BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 2021
                                                                  Page  1

          Date of Hearing:   April 24, 2012

              ASSEMBLY COMMITTEE ON BUSINESS, PROFESSIONS AND CONSUMER 
                                     PROTECTION
                                 Mary Hayashi, Chair
                    AB 2021 (Wagner) - As Amended:  March 29, 2012
           
          SUBJECT  :   Works of improvement: disputed amounts. 

           SUMMARY  :   Revises the amount that an owner can withhold from a 
          contractor, and a contractor from a subcontractor, for disputed 
          private works of improvement.  Specifically,  this bill  :  

          1)Requires an owner who withholds money from a contractor, and a 
            prime contractor or subcontractor from a subcontractor, for 
            disputed works of improvement involving progress payments, to 
            withhold an amount from a progress payment not to exceed the 
            sum of the following: 

             a)   The liquidated damages owed by the contractor or 
               subcontractor; and, 

             b)   150% of the estimated cost to repair or replace contract 
               work that was not performed according to the contract. 

          2)Requires an owner who withholds money from a contractor, for 
            disputed works of improvement involving retention, to withhold 
            from the final payment an amount not to exceed the sum of the 
            following: 

             a)   The liquidated damages owed by the contractor; 

             b)   The amounts that are withheld due to a lien claim, lien 
               judgment, or bond payment claim;  

             c)   150% of the estimated cost of uncompleted work, except 
               for those costs withheld under (b); and, 

             d)   150% of the estimated cost to repair or replace contract 
               work that was not performed according to the contract, 
               except for those costs withheld under (b) and (c)

          3)Requires a direct contractor who withholds money from a 
            subcontractor, for disputed works of improvement involving 
            retention, to withhold from the final payment an amount not to 








                                                                  AB 2021
                                                                  Page  2

            exceed the sum of the following: 

             a)   The liquidated damages owed by the subcontractor; 

             b)   That portion of any mechanic's lien or stop payment 
               notice claim by the subcontractor that has already been 
               paid to the subcontractor; 

             c)   The amount that would have been withheld by the owner 
               due to a lien claim, lien judgment, or bond payment claim, 
               but for a release bond provided by the direct contractor, 
               as specified.

             d)   150% of the estimated cost of uncompleted subcontract 
               work, except for those costs withheld under (b); and, 

             e)   150% of the estimated cost to repair or replace 
               subcontract work that was not performed according to the 
               subcontract, except for those costs withheld under (b) or 
               (c).

           EXISTING LAW  contains various provisions relating to contracts 
          for the performance of private and public works of improvement, 
          including provisions for the withholding and disbursement of 
          retention proceeds, and provides that, with respect to those 
          contracts for works of improvement, the retention proceeds 
          withheld from any payment may not exceed 150% of the disputed 
          amount.  (Business and Professions Code Section 7108.5, Civil 
          Code Sections 3260 and 3260.1, and Public Contract Code Sections 
          7107 and10262.5)

           FISCAL EFFECT  :   Unknown.  This bill is keyed non-fiscal.
          
           COMMENTS  :   

           Purpose of this bill  .  According to the author's office, "The 
          Prompt Payment statutes are turning into a mess of loopholes.  
          They provide no relief to contractors against a sophisticated 
          owner.  Worse, they provide those owners with excuses for 
          withholding more money due to a loophole within the existed 
          statute."

           Background  .  Existing law authorizes an owner or contractor to 
          withhold up to 150% of the value of the disputed work performed 
          for a private work of improvement.  The sponsors contend that 








                                                                  AB 2021
                                                                  Page  3

          existing law provides a loophole for a person or contractor to 
          dispute work in order to withhold payment to a contractor 
          because there is no definition for determining the value of 
          disputed work.  This bill revises the amount that an owner can 
          withhold from a contractor, and contractor from subcontractor, 
          for disputed private works of improvement.  

           Support  .  According to the sponsors, the California Fence 
          Contractor's Association, Engineering Contractor's Association, 
          Flasher Barricade Association, and the Marin Builders 
          Association, "�The Prompt Pay statutes] provide owners with 
          excuses for withholding more money �from a contractor].  Here's 
          why: 'disputed amount' is not defined.  As a result, virtually 
          every construction attorney is running into these kinds of 
          things: 

          "A)  The owner orders time and material extra work.  Daily 
          tickets are signed by the owner's job site representative, 
          confirming that the equipment and labor actually performed the 
          extra work.   When the extra work is completed, the contractor 
          submits an invoice for $10,000 for the extra work?  The owner 
          decides the total is too much, so he declares this to be a 
          disputed amount.  Not only does the owner not pay for the extra 
          work, but because it is a 'disputed amount,' the owner withholds 
          what the law provides, which is 150% of that amount, or $15,000. 


          "B)  The job is delayed.  The causes of the delay are disputed.  
          The owner assesses liquated damages of $10,000.  The contractor 
          contests this assessment.  The owner, in-turn, declares this to 
          be a 'disputed amount' and withholds �150% of that amount, or 
          $15,000].

          "C)  A cost-plus job is performed.  Under the agreement, the 
          owner must pay all of the costs of the work.  A dispute develops 
          near the end of the job.  In response, the owner stops paying 
          and the contractor pulls off the job.  The owner hires another 
          contractor to finish the work at a cost of $10,000? to justify 
          withholding �150% of that amount, or] $15,000 from what is still 
          owed to the original contractor for costs of the work performed 
          by the original contractor."

           Previous Legislation  .  AB 2549 (Pacheco) of 2004, would have 
          revised the law with respect to retention proceeds for works of 
          improvement.  This bill would have increased the amount that may 








                                                                  AB 2021
                                                                  Page  4

          be withheld from progress payments or final payments, depending 
          on the circumstances, to a sum of various amounts and 
          percentages, as specified.  The Governor vetoed this bill with 
          the following message: 

               "Existing law, including lien protections and other 
               prompt pay requirements, afford most contractors with 
               sufficient protection to ensure payment on disputed 
               payments.   Additionally, I believe this bill will 
               only further complicate the various disparate statutes 
               regarding disputed payments between contractors and 
               owners.  This area of law that is very important to 
               both the consumer and contractor has been amended 
               piecemeal for far too long."

           Double-referred  .  This bill is double-referred to Assembly 
          Judiciary Committee.

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          California Fence Contractor's Association (co-sponsor)
          Engineering Contractor's Association (co-sponsor)
          Flasher Barricade Association (co-sponsor)
          Marin Builders Association (co-sponsor)

           Opposition 
           
          None on file. 
           
          Analysis Prepared by  :    Joanna Gin / B.,P. & C.P. / (916) 
          319-3301