile the Senate and 
            Assembly actions by joint action of the Assembly and Senate.
           
          REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          California Chamber of Commerce
          California State Association of Electrical Workers
          K Road Calico Solar
          Palm Desert Area Chamber of Commerce

           Opposition 
           
          Audubon California
          California Coastal Protection Network
          California League of Conservation Voters
          California Native Plant Society
          Center for Biological Diversity
          Defenders of Wildlife
          Kern County Board of Supervisors
          Natural Resources Defense Council
          Planning and Conservation League
          Sierra Club California
          The Nature Conservancy








                                                                  AB 1073
                                                                  Page  9

          The Wilderness Society
           

          Analysis Prepared by  :  Lawrence Lingbloom / NAT. RES. / (916) 
          319-2092