                                 THIRD READING


          Bill No:  AB 2021
          Author:   Wagner (R)
          Amended:  8/29/12 in Senate
          Vote:     21

           
           SENATE BUSINESS, PROF. & ECON. DEV. COMM.  :  8-0, 6/25/12
          AYES:  Price, Emmerson, Corbett, Correa, Negrete McLeod, 
            Strickland, Vargas, Wyland
          NO VOTE RECORDED:  Hernandez

           SENATE JUDICIARY COMMITTEE  :  4-0, 7/3/12
          AYES:  Evans, Blakeslee, Corbett, Leno
          NO VOTE RECORDED:  Harman
           
          ASSEMBLY FLOOR  :  74-0, 5/10/12 - See last page for vote


           SUBJECT  :    Works of improvement:  disputed amounts

           SOURCE  :     California Chapter of American Fence 
          Association 
                      California Fence Contractors Association 
                      Engineering Contractors Association 
                      Flasher Barricade Association 
                      Marin Builders Association 


           DIGEST  :    This bill revises the amount that an owner can 
          withhold from a contractor, and a contractor from a 
          subcontractor, for disputed private works of improvement.

           Senate Floor Amendments  of 8/29/12 undo an amendment taken 
                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          2

          on 
          August 23, 2012, on the Senate Floor, which moved the 
          statement "unless otherwise agreed to in writing" to the 
          end of that sentence.  These amendments undo that specific 
          amendment to restore that sentence to existing law.

           Senate Floor Amendments  of 8/23/12 address concerns 
          regarding the disputed amounts that may be withheld from 
          progress, retention, or final payments in private works of 
          improvement, and make other clarifying changes.

           ANALYSIS  :    Existing law, the Business and Professions 
          Code (BPC):

          1. Licenses and regulates contractors by the Contractors 
             State License Board within the Department of Consumer 
             Affairs.

          2. Requires a prime contractor or subcontractor to pay 
             subcontractors, to the extent of their interest therein, 
             within seven days of receipt of any progress payment, 
             unless otherwise agreed to in writing.  In the event of 
             a "good faith" dispute over all or any portion of the 
             amount due, the prime contractor or subcontractor may 
             withhold up to 150% of the "disputed amount."  (BPC 
             Section 7108.5)

             A.    Specifies that any violation of these provisions 
                shall constitute a cause for disciplinary action and 
                shall subject the licensee to a penalty, payable to 
                the subcontractor, of 2% of the amount due per month 
                for every month that payment is not made.

             B.    Provides that in any action for the collection of 
                funds wrongfully withheld, the prevailing party shall 
                be entitled to attorney fees and costs.

             C.    Applies these provisions to private and public 
                works of improvement, except as specified.

          Existing law, the Civil Code (CIV):

          1. Unless otherwise agreed in writing, an owner shall pay a 
             direct contractor, within 30 days after receiving a 

                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          3

             notice demanding payment under the contract, any 
             progress payment due.  In the event of a "good faith" 
             dispute over the progress payment due, the owner may 
             withhold up to 150% of the disputed amount of the 
             progress payment.  (CIV Section 8800)

          2. Requires an owner who has withheld a retention payment 
             from a direct contractor, to pay the retention to the 
             contractor within 45 days after completion of the work 
             of improvement.  In the event of a "good faith" dispute 
             over the retention payment due, the owner may withhold 
             up to 150% of the disputed amount from final payment.  
             (CIV Section 8812)

          3. Requires a direct contractor who has withheld a 
             retention payment from a subcontractor, to pay the 
             subcontractor the appropriate share of the retention 
             payment within 10 days after receiving all or part of a 
             retention payment.  In the event of a "good faith" 
             dispute, the direct contractor may withhold up to 150% 
             of the estimated value of the disputed amount.  (CIV 
             Section 8814)

          This bill:

          1. Requires a prime contractor who withholds payment from a 
             subcontract, for disputed works of improvement involving 
             progress payments, to withhold an amount from a progress 
             payment not to exceed the sum of the following: 

             A.    The delay damages for which the subcontractor may 
                be liable.

             B.    150% of the estimated cost to repair or replace 
                contract work that was not performed according to the 
                contract.

             C.    The amount of any written claim against the prime 
                contractor for a violation of the Labor Code or a 
                collective bargaining agreement by the subcontractor 
                or any other person performing work required by the 
                subcontract.

             D.    That portion of any mechanics lien or stop payment 

                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          4

                notice claim by the subcontractor or any other person 
                performing work required by the subcontract for which 
                the subcontractor has already been paid.

             E.    The amount that would have been withheld by the 
                owner pursuant to specified sections of law relating 
                to mechanics liens or stop payment notices, but for a 
                bond provided by the contractor as specified.

          2. Requires an owner who withholds payment from a direct 
             contractor for disputed works of improvement involving 
             progress payments, to withhold an amount from a progress 
             payment not to exceed the sum of the following:

             A.    The liquidated damages assessed against the 
                contractor.

             B.    150% of the estimated cost of repair or 
                replacement of contract work that was not performed 
                according to the contract.

             C.    The amount of any written claim against the owner 
                for a violation of the Labor Code or a collective 
                bargaining agreement by any contractor.

             D.    That portion of any mechanics lien or stop payment 
                notice claim by any contractor for which the direct 
                contractor has already been paid.

          3. Requires an owner who withholds money from a contractor, 
             for disputed works of improvement involving retention, 
             to withhold from the final payment, unless already 
             withheld from a progress payment, an amount not to 
             exceed the sum of the following: 

             A.    The liquidated damages assessed against the 
                contractor;

             B.    The amounts withheld due to a lien claim, lien 
                judgment, or bond payment claim;

             C.    150% of the estimated cost of uncompleted work, 
                except for those costs withheld under this item; and 


                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          5

             D.    150% of the estimated cost to repair or replace 
                contract work that was not performed according to the 
                contract, except for those costs withheld under this 
                bill.

             E.    The amount of any written claim against the owner 
                for a violation of the Labor Code or a collective 
                bargaining agreement by any contractor.

             F.    That portion of any mechanics lien or stop payment 
                notice claim by any contractor for which the direct 
                contractor has already been paid.

          4. Requires a direct contractor who withholds money from a 
             subcontractor, for disputed works of improvement 
             involving retention, to withhold from the final payment 
             an amount not to exceed the sum of the following:

             A.    The delay damages for which the subcontractor may 
                be liable;

             B.    That portion of any mechanic's lien or stop 
                payment notice claim by the subcontractor or any 
                other person performing work required by the 
                subcontract that has already been paid to the 
                subcontractor;

             C.    The amount that would have been withheld by the 
                owner due to a lien claim, lien judgment, or bond 
                payment claim, but for a release bond provided by the 
                direct contractor, as specified;

             D.    150% of the estimated cost of uncompleted 
                subcontract work, except for those costs withheld 
                under this item;

             E.    150% of the estimated cost to repair or replace 
                subcontract work that was not performed according to 
                the subcontract, except for those costs withheld 
                under this bill; and

             F.    The amount of any written claim against the direct 
                contractor for a violation of the Labor Code or a 
                collective bargaining agreement by the subcontractor 

                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          6

                or any other person performing work required by the 
                subcontract.

           Related Legislation
           
          AB 2549 (Pacheco, 2004) was a nearly identical measure, 
          although it applied to both public and private projects, 
          while this bill relates only to private works.  The bill 
          passed both houses unanimously only to be vetoed by 
          Governor Schwarzenegger, who stated in part:

             While I understand the arguments behind this measure, I 
             believe the nuances of the changes proposed may be too 
             complex for many Californians who hire contractors to 
             perform private works of improvement on their homes and 
             private property.

             Existing law, including lien protections and other 
             prompt pay requirements, afford most contractors with 
             sufficient protection to ensure payment on disputed 
             payments.  Additionally, I believe this bill will only 
             further complicate the various disparate statutes 
             regarding disputed payments between contractors and 
             owners.  This area of law that is very important to both 
             the consumer and contractor has been amended piecemeal 
             for far too long.

             I am asking the Legislature to work on crafting a 
             measure that would, not only simplify existing law, but 
             ensure that California consumers are adequately 
             protected and that contractors continue to be treated 
             fairly while providing a consolidation and reform of 
             this entire body of law.

          AB 341 (Huff, 2005) passed both houses unanimously and was 
          again going to be vetoed, so the bill was returned to the 
          Legislature and gutted.

           FISCAL EFFECT  :    Appropriation:  No   Fiscal Com.:  No   
          Local:  No

           SUPPORT  :   (Verified  8/23/12)

          California Chapter of American Fence Association 

                                                           CONTINUED





                                                               AB 2021
                                                                Page 
          7

          (co-source) 
          California Fence Contractors Association (co-source)
          Engineering Contractors Association (co-source)
          Flasher Barricade Association (co-source)
          Marin Builders Association (co-source)

           ARGUMENTS IN SUPPORT  :    The author states, "The Prompt Pay 
          statutes are turning into a mess of loopholes.  They 
          provide no relief to contractors against a sophisticated 
          owner.  Worse, they provide those owners with excuses for 
          withholding more money due to a loophole within the 
          existing statute:  Section 7107 (e) of the Public Contract 
          Code states:  (e) The original contractor may withhold from 
          a subcontractor its portion of the retention proceeds if a 
          bona fide dispute exists between the subcontractor and the 
          original contractor.  The amount withheld from the 
          retention payment shall not exceed 150 percent of the 
          estimated value of the disputed amount.  Unfortunately, 
          'disputed amount' is not defined in the statute.  As a 
          result, virtually every construction attorney is running 
          into these kinds of things."


           ASSEMBLY FLOOR  :  74-0, 5/10/12
          AYES:  Achadjian, Alejo, Allen, Ammiano, Atkins, Beall, 
            Bill Berryhill, Block, Blumenfield, Bonilla, Bradford, 
            Brownley, Buchanan, Butler, Charles Calderon, Campos, 
            Carter, Cedillo, Chesbro, Conway, Davis, Dickinson, 
            Donnelly, Eng, Feuer, Fong, Fuentes, Beth Gaines, 
            Galgiani, Garrick, Gatto, Gordon, Gorell, Grove, Hagman, 
            Halderman, Hall, Harkey, Hayashi, Roger Hern�ndez, Hill, 
            Huber, Hueso, Huffman, Jones, Knight, Lara, Logue, Bonnie 
            Lowenthal, Ma, Mansoor, Mendoza, Miller, Mitchell, 
            Monning, Morrell, Nestande, Nielsen, Norby, Pan, Perea, 
            Portantino, Silva, Skinner, Smyth, Solorio, Swanson, 
            Torres, Valadao, Wagner, Wieckowski, Williams, Yamada, 
            John A. P�rez
          NO VOTE RECORDED:  Cook, Fletcher, Furutani, Jeffries, 
            Olsen, V. Manuel P�rez


          JJA:k  8/30/12   Senate Floor Analyses 

                         SUPPORT/OPPOSITION:  SEE ABOVE