BILL ANALYSIS                                                                                                                                                                                                    �






           SENATE TRANSPORTATION & HOUSING COMMITTEE       BILL NO: AB 2498
          SENATOR MARK DESAULNIER, CHAIRMAN              AUTHOR:  Gordon
                                                         VERSION: 
          6/15/2012
          Analysis by:  Art Bauer                        FISCAL:  yes
          Hearing date:  June 26, 2012




          SUBJECT:

          Construction manager/general contractor procurement

          DESCRIPTION:

          This bill authorizes the California Department of Transportation 
          (Caltrans) to use an alternative procurement method referred to 
          as Construction Manager/General Contractor (CM/GC) for up to 
          four projects. 

          ANALYSIS:

          Under the State Contract Act, public entities must fully 
          complete the design of a project prior to awarding a 
          construction contract and must award that contract to the 
          "lowest responsible bidder." This process, commonly known as 
          design-bid-build, is intended to ensure that the project is 
          built for the lowest possible cost.  Although this is by far the 
          most common method of public contracting, for certain projects 
          it may not  result in the lowest cost, nor be the most efficient 
          method of delivery. 

          Under design-bid-build, the project designer (whether 
          consultants or employees of a public entity) has sole ownership 
          of the project design and does not have the benefit of 
          consultation with the contractor that will ultimately be 
          responsible for construction of the project.  Thus, there may be 
          significant construction issues that the designer does not 
          anticipate which can result in change orders later in the 
          process.  This can drive up the project cost and shift all the 
          risk to the agency commissioning the project.  Moreover, because 
          under design-bid-build, all design, permits, right-of-way 
          acquisition, etc., must occur prior to contract award, the 
          opportunity to save time by fast-tracking certain elements of a 
          project while work continues on other elements is lost. 




          AB 2498 (GORDON)                                       Page 2

                                                                       



          Existing law establishes the Design-Build Demonstration Program, 
          which authorizes Caltrans to use the design-build method of 
          procurement for up to ten projects, subject to the California 
          Transportation Commission (CTC) approval.  The design-build 
          entity is made up of a design firm and a construction firm.  
          This ensures collaboration between the designer and the 
          contractor. It also allows the design-build firm to fast track 
          aspects of a project as issues around other elements are 
          resolved.  However, the potential weakness of this method is 
          that the owner of the project relinquishes substantial control 
          over the design.  Collaboration occurs between the design and 
          construction members of the design-build team, but design-build 
          limits the role of the project owner. 


           This bill  :

          1.Defines a CM/GC method of procurement as one in which Caltrans 
            selects the construction manager to provide preconstruction 
            services during the design phase of a project, plus actual 
            construction services when the project is being built.

          2.Authorizes Caltrans to use CM/GC procurement method for four 
            projects, with at least three of the projects having a 
            construction value greater than $10 million each. 

          3.Selection of the CM/GC team is a competitive procurement 
            process where Caltrans evaluates bids on the basis of 
            qualifications of the firm, proposed approach to design, 
            experience, and other factors.

          4.Requires Caltrans to prepare and submit a status report to the 
            Legislature no later than July 1 of each year during which a 
            CM/CG project is underway.  

          COMMENTS:

           1.Purpose  .  The purpose of this bill, according to Caltrans, the 
            bill's sponsor, is to use CM/CG to expedite project delivery. 
            Caltrans states that it intends to use CM/CG "where unusual 
            constructability issues are likely to emerge.  In such cases, 
            having the insight and cooperation of the construction 
            contractor early in the process can yield innovative solutions 
            that save significant time and cost." 





          AB 2498 (GORDON)                                       Page 3

                                                                       


           2.Alternative project delivery methods  .  In the last several 
            years, public agencies have been adopting alternative project 
            delivery methods.  The principle reason for this is the desire 
            to shift construction risk from the agency/owner to the 
            project contractor.  The most widely used alternative project 
            delivery technique is design-build. 

           3.The Construction Manager/General Contractor.   The CMGC project 
            delivery method allows an agency to engage a construction 
            manager during the design process to provide assistance to the 
            design team, including advice regarding scheduling, pricing, 
            phasing, and other matters that helps the owner design a more 
            constructible project.  According to the Federal Highway 
            Administration (FHWA), when design reaches approximately 60 to 
            90 percent completion, the agency and the construction manager 
            negotiate a guaranteed maximum price for the construction of 
            the project based on the defined scope and schedule.  If this 
            price is acceptable to both parties, a contract is executed 
            for construction services, and the construction manager 
            becomes the general contractor.  The FHWA has found that the 
            benefits of this procurement method include that the public 
            agency does not sacrifice control over the design of the 
            project and during the construction phase, the contractor is 
            very familiar with the project design resulting in less 
            disputes over design issues.

          RELATED LEGISLATION: 


          SB 1549 (Vargas) authorizes the San Diego Association of 
          Governments to use the CM/GC project delivery method for 
          projects that it sponsors.  SB 1549 passed this committee 
          earlier this year 9-0.  The bill is currently in the Assembly 
          Local Government Committee.

          

          Assembly Votes:
               Floor:    71-0
               Appr: 17-0
               Trans:    11-2

          POSITIONS:  (Communicated to the committee before noon on 
          Wednesday, 
                     June 20, 2012)





          AB 2498 (GORDON)                                       Page 4

                                                                       


               SUPPORT:  Department of Transportation (sponsor)
                         Associated General Contractors
          
               OPPOSED:  None received.