BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 2021
                                                                  Page  1

          Date of Hearing:  May 8, 2012

                           ASSEMBLY COMMITTEE ON JUDICIARY
                                  Mike Feuer, Chair
                    AB 2021 (Wagner) - As Amended: March 29, 2012
                                           
          SUBJECT  :  WORKS OF IMPROVEMENT: DISPUTED AMOUNTS

           KEY ISSUE  :  SHOULD STATUTES RELATING TO RETENTION BY AN OWNER OR 
          CONTRACTOR OF DISPUTED AMOUNTS DUE TO A CONTRACTOR OR 
          SUBCONTRACTOR BE CLARIFIED BY BETTER DEFINING WHAT CONSTITUTES A 
          DISPUTED AMOUNT? 

           FISCAL EFFECT  :  As currently in print this bill is keyed 
          non-fiscal.

                                      SYNOPSIS
          
          This bill, sponsored by construction contractors, proposes to 
          clarify the "prompt-pay" statutes regarding works of 
          improvement. Supporters maintain that it would bring needed 
          certainty to the amounts that can be withheld by owners, 
          contractors and subcontractors from those to whom they owe 
          payment.  The bill is substantially similar to a prior measure, 
          AB 2549 of 2004, which passes this Committee but was vetoed by 
          the Governor.  There is no known opposition.

           SUMMARY  :  Revises the law with respect to exclusions from 
          progress payments as well as the allowable amount of retention 
          proceeds for works of improvement.  Specifically,  this bill  
          would increase the amount that may be withheld from progress 
          payments and retentions to the sum of liquidated damages owed by 
          the subcontractor and 150 percent of the estimated cost of 
          repair or replacement of subcontract work that was not performed 
          according to the subcontract or comparable sums where mechanics' 
          liens and other claims are involved, depending on specified 
          circumstances.

           EXISTING LAW  contains various provisions relating to contracts 
          for the performance of private and public works of improvement, 
          including provisions for the withholding and disbursement of 
          retention proceeds, and provides that, with respect to those 
          contracts for works of improvement, the retention proceeds 
          withheld from any payment may not exceed 150 percent of the 
          disputed amount.  (Business and Professions Code section 7108.5; 








                                                                  AB 2021
                                                                  Page  2

          Civil Code sections 8800, 8812 and 8814.)

           COMMENTS  :  According to the author:

               The Prompt Pay statutes are turning into a mess of 
               loopholes.  They provide no relief to contractors against a 
               sophisticated owner.  Worse, they provide those owners with 
               excuses for withholding more money due to a loophole within 
               the existing statute. Unfortunately, "disputed amount" is 
               not defined in the statute.  As a result, virtually every 
               construction attorney is running into these kinds of 
               things:

               A). The owner orders time and material extra work.  Daily 
               tickets are signed by the owner's jobsite representative 
               confirming that the equipment and labor actually performed 
               the extra work.  When the extra work is completed, the 
               contractor submits an invoice for $10,000 (for example) for 
               the extra work.  That invoice is the product of what the 
               contractor thought were agreed upon labor rates multiplied 
               by the labor hours on the tickets and what the contractor 
               thought were the agreed upon equipment rates multiplied by 
               the equipment hours on the tickets.  

               The owner decides the total is too much, so he declares 
               this to be a disputed amount.  Not only does the owner NOT 
               pay for the extra work, but because it is a "disputed 
               amount," the owner withholds what the law provides which is 
               150% of that amount, i.e. $15,000, from money otherwise 
               due.  In other words, if the contractor had never performed 
               the extra work, that $15,000 would never have been withheld 
               from money otherwise due.  However, since the contractor 
               did $10,000 in extra work, his cash flow is now reduced by 
               $25,000 ($10,000 paid out for the labor and equipment for 
               the extra work PLUS the $15,000 "disputed work" withhold).  


               While this action is blatantly unfair on the part of an 
               owner, the language in the existing prompt pay statutes 
               appears to sanction it - and sophisticated owners are using 
               this loophole in the law.

               B). The job is delayed.  The causes of the delay are 
               disputed.  The owner assesses liquidated damages of 
               $10,000. The contractor contests this assessment.  The 








                                                                  AB 2021
                                                                  Page  3

               owner, in-turn, declares this to be a "disputed amount" and 
               withholds NOT the $10,000, but 150% of the $10,000, i.e. 
               $15,000, because the contractor has disputed the liquidated 
               damages assessment. Once again, the language in the 
               existing prompt pay statutes appears to sanction this 
               loophole in the law.

               C). A cost-plus job is performed.  Under the agreement, the 
               owner must pay all of the costs of the work.  A dispute 
               develops near the end of the job.  In response, the owner 
               stops paying and the contractor pulls off the job.  The 
               owner now hires another contractor to finish the work at a 
               cost of $10,000 (for example).  The owner then contends 
               that the $10,000 it paid to the other contractor - money it 
               would have had to pay the original contractor under the 
               cost-plus contract - is a disputed amount.  Thus, the owner 
               uses that argument to justify withholding $15,000 from what 
               is still owed to the original contractor for costs of the 
               work done by the original contractor

               In summary, not only are owners using these kinds of 
               arguments to withhold payment, but they are also using them 
               to avoid the prompt payment penalties that were supposed to 
               assure prompt payment.

               AB 2021 is intended to correct this major loophole in the 
               current prompt pay statutes by defining disputed amount.  
               This will ensure that the process is fair and equitable to 
               all sides. 

           Substantially Similar Prior Measure Vetoed  .  AB 2549 of 2004 was 
          a nearly identical measure, although it applied to both public 
          and private projects, while this bill relates only to private 
          works.  That measure was vetoed by Governor Schwarzenegger who 
          stated:

               While I understand the arguments behind this measure, I 
               believe the nuances of the changes proposed may be too 
               complex for many Californians who hire contractors to 
               perform private works of improvement on their homes and 
               private property.

               Existing law, including lien protections and other prompt 
               pay requirements, afford most contractors with sufficient 
               protection to ensure payment on disputed payments.   








                                                                  AB 2021
                                                                  Page  4

               Additionally, I believe this bill will only further 
               complicate the various disparate statutes
               regarding disputed payments between contractors and owners. 
                This area of law that is very important to both the 
               consumer and contractor has been amended piecemeal for far 
               too long.

               I am asking the Legislature to work on crafting a measure 
               that would, not only simplify existing law, but ensure that 
               California consumers are adequately protected and that 
               contractors continue to be treated fairly while providing a 
               consolidation and reform of this entire body of law.

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Engineering Contractors' Association (co-sponsor)
          California Chapter of American Fence Association
          California Fence Contractors' Association
          California Professional Association of Specialty Contractors
          Flasher Barricade Association
          Marin Builders Association

           Opposition 
           
          None on file
           

          Analysis Prepared by  :  Kevin G. Baker / JUD. / (916) 319-2334