BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 1214
                                                                  Page  1

          Date of Hearing:   May 4, 2011

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Steven Bradford, Chair
                   AB 1214 (Skinner) - As Amended:  April 26, 2011
           
          SUBJECT  :   Electricity transmission, permitting

           SUMMARY  :   Requires the California Public Utilities Commission 
          to deem transmission projects necessary if the California 
          Integrated System Operator has determined a transmission 
          facility is needed.  Specifically,  this bill  :  

          Requires the California Integrated System Operator (CAISO) and 
          the California Public Utilities Commission (PUC) to jointly 
          evaluate transmission facilities that serve solar development 
          areas.

          Requires the PUC and CAISO to publish a report, no later than 
          March 31, 2012 to identify new and upgraded transmission 
          facilities that can be placed in service by December 31, 2016, 
          including identifying barriers to placing the facilities in 
          service by December 31, 2016 and the means to overcome those 
          barriers.

          Requires the PUC and the CAISO to coordinate the CAISO's 
          transmission planning process and identification of needed 
          transmission facilities with the PUC's issuance of certificates 
          of public convenience and necessity for transmission facilities.

          Requires the PUC to find construction of new transmission 
          necessary if the CAISO determines that the building or upgrading 
          of electrical transmission facilities is necessary, and the 
          commission determines that those transmission facilities will 
          serve at least 200 megawatts of eligible renewable energy 
          resources for which the commission has approved a purchase 
          agreement for RPS compliance and additionally determines that 
          those facilities assist in achievement of resource adequacy 
          requirements unless new information is provided showing good 
          cause for denial.

           EXISTING LAW  :

          1)Requires the California Public Utilities Commission (PUC) to 
            grant a Certificate of Public Convenience (CPCN) for 200 








                                                                  AB 1214
                                                                  Page  2

            kilovolt and above before beginning construction of a 
            transmission line or extension or a Permit to Construct (PTC) 
            for projects between 50kV and 200kV.

          2)Requires the PUC to take into consideration community values, 
            recreational and park areas, historic and aesthetic values, 
            influence on the environment, cost-effective alternatives 
            (including but not limited to demand-side alternatives, 
            targeted energy efficiency, ultraclean distributed generation, 
            and other demand reduction resources when considering 
            approving new transmission lines and expansions.

          3)Requires the CAISO to adopt inspection, maintenance, repair, 
            and replacement standards for transmission facilities in order 
            to provide high quality, safe, and reliable service and take 
            into account cost, local geography and weather, applicable 
            codes, and industry practice.

           FISCAL EFFECT  :   Unknown

           COMMENTS  :   

          According to the author, this bill will eliminate redundancy 
          where the CAISO has determined a transmission facility is 
          necessary via a Federal Energy Regulatory Commission (FERC) 
          approved interconnection agreement.  This would then relieve the 
          PUC from considering alternatives to the facility.

           1)Background  .  The PUC has constitutional authority to fix 
            rates, establish rules, examine records, issue subpoenas, 
            administer oaths, take testimony, punish for contempt, and 
            prescribe a uniform system of accounts for California investor 
            owned utilities.  In addition, the PUC provides a program to 
            provide reasonable compensation to interveners to assist 
            public participation in PUC proceedings.  The PUC is funded by 
            ratepayers.

            The CAISO is a non-profit public benefit corporation that has 
            statutory requirements to manage the State's electricity grid 
            and consult and coordinate with state and local agencies. 
            CAISO must meet the State's open meeting requirements and 
            comply with the California Public Records Act.  The CAISO is 
            funded generally through grid and transmission management 
            charges.
           








                                                                  AB 1214
                                                                  Page  3

          2)In April 2011 the PUC and CAISO executed a Memorandum of 
            Understand that seeks to coordinate CAISO transmission 
            planning with the PUC transmission permitting processes.

          3)The State's electricity grid is generally comprised of 
            transmission lines, distributions lines, and transfer stations 
            (commonly known as substations).  Transmission lines carry 
            bulk high-voltage electricity over long distances, while 
            distribution lines are short and carry smaller quantities of 
            electricity (typically 20 megawatt maximum per distribution 
            line).  Distribution lines carry electricity at a lower 
            voltage rating for residential, commercial, and industrial 
            uses.

            An interconnection agreement is a contract between an 
            electricity seller and either a transmission line owner or a 
            distribution line owner.  In California, transmission level 
            interconnection agreements must be reviewed and approved by 
            CAISO. 

            Separately, the electricity seller will enter into an 
            agreement to sell electricity to a utility, load serving 
            entity, community choice aggregator, or direct access 
            customer.

          4)Ratepayers pay 100% of the cost of construction for new 
            transmission lines, facilities, and expansions.

          5)CAISO relies on the Energy Commission's annual demand forecast 
            and the PUC Long Term Planning Procurement process to develop 
            an annual transmission plan.  The Energy Commission will be 
            updating its annual demand forecast through the 2011 
            proceeding on the Integrated Energy Policy Report.  At that 
            time, the Energy Commission is likely to begin incorporating 
            larger allocations of distributed generation (in particular 
            the 12,000 MW localized renewable goal advocated by Governor 
            Brown) and perhaps additional energy efficiency reductions.  
            This could reduce or delay the need to build new transmission 
            lines and facilities.

          6)In California, the CAISO has authority to execute 
            interconnection agreements over California's  transmission  
            lines.  However, it is important to point out that CAISO does 
            not control all of the electricity system in California.  The 
            owner of  distribution  level lines has review authority over 








                                                                  AB 1214
                                                                  Page  4

            connections to their distribution lines. In California, 
            distribution lines are owned by utilities. 

            Both CAISO and distribution line owners offer interconnection 
            agreements, which are regulated in form and content by the 
            FERC.  In addition, the PUC holds regulatory authority over 
            self-generation interconnections within the areas served by 
            investor owned utilities where the power that is produced is 
            also consumed on the same site (this is known at Rule 21).  
            Publicly owned utilities develop and implement their own 
            interconnection rules, most of which are generally similar to 
            Rule 21.

           7)An interconnection agreement is no substitute for assessing 
            alternatives to developing generation facilities.   The 
            approval of an interconnection agreement to construct a 
             project  is not equal to the review required by the California 
            Environmental Quality Act (CEQA), which would be used for 
            determining whether a utility  may receive ratepayer funding to 
            construct  a transmission line.

          8)Importantly, CAISO has no authority or access to information 
            regarding distribution level interconnection agreements 
            pending with the utilities.  Only the PUC has access to the 
            full spectrum of information necessary to determine whether to 
            issue a certificate of public convenience, including but not 
            limited to distributed generation programs (Reverse Auction, 
            Feed in Tariff, Self Generation Incentives, California Solar 
            Initiative) and energy efficiency programs.  The PUC is also 
            intimately familiar with the facilities in development through 
            the solicitations for compliance with the Renewable Portfolio 
            Standard. Additionally, the PUC has information regarding 
            Resource Adequacy and cost of generation that is critical to 
            ensuring that California ratepayers do not over pay and 
            utilities do not over-procure generation (conventional or 
            renewable fuels).  Moreover, the PUC is uniquely situated to 
            review whether new transmission is needed for reliability and 
            security or if an alternative to new transmission provides 
            equal or better ratepayer benefits. 

          9)The PUC is already required to report to the Legislature 
            annually on rates and programs.

          The author is correct that time is of the essence with regard to 
          opportunities for project developers to receive the benefits of 








                                                                  AB 1214
                                                                  Page  5

          federal tax credit and depreciation programs.  Projects that are 
          completed by December 31, 2011 would receive potentially as much 
          as 100% depreciation in their first year.  Tax credits are 
          scheduled to sunset December 31, 2016.   Renewable energy project 
          developers knew this when they designed and developed their 
          projects.

          It is not clear that interested and affected parties 
          (particularly the affected and adjacent property owner would 
          want to have their opportunity to intervene at the PUC bypassed 
          by an interconnection decision at the CAISO.
           
           The author may wish to consider an amendment to remove the 
          requirement that the PUC find a transmission facility is 
          necessary based on a determination by the CAISO.  

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          BrightSource Energy (sponsor)

           Opposition 
           
          Division of Ratepayer Advocates (DRA)
           
          Analysis Prepared by  :   Sue Kateley / U. & C. / (916) 319-2083