BILL ANALYSIS                                                                                                                                                                                                    �




                   Senate Appropriations Committee Fiscal Summary
                           Senator Christine Kehoe, Chair


          AB 2498 (Gordon) - Caltrans project delivery: Construction 
          Manager/General Contractor.
          
          Amended: June 15, 2012          Policy Vote: T&H 9-0
          Urgency: No                     Mandate: Yes
          Hearing Date: August 6, 2012                           
          Consultant: Mark McKenzie       
          
          This bill may meet the criteria for referral to the Suspense 
          File. 
          
          Bill Summary: AB 2498 would authorize the Department of 
          Transportation (Caltrans) to use the Construction 
          Manager/General Contractor (CMGC) procurement method on up to 
          four projects, three of which must have construction costs of 
          over $10 million.

          Fiscal Impact: Unknown project costs or savings to Caltrans 
          (State Highway Account and federal funds) by providing authority 
          to use a new project delivery method.  Caltrans costs to 
          administer and report on the new contracting method would be 
          minor.

          Caltrans anticipates significant long term savings, based on 
          other states' experience.  Staff notes, however, that early 
          experience with any new project delivery method usually proves 
          to be more costly than traditional design-bid-build in the 
          initial implementation period.  (see staff comments)

          In addition, since a contract for preconstruction and 
          construction services for CMGC is a negotiated process with the 
          most qualified construction manager, rather than a traditional 
          "lowest responsible bidder" process, it is difficult to 
          determine whether the negotiated price would be lower or higher 
          than project delivery costs through a traditional 
          design-bid-build process.  It is expected that use of the CMGC 
          method would minimize change orders, which is currently a 
          significant factor in unexpected cost escalation on Caltrans 
          projects.

          Background: The traditional project delivery process is the 
          design-bid-build method, whereby complete plans and 








          AB 2498 (Gordon)
          Page 1


          specifications are prepared prior to the advertising, bidding, 
          and awarding of any construction contracts.  The agency awards 
          the contract to the lowest, responsible bidder.  Although this 
          method is structured to ensure a project is built for the lowest 
          cost, oftentimes project costs escalate dramatically as change 
          orders are necessary to address unforeseen problems encountered 
          during the construction phase.  In addition, the bulk of project 
          risk remains with the sponsoring agency.

          In the last several years, public agencies have been adopting 
          alternative project delivery methods.  The principle reason for 
          this is the desire to shift construction risk from the 
          agency/owner to the project contractor and to expedite project 
          completion.  The most widely used alternative project delivery 
          technique is design-build.  This method requires the public 
          agency to prepare plans to 30 percent completion before 
          advertising for bids.  The bids are submitted with a fixed cost 
          for both design and construction services, and they are 
          evaluated using the best value methodology, which includes 
          factors such as the design-build firm's qualifications, proposed 
          approach to design, experience, and other factors.  The winning 
          bidder completes the design work and commences construction.  
          Because the team finishes the design work, it carries most of 
          the risk associated with the adequacy of plans.  Often 
          construction can commence on a phase of the project before the 
          entire project is designed, reducing the construction time.

          Design-sequencing is a method of contracting that enables the 
          sequencing of design activities to permit each project 
          construction phase to commence when design for that phase is 
          complete, rather than requiring a complete design before 
          commencing construction.  When the contractor bids, the first 
          phase of the project is completed and the remaining phases must 
          be at 30 percent completion according to Department of 
          Transportation (Caltrans) guidelines.  The award is made to the 
          lowest, responsible bidder.  The benefit of design-sequencing is 
          assumed to be time savings.  Caltrans' authority to use 
          design-sequencing expired in 2010, and final reports on its use 
          on state projects are pending.

          The construction manager/general contractor (CMGC) project 
          delivery method allows an agency to engage a construction 
          manager during the design process to provide assistance to the 
          design team, including advice regarding scheduling, pricing, 








          AB 2498 (Gordon)
          Page 2


          phasing, and other input that helps the owner design a more 
          constructible project.  The agency selects the construction 
          manager on the basis of qualifications, past experience, or a 
          best-value basis. According to the Federal Highway 
          Administration, when design reaches approximately 60 to 90 
          percent completion, the agency and the construction manager 
          negotiate a guaranteed maximum price for the construction of the 
          project based on the defined scope and schedule.  If this price 
          is acceptable to both parties, a contract is executed for 
          construction services, and the construction manager becomes the 
          general contractor.  The benefits of this procurement method is 
          that the public agency does not sacrifice control over the 
          design of the project, and during the construction phase the 
          contractor is familiar with the project design, resulting in 
          fewer change orders and disputes over design issues.

          Proposed Law: AB 2498 would authorize Caltrans to use the CMGC 
          project delivery method for up to four projects statewide, three 
          of which must have construction costs of $10 million or more.  
          The CMGC method is a procurement method in which Caltrans 
          selects a construction manager to provide preconstruction 
          services during the design phase and construction services 
          during the construction phase of a project, and the execution of 
          the design and construction phases may be sequential or 
          concurrent.  

          The bill requires Caltrans to establish a procedure to evaluate 
          and select a construction manager through a ranked request for 
          qualifications process, as specified.  Caltrans would enter into 
          a negotiated contract with a construction manager for 
          preconstruction services that includes a fee for those services 
          but may not include provisions for payment for construction 
          services.  The contract would provide for subsequent negotiation 
          for construction.  The construction services contract would be 
          awarded after plans are sufficiently developed and either a 
          fixed price or guaranteed maximum price has been negotiated, as 
          specified, and the construction manager must perform at least 30 
          percent of the work covered by the contract.  The bill would 
          also require annual progress reports to the Legislature by July 
          1 of each year during which a CMGC project is underway, and no 
          later than July 1 of the year after any CMGC project is 
          completed.

          Related Legislation: AB 1549 (Vargas), which is currently 








          AB 2498 (Gordon)
          Page 3


          pending in the Assembly Appropriations Committee, would 
          authorize the San Diego Association of Governments to use both 
          design-sequencing and CMGC contracting methods for an unlimited 
          number of public transit projects, as specified.

          Staff Comments: The Legislature has generally taken a measured 
          approach to authorizing the use of new project delivery methods. 
           This usually involves some limited authorization initially, 
          either through a fixed number of projects or period of time, 
          which provides the opportunity for evaluation through data 
          collection and analysis.  For example, the Legislature 
          authorized Caltrans to use design-sequencing for a total of 24 
          projects over two phases, and evaluations are ongoing.  Initial 
          reports for design-sequencing have been mixed, with some 
          projects achieving moderate time and cost savings while others 
          experienced significant cost overruns.  On balance, Caltrans' 
          ability to target which projects might benefit from 
          design-sequencing has improved as they gained experience, so 
          they expect to show improved results for more recent Phase II 
          projects.  Initially, however, whenever the state authorizes a 
          new project delivery method, actual costs tend to exceed 
          estimated costs in the early stages.  The Legislature has never 
          authorized the use of the CMGC project delivery methodology, but 
          based on experience with previous authorizations of innovative 
          procurement methods, it is likely that actual costs for CMGC 
          projects would exceed estimated costs during the pilot period 
          authorized by this bill.  It is unknown whether total project 
          costs, including any unexpected escalation due to inexperience, 
          would exceed project costs under the design-bid-build method.

          A detailed 2009 report from the Utah Department of 
          Transportation (UDOT) on experience with 19 projects utilizing 
          the CMGC project delivery method describes the benefits of 
          having the contractor involved with in the design process.  The 
          report indicates that CMGC delivers projects more economically 
          than traditional design-bid-build and design-build methods, and 
          that cost savings are primarily achieved by minimizing risk and 
          implementing innovations, resulting in reductions in bid prices, 
          optimization of construction methodology, and minimization of 
          price adjustments during construction.  In UDOT's experience, 
          overall project costs are reduced by as much as 15 percent from 
          state average pricing models.  Staff notes that despite overall 
          long-term savings, the report suggests that most of the early 
          projects experienced costs that exceeded estimates.  After 








          AB 2498 (Gordon)
          Page 4


          gaining experience with the program and making adjustments to 
          various procedures, however, more recent UDOT projects 
          experienced more savings than anticipated.  One significant 
          limitation of CMGC noted in the report is the lack of 
          competitive pricing in the construction bid.  To address this 
          risk factor, UDOT began collecting price information in the 
          construction manager selection process, rather than selecting 
          contractors strictly though a qualifications-based evaluation.  
          The Committee may wish to consider whether the pilot program 
          authorized in this bill should include similar considerations of 
          price during the RFP process.

          Recommended Amendments: Staff recommends that additional 
          information be reported to the Legislature on estimated and 
          actual project costs, a description of challenges or unexpected 
          problems, and the number of change orders on CMGC projects.