BILL ANALYSIS                                                                                                                                                                                                    �






                             SENATE JUDICIARY COMMITTEE
                             Senator Noreen Evans, Chair
                              2011-2012 Regular Session


          AB 2021 (Wagner)
          As Amended June 7, 2012
          Hearing Date: July 3, 2012
          Fiscal: No
          Urgency: No
          RD
                    

                                       SUBJECT
                                           
                       Works of Improvement: Disputed Amounts

                                      DESCRIPTION  

          This bill would revise certain existing statutes authorizing the 
          withholding of disputed amounts owed to a contractor to provide 
          for greater specificity and clarity in the amounts that may be 
          withheld in a pending dispute. The bill would state the intent 
          of the Legislature to overrule Martin Brothers Construction Inc. 
          v. Thompson Pacific Construction Inc. (2009) 179 Cal.App.4th 
          1401 to the extent that the decision is inconsistent with the 
          provisions of the bill.  The bill would make other technical, 
          non-substantive changes.
          
                                      BACKGROUND  

          Existing law, with respect to private and public works of 
          improvement, contains various "prompt pay" statutes requiring 
          that contractors and subcontractors be paid within certain 
          timeframes, unless there is a dispute over payment, in which 
          case the payor is allowed to withhold the disputed amount until 
          the dispute is resolved.  These prompt payment statutes serve a 
          "'remedial purpose: to encourage general contractors to pay 
          timely their subcontractors and to provide the subcontractor 
          with a remedy in the event that the contractor violates the 
          statute.'" (S&S Cummins Corp. v. West Bay Builders, Inc. (2008) 
          159 Cal.App.4th 765, 777 �citation omitted].)   

          In 2004 and 2005, the Legislature passed two bills, AB 2549 
          (Pacheco, 2004) and AB 341 (Huff, 2005), which were 
          substantially similar to this bill and revised statutes 
                                                                (more)



          AB 2021 (Wagner)
          Page 2 of ?



          authorizing the withholding of disputed amounts owed to a 
          contractor to provide for greater specificity and clarity in the 
          amounts that may be withheld in a pending dispute.  Unlike this 
          bill, which by and large applies to private works of 
          improvement, those bills applied to both public and private 
          works of improvement.  AB 2549 was vetoed by then-Governor 
          Arnold Schwarzenegger, and AB 341 was later gutted and amended 
          into another bill after it passed both houses unanimously.  
          In response to concerns that existing prompt pay statutes are 
          being abused by individuals who withhold excessive amounts 
          claiming they are "disputed," this bill would, with respect to 
          private works of improvement, revise existing statutes 
          authorizing the withholding of disputed amounts owed to a 
          contractor to provide for greater specificity and clarity in the 
          amounts that may be withheld in a pending dispute.  

          This bill was heard by the Senate Business, Professions and 
          Economic Development Committee on June 25, 2012 and passed out 
          on a vote of 8-0.


                                CHANGES TO EXISTING LAW
           
          1.    Existing law  provides that a prime contractor must pay 
            subcontractors within seven days of receipt of any progress 
            payment, unless otherwise agreed to in writing.  In the event 
            of a "good faith dispute" over the amount due, the prime 
            contractor may withhold up to 150 percent of the "disputed 
            amount."  Existing law provides that this section applies to 
            all private works of improvement as well as to public works of 
            improvement except as specified under the Public Contract 
            Code.  (Bus. & Prof. Code Sec. 7108.5.)

             This bill  would provide that the withholding amount may not 
            exceed the sum of liquidated damages assessed against the 
            subcontractor and 150 percent of the estimated cost of repair 
            or replacement of work that was not performed according to the 
            subcontract.

          2.    Existing law  provides that on a private work of 
            improvement, the owner shall pay a direct contractor within 30 
            days of receiving a notice demanding payment pursuant to the 
            contract, any progress payments due as to which there is no 
            good faith dispute between them, as specified.  Existing law 
            provides that if there is a good faith dispute between the 
            owner and direct contractor as to a progress payment due, the 
                                                                      



          AB 2021 (Wagner)
          Page 3 of ?



            owner may withhold up to 150 percent of the disputed amount. 
            (Civ. Code Sec. 8800.)

             This bill  would provide that the withheld amount may not 
            exceed the sum of both the liquidated damages assessed against 
            the contractor and 150 percent of the estimated cost of repair 
            or replacement of contract work not performed according to 
            contract.

          3.    Existing law  provides for the distribution of any proceeds 
            withheld by a project owner ("retention proceeds") within 45 
            days of completion of a work of improvement.  However, an 
            owner may withhold 150 percent of any disputed amount.  (Civ. 
            Code Sec. 8812.)
             
            This bill  would provide that the amounts that may be withheld 
            by an owner or original contractor may not exceed the sum of 
            all of the following: 
                the liquidated damages assessed against the contractor; 
                the amount withheld by the owner pursuant to specified 
               sections of law relating to certain liens and stop payment 
               notices; 
                150 percent of the estimated cost of uncompleted contract 
               work, except for those costs that are withheld as 
               specified; and 
                150 percent of the estimated cost to repair or replace 
               contract work that was not performed according to contract, 
               except for those costs withheld as specified.

          4.    Existing law  provides that a direct contractor must pay 
            subcontractors from whom retention has been withheld the 
            subcontractor's share of the payment from the retention 
            payment received, within 10 days.  Existing law provides that 
            if a good faith dispute exists between the direct contractor 
            and subcontractor, the direct subcontractor may withhold from 
            the retention to the subcontractor up to 150 percent of any 
            disputed amount.  (Civ. Code Sec. 8814.) 

             This bill  would provide that the amounts that may be withheld 
            by an owner or original contractor may not exceed the sum of 
            all of the following:
                 the liquidated damages assessed against the 
               subcontractor;
                 the portions withheld due to lien claims or stop payment 
               notice claim by the contractor for which the subcontractor 
               has already been paid
                                                                      



          AB 2021 (Wagner)
          Page 4 of ?



                 the amount that would have been withheld by the owner, 
               as specified, but for a bond provided by the direct 
               contractor as specified; 
                 150 percent of the estimated cost of uncompleted 
               contract work, except for those costs that are withheld as 
               specified; and 
                 150 percent of the estimated cost to repair or replace 
               contract work that was not performed according to contract, 
               except for those costs withheld as specified.

             This bill  would state the intent of the Legislature to 
            overrule Martin Brothers Construction Inc. v. Thompson Pacific 
            Construction Inc. (2009) 179 Cal.App.4th 1401 to the extent 
            that the decision is inconsistent with the provisions of the 
            bill.
             
            This bill  would make other technical, non-substantive changes. 


                                        COMMENT
           
          1.  Stated need for the bill  
          
          The author writes:
          
            The Prompt Pay statutes are turning into a mess of loopholes.  
            They provide no relief to contractors against a sophisticated 
            owner.  Worse, they provide those owners with excuses for 
            withholding more money.  Unfortunately, "disputed amount" is 
            not defined in the statute.  . . . AB 2021 is intended to 
            correct this major loophole in the current prompt pay statutes 
            by defining disputed amount.  This will ensure that the 
            process is fair and equitable to all sides.  
          
          2.    Difficulties witnessed with prompt pay statutes
            
          This bill would, with respect to private works of improvement, 
          revise existing statutes authorizing the withholding of disputed 
          amounts owed to a contractor to provide for greater specificity 
          and clarity in the amounts that may be withheld in a pending 
          dispute.  

          Proponents provide several examples of problems with the current 
          law, as follows: 

            �V]irtually every construction attorney is running into these 
                                                                      



          AB 2021 (Wagner)
          Page 5 of ?



            kinds of things:

            A). The owner orders time and material extra work.  Daily 
            tickets are signed by the owner's jobsite representative 
            confirming that the equipment and labor actually performed the 
            extra work.  When the extra work is completed, the contractor 
            submits an invoice for $10,000 (for example) for the extra 
            work.  That invoice is the product of what the contractor 
            thought were agreed upon labor rates multiplied by the labor 
            hours on the tickets and what the contractor thought were the 
            agreed upon equipment rates multiplied by the equipment hours 
            on the tickets.  

            The owner decides the total is too much, so he declares this 
            to be a disputed amount.  Not only does the owner NOT pay for 
            the extra work, but because it is a "disputed amount," the 
            owner withholds what the law provides which is 150 �percent] 
            of that amount, i.e. $15,000, from money otherwise due.  In 
            other words, if the contractor had never performed the extra 
            work, that $15,000 would never have been withheld from money 
            otherwise due.  However, since the contractor did $10,000 in 
            extra work, his cash flow is now reduced by $25,000 ($10,000 
            paid out for the labor and equipment for the extra work PLUS 
            the $15,000 "disputed work" withhold).  

            While this action is blatantly unfair on the part of an owner, 
            the language in the existing prompt pay statutes appears to 
            sanction it - and sophisticated owners are using this loophole 
            in the law.

            B). The job is delayed.  The causes of the delay are disputed. 
             The owner assesses liquidated damages of $10,000. The 
            contractor contests this assessment.  The owner, in-turn, 
            declares this to be a "disputed amount" and withholds NOT the 
            $10,000, but 150 �percent] of the $10,000, i.e. $15,000, 
            because the contractor has disputed the liquidated damages 
            assessment. Once again, the language in the existing prompt 
            pay statutes appears to sanction this loophole in the law.

            C). A cost-plus job is performed.  Under the agreement, the 
            owner must pay all of the costs of the work.  A dispute 
            develops near the end of the job.  In response, the owner 
            stops paying and the contractor pulls off the job.  The owner 
            now hires another contractor to finish the work at a cost of 
            $10,000 (for example).  The owner then contends that the 
            $10,000 it paid to the other contractor - money it would have 
                                                                      



          AB 2021 (Wagner)
          Page 6 of ?



            had to pay the original contractor under the cost-plus 
            contract - is a disputed amount.  Thus, the owner uses that 
            argument to justify withholding $15,000 from what is still 
            owed to the original contractor for costs of the work done by 
            the original contractor.

            In summary, not only are owners using these kinds of arguments 
            to withhold payment, BUT they are also using them to avoid the 
            prompt payment penalties that were supposed to assure prompt 
            payment!

          As noted in the background, this bill is substantially similar 
          to two prior bills from 2004 and 2005 which attempted to address 
          these same problems but were ultimately vetoed or later gutted 
          and amended after passing the Legislature unanimously.  The 
          Senate Judiciary Committee analysis to AB 2549 (Pacheco, 2004), 
          the first of these bills, noted that "�i]ndeed, the prompt pay 
          statutes which according to the bill's supporters are being used 
          in an unfair manner against subcontractors, were first placed in 
          statute to protect subcontractors."  

          Committee staff notes, as it did then, that with respect to the 
          payment issues raised by this bill, the problems seen on the 
          marketplace might not be easily fixed.  A party that wishes to 
          be unreasonable in withholding payment will almost always be 
          able to find some legally justifiable reason in the contract to 
          withhold large payment amounts until the dispute is resolved 
          through litigation.  For example, the new definitions of 
          disputed amount provided for by this bill still refer to 
          "estimated" amounts - estimates which can be inflated or 
          deflated with the flimsiest of justifications.  

          Nevertheless, the continued advocacy for changes in law by 
          subcontractor advocates, and the opposition of original 
          contractors and public entities to previous versions of the 
          bill, suggests that changes such as those proposed by this bill 
          do have some impact in the "real world" construction market.  To 
          the extent that changes can prevent some abuses of the term 
          "disputed amount," those proposed by this bill appear to be 
          unobjectionable and sound public policy.

          3.    Intent to overrule Martin Brothers Construction Inc. v. 
            Thompson Pacific Construction Inc  .

          The June 6, 2012 amendments added language that states the 
          intent of the Legislature to "overrule Martin Brothers 
                                                                      



          AB 2021 (Wagner)
          Page 7 of ?



          Construction Inc. v. Thompson Pacific Construction Inc. (2009) 
          179 Cal.App.4th 1401 to the extent that it is inconsistent with 
          this act."  The plaintiff in that case, the subcontractor, 
          Martin Brothers Construction Inc., sought penalties, interest, 
          and attorneys' fees for allegedly late progress and retention 
          payments by the contractor defendant, Thompson Pacific 
          Construction Inc., arising out of work done on a public project 
          under two "prompt payment" statutes, Public Contracts Code 
          Section 7107 (relating to retention payments) and Business & 
          Professions Code Section 2108.5 (relating to progress payments). 
           By the time of the trial, the defendant had already paid the 
          disputed amounts that had been withheld, making the penalties, 
          interest and attorneys fees the sole issues at trial. 

          The appellate court, in ruling against the plaintiff, held that 
          a section of the Public Contract Code, which authorized the 
          withholding of retention payments when a bona fide dispute 
          existed in public works of improvement, was applicable to a 
          dispute regarding change order work and therefore the defendant 
          contractor had no liability under that section for delayed 
          payments of retention proceeds given the parties' dispute over 
          the additional work.  Key to the court's decision was that the 
          meaning of "dispute" in that section was restricted only by the 
          requirement that it be bona fide-otherwise, the subject is 
          immaterial and could arise out of any number of subjects as a 
          result, including, but not limited to substandard performance, 
          timing of performance, or additional performance of work.  
          Ultimately, the court found that nothing in that section evinces 
          a legislative intent to limit the types of honest disputes that 
          would justify the withholding of retentions. 

          The court also held that the defendant contractor did not 
          violate Section 7108.5 of the Business and Professions Code, 
          which governs progress payments between a contactor and 
          subcontractor with respect to all private works of improvement 
          and most public works of improvement, by waiting until the 
          plaintiff provided the required documentation before making 
          progress payments to the plaintiff because the parties had 
          agreed to an alternative payment schedule and required 
          conditional lien releases before payment within the meaning of 
          that section.  The court noted that the section specifically 
          provides that the payments shall be made within 10 days (the 
          current statute now says seven days), unless otherwise agreed to 
          in writing. The court held that if the Legislature intended that 
          language to permit a fixed payment schedule as the only 
          alternative to the section, "it would have said so."  (179 
                                                                      



          AB 2021 (Wagner)
          Page 8 of ?



          Cal.App.4th 1401 at 1415.)  

          Staff notes, again, that the underlying issues in that case 
          arose out of a public project.  This bill, as introduced, would 
          have applied to both public and private works of improvement, in 
          virtually identical fashion as its predecessors, AB 2549 
          (Pachecho, 2004) and AB 341 (Huff, 2004).  However, in March, 
          the bill was amended to apply to only those prompt payment 
          provisions in the private works of improvement sections of the 
          Civil Code.  However, this bill does not amend the Public 
          Contracts Code Sections that were also included in AB 2549 and 
          AB 341.  Insofar as recent language added to this bill would 
          declare the Legislature's intent to overrule the decision to the 
          extent that it is in conflict with this bill's provisions, it is 
          unclear how the provisions of this bill could impact a decision 
          relating to public works of improvement.

          While the bill does amend Section 7108.5 of the Business and 
          Professions Code as well, a section that can apply to public 
          works of improvement and did apply in that case, this bill does 
          not in any way alter or otherwise impact the language that the 
          court relied upon in making its ruling.  Thus, given the unclear 
          nature of how this bill would at all overrule a case relating to 
          public works of improvement, let alone one that was focused on 
          issues surrounding penalties, interest, and attorneys fees, 
          which were alleged to be owed because retention and progress 
          payments were withheld and which the court held were authorized 
          to be withheld under the applicable sections of law, the 
          following amendment is suggested to strike the intent language 
          from the bill: 

             Suggested Amendment  : 

            On page 4, strike lines 29-32

          4.   Governor Schwarzenegger's veto of AB 2549  

          This bill is substantially similar to the enrolled version of AB 
          2549 (Pachecho, 2004), except that this bill by and large 
          relates only to private works of improvement and also includes 
          intent language to overrule specified case law.  In vetoing AB 
          2549, Governor Schwarzenegger stated:

            While I understand the arguments behind this measure, I 
            believe the nuances of the changes proposed may be too complex 
            for many Californians who hire contractors to perform private 
                                                                      



          AB 2021 (Wagner)
          Page 9 of ?



            works of improvement on their homes and private property.

            Existing law, including lien protections and other prompt pay 
            requirements, afford most contractors with sufficient 
            protection to ensure payment on disputed payments.   
            Additionally, I believe this bill will only further complicate 
            the various disparate statutes regarding disputed payments 
            between contractors and owners.  This area of law that is very 
            important to both the consumer and contractor has been amended 
            piecemeal for far too long.

            I am asking the Legislature to work on crafting a measure that 
            would, not only simplify existing law, but ensure that 
            California consumers are adequately protected and that 
            contractors continue to be treated fairly while providing a 
            consolidation and reform of this entire body of law.

          5.    Technical amendments  

          The following technical amendments are suggested to correct 
          internal cross-references in the bill: 

             Suggested Amendments  : 

            On page 3, line 34 after paragraph (2) add "or (3)"

            On page 3, line 38 strike "(2) or (3)" and insert "(2), (3) or 
            (4)"


           Support  :  None Known 
           Opposition  :  None Known

                                        HISTORY
           
           Source  :  California Chapter of American Fence Association; 
          California Fence Contractors' Association; Engineering 
          Contractors' Association; Flasher Barricade Association; Marin 
          Builders Association 

           Related Pending Legislation  :  None Known

           Prior Legislation  :

          AB 341 (Huff, 2005) See Background.  That bill passed the Senate 
          Judiciary Committee on a vote of 6-0. 
                                                                      



          AB 2021 (Wagner)
          Page 10 of ?




          AB 2549 (Pacheco, 2004) See Background.  That bill passed the 
          Senate Judiciary Committee on a vote of 7-0. 

           Prior Vote  :

          Senate Business, Professions & Economic Development Committee 
          (Ayes 8, Noes 0)
          Assembly Floor (Ayes 74, Noes 0)
          Assembly Judiciary Committee (Ayes 10, Noes 0) 
          Assembly Business, Professions & Consumer Protection Committee 
          (Ayes 9, Noes 0)

                                   **************