BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 2341
                                                                  Page  1

          Date of Hearing:   April 23, 2012

                    ASSEMBLY COMMITTEE ON UTILITIES AND COMMERCE
                               Steven Bradford, Chair
                AB 2341 (Williams) - As Introduced:  February 24, 2012
           
          SUBJECT  :   Distribution grid: distributed generation.

          SUMMARY  :   Requires the California Public Utilities Commission 
          (PUC) to ensure through its electric general rate cases and 
          related proceedings, that all investments in the distribution 
          grid are compatible with optimal deployment of distributed 
          generation, to the extent grid upgrades are required to meet a 
          goal of 12,000 megawatts of distributed generation by 2020.  

           EXISTING LAW  :

          1)States the PUC has regulatory authority over public utilities, 
            including electrical corporations, as defined.

          2)Requires the PUC to administer, until January 1, 2016, a 
            self-generation incentive program for distributed generation 
            resources to facilitate the integration of those resources 
            into the electrical grid, improve efficiency and reliability 
            of the distribution and transmission system, and reduce 
            emissions of greenhouse gases, peak demand, and ratepayer 
            costs.

          3)States requirements apply to projects that interconnect on the 
            side of the electrical meter that is controlled by a customer 
            of a utility and designed to provide electricity that is 
            generally consumed on site by the customer (known as PUC Rule 
            21). The PUC has oversight of Rule 21.

          4)Federal laws apply to projects that interconnect on the side 
            of the electrical meter that is controlled by the utility and 
            designed to provide electricity that will be purchased by the 
            utility for sale to a customer. There are two types of 
            possible interconnection rules, one for transmission level 
            interconnection and another for all others. The Generator 
            Interconnection Process applies to transmission 
            interconnection requests and is administered by the California 
            Independent System Operator (CAISO). Local electric utilities 
            administer the other, distribution level interconnection 
            request. It is known as the Wholesale Distribution Access 








                                                                  AB 2341
                                                                  Page  2

            Tariff, (WDAT). Both GIP and WDAT are overseen by The Federal 
            Energy Regulatory Commission (FERC).

           FISCAL EFFECT  :   Unknown.

           1)COMMENTS  :   According to the author, "Governor Brown has 
            established a goal of 12,000 megawatts of new distributed 
            generation (DG) to help meet California's clean energy and 
            economic development goals.  To achieve this, it's incumbent 
            upon the state to ensure that investments made on the 
            distribution grid now, are preparing California for future 
            with a high level of DG development. Doing so ensures that 
            ratepayers save money, the State is proactive about DG-capable 
            grid investments, and DG-developers have more certainty as 
            they help California move toward meeting the Governor's goal 
            for new distributed generation."
           2)Background  :  DG refers to electric generation facilities that 
            are located close to the point of electricity consumption.  DG 
            includes a range of technologies such as solar, wind, fuel 
            cells powered by natural gas, or biogas.

            Governor Brown has established a goal to install 12,000 
            megawatts of localized energy resources (LER) to help meet 
            California's clean energy and economic development goals.  To 
            achieve this, more investments into the distribution grid may 
            be warranted.

            The PUC is mandated to ensure that electricity rates meet a 
            just and reasonable standard. A General Rate Case (GRC) is the 
            major proceeding under which the PUC has the opportunity to 
            apply that standard to review a utility's proposed revenues, 
            expenses, and plant and equipment investments, including 
            maintaining and enhancing generation and distribution 
            infrastructure. Thus, the proceeding does not typically 
            include a comprehensive identification of infrastructure 
            needs, a comparison of investment option, or cost-benefit 
            analysis of resource types.

           3)Cost-shifting  :  This bill requires the PUC to ensure that its 
            decisions in GRC proceedings invest in distribution system 
            upgrades sufficient to meet a goal of 12,000 MW of LER by 
            2020. This bill would assign to ratepayers the cost of 
            investments in the distribution system to achieve such a goal. 
            This policy approach reverses longstanding PUC policy which 
            assigns distribution system upgrade costs to the developer.  








                                                                  AB 2341
                                                                  Page  3


            Moreover, this bill does not contain any provisions to 
            determine if the proposed DG upgrades are cost-effective 
            and/or whether alternative resources, such as energy 
            efficiency or demand response, would be less expensive. Such 
            provisions would be most critical to ensure ratepayer 
            protection.  

           4)PUC efforts underway  :  The PUC is examining how to implement 
            the Governor's 12,000 megawatts goal in several open long-term 
            planning, procurement, resource adequacy, interconnection, and 
            smart grid proceedings.  

            The PUC is addressing issues related to distribution level 
            interconnection in an open proceeding (R.11-09-011).  Phase 2 
            of the proceeding, which is anticipated to begin in Quarter 3 
            2012, will address cost issues associated with interconnecting 
            DG.  

            Evaluation of the costs and benefits of DG, including 
            infrastructure costs, is also being conducted in a series of 
            technical studies being launched this year.  The Long-Term 
            Procurement Plan (LTPP) proceeding serves as the PUC's 
            umbrella proceeding to consider, in an integrated fashion, the 
            utilities' procurement of supply resources and ensure 
            compliance with the loading order resource policies.
           
            Within the PUC's Resource Adequacy proceeding, the PUC will 
            consider rule changes relating to DG, including a proposal by 
            the California Independent System Operator (CAISO) to provide 
            Resource Adequacy Deliverability for DG.  CAISO's proposal, if 
            implemented, will provide additional market signals about 
            efficient siting of distributed generation and facilitate 
            Resource Adequacy Deliverability for DG.

            Earlier this year the PUC issued requests for proposals for 
            technical expertise to study and compare costs and benefits 
            among different types of DG and procurement mechanisms. Work 
            is anticipated to begin on these studies in the coming months. 


           5)Suggested amendment  :  The author and this committee may wish 
            to amend the bill  to give the PUC the flexibility to address 
            distribution grid investment issues in a separate proceeding, 
            or combine them with interrelated issues outside of the GRC 








                                                                 AB 2341
                                                                  Page  4

            rather than mandating distribution grid investment issues be 
            vetted in the GRC.  

           6)Technical concerns  :  The bill language specifies key terms 
            such as ensure that all investments are "compatible with 
            optimal deployment".  It is unclear how the author is defining 
            "compatible" and "optimal deployment".


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Absolutely Solar Inc. (ASI)
          American Biogas Council
          Clean Coalition (sponsor)
          Environmental Health Coalition 
          Green-Collar Jobs Campaign of the Ella Baker Center for Human 
          Rights
          Sierra Club California
          Solar Developers Council

          Opposition 
           
          California Manufacturers & Technology Association (CMTA)
          California Public Utilities Commission (CPUC)
          Sempra Energy utilities (SEu)
          Southern California Edison (SCE)
           
          Analysis Prepared by  :    DaVina Flemings / U. & C. / (916) 
          319-2083