BILL ANALYSIS                                                                                                                                                                                                    �



                                                                      



           ------------------------------------------------------------ 
          |SENATE RULES COMMITTEE            |                   SB 216|
          |Office of Senate Floor Analyses   |                         |
          |1020 N Street, Suite 524          |                         |
          |(916) 651-1520         Fax: (916) |                         |
          |327-4478                          |                         |
           ------------------------------------------------------------ 
           
                                         
                                 THIRD READING


          Bill No:  SB 216
          Author:   Yee (D)
          Amended:  4/25/11
          Vote:     21

           
           SENATE ENERGY, UTILITIES & COMM COMMITTEE  :  11-0, 04/05/11
          AYES:  Padilla, Fuller, Berryhill, Corbett, De Le�n, 
            DeSaulnier, Pavley, Rubio, Simitian, Strickland, Wright

           SENATE APPROPRIATIONS COMMITTEE  :  8-0, 05/26/11
          AYES:  Kehoe, Walters, Alquist, Lieu, Pavley, Price, 
            Runner, Steinberg
          NO VOTE RECORDED:  Emmerson


           SUBJECT  :    Public utilities:  intrastate natural gas 
          pipeline safety

           SOURCE  :     Author


           DIGEST  :    This bill designates the Public Utilities 
          Commission as the state authority responsible for 
          regulating and enforcing intrastate gas pipeline 
          transportation and pipeline facilities pursuant to federal 
          law, including the development, submission, and 
          administration of a state pipeline safety program 
          certification for natural gas pipelines.  This bill 
          requires the commission to evaluate current practices and 
          to determine whether compatible transmission safety 
          standards, as defined, should be adopted for the 
          enhancement of public safety with respect to the proximity 
                                                           CONTINUED





                                                                SB 216
                                                                Page 
          2

          of pipelines carrying liquid materials to 
          commission-regulated gas pipeline facilities, as defined, 
          that are intrastate transmission lines, as defined.  This 
          bill requires the commission, unless it determines that 
          doing so is preempted under federal law, to require the 
          installation of automatic shut-off or remote controlled 
          sectionalized block valves on intrastate transmission lines 
          that are located in a high consequence area, as defined, or 
          that traverse an active seismic earthquake fault if the 
          commission determines those valves are necessary for the 
          protection of the public.  This bill requires the owner or 
          operator of a commission-regulated gas pipeline facility 
          that is an intrastate transmission line to provide the 
          commission with a valve location plan, along with any 
          recommendations for valve locations, and would authorize 
          the commission to make modifications to the valve location 
          plan.

           ANALYSIS  :    Federal law and general orders of the 
          California Public Utilities Commission (CPUC) require the 
          commission to regulate gas transmission, distribution and 
          gathering pipeline facilities which include investor-owned 
          utilities, master-metered mobile home parks, storage 
          facilities, and propane operators.

          Federal Law and general orders of the CPUC set forth 
          requirements for the design, construction, testing, 
          maintenance and operation of utility gas gathering, 
          transmission and distribution piping systems.

          Federal Law and general orders of the CPUC require that 
          each transmission line have sectionalized block valves 
          placed at specified intervals and in specified locations 
          ranging from every 2  miles to every 10 miles and 
          classifies pipelines based on the types of facilities that 
          are within 220 yards of its location as follows:

          Class 1:  an offshore area or location that has 10 or fewer 
          buildings intended 
                         for human occupancy;

          Class 2:  any location that has more than 10 but fewer than 
          46 buildings 
                         intended for human occupancy;

                                                           CONTINUED





                                                                SB 216
                                                                Page 
          3


          Class 3:  any location that has 46 or more buildings 
          intended for human     
                         occupancy; or an area where the pipeline 
          lies within 100 yards of  
                         either a building or a small, well-defined 
          outside area (such as a  
                         playground, recreation area, outdoor 
          theater, or other place of 
                         public assembly) that is occupied by 20 or 
          more persons on at least 
                         5 days a week for 10 weeks in any 12-month 
          period.

          Class 4:  any location where buildings with four or more 
          stories above 
                         ground.

           Federal law  defines a High Consequence Area as an area 
          including all class 3 and class 4 locations and some class 
          1 and class 2 locations with unique circumstances related 
          to surrounding populated facilities.

           This bill
           
           1.Defines a commission-regulated gas pipeline facility to 
            include transmission, distribution and gathering pipeline 
            facilities which include investor-owned utilities, 
            master-metered mobile home parks, storage facilities, and 
            propane operators. 

          2.Requires each owner or operator of a commission-regulated 
            gas pipeline facility that is an intrastate transmission 
            line to provide the commission with a valve location 
            plan, along with any recommendations for valve locations. 
            The commission may make modifications to the valve 
            location plan or provide for variations from any location 
            requirements adopted by the commission pursuant to this 
            section that it deems necessary or appropriate and 
            consistent with protection of the public. 

          3.Requires the Public Utilities Commission to require 
            operators of natural gas transmission pipelines to 
            install automatic or remote-controlled shut off valves on 

                                                           CONTINUED





                                                                SB 216
                                                                Page 
          4

            natural gas pipelines in areas of high population density 
            or which cross active seismic faults. Pipeline operators 
            are authorized under the bill to recover the costs of 
            these upgrades from natural gas ratepayers.

          4.Requires the commission to additionally establish action 
            timelines, adopt standards for how to prioritize 
            installation of automatic shut-off or remote controlled 
            sectionalized bock vales, ensure that remote and 
            automatic shut-off valves are installed as quickly as is 
            reasonably possible, and establish ongoing procedures for 
            monitoring progress in achieving the requirements of the 
            bill.  

          5.Designates the CPUC as the state authority for the 
            "811/Call Before You Dig" program established by the 
            Secretary of the Department of Transportation.

           Background

          Gas Transmission Pipeline Flow  .  The explosion created a 
          76-foot-long crater and the released natural gas ignited.  
          A 28-foot segment of the pipeline (Line 132) was shattered 
          out of the ground and blasted about 100 feet away.  Over an 
          hour passed before the valves were shut and the flow of gas 
          stopped.  The explosion occurred at 6:11 p.m.; the upstream 
          valve was closed at 7:30 p.m.; and the downstream valve was 
          closed at 7:45 p.m.  At about 7:42 p.m. flames at the 
          rupture location had diminished to the point that the 
          firefighters were able to get closer to the ruptured 
          pipeline.  Once the ruptured section was isolated and the 
          gas flow was stopped, the resulting fire from the ruptured 
          line self-extinguished.  Later that evening, PG&E isolated 
          the natural gas distribution system serving residences in 
          the area, and within a minute of stopping the gas flow at 
          about 11:30 p.m., fires from escaping natural gas at 
          damaged houses went out.

          The flows to Line 132 were controlled by manual valves 
          which are hand-operated by wheel and gear assembly or by a 
          wrench with an indicator to show whether it is open or 
          closed.   Many have questioned whether other technologies 
          such as automatic or remotely-controlled valves should be 
          in greater use so that gas flows can be interrupted more 

                                                           CONTINUED





                                                                SB 216
                                                                Page 
          5

          quickly.  After the San Bruno explosion, PG&E was able to 
          detect pressure changes in Line 132 from its control center 
          but could not stop the flow of gas from the center due to a 
          lack of remotely-controlled valves which necessitated the 
          dispatch of a crew to manually stop the gas flow.  That 
          crew was delayed due to traffic.  However the greatest 
          factor in the delay to shut down the pipes was that the 
          utility did not know the cause of the explosion.  PG&E 
          control room operators saw drops in gas pressure on the 
          transmission pipeline system and were also aware that there 
          had been an explosion in San Bruno but were unable to 
          connect the two occurrences for some time.  Reports to the 
          control room included speculation of an airplane crash or 
          gas station explosion.   
          For more information on the San Bruno tragedy, see the 
          Senate Energy, Utilities and Communications Committee 
          analysis.  
           
           Related Federal Legislation   

          There are three measures pending in Congress which also 
          call for the installation of automatic or remote valves on 
          gas transmission pipelines.

           Related State Legislation   

          AB 56 (Hill), 2010-11 Session, implements a number of 
          public safety measures with regard to natural gas pipeline 
          facilities, including requiring the owner or operator of a 
          gas pipeline to develop a public safety program and a 
          facilities modernization program, and requiring the CPUC to 
          track proposed repairs to gas facilities to determine if 
          the repairs were made.

           FISCAL EFFECT  :    Appropriation:  No   Fiscal Com.:  Yes   
          Local:  Yes

          According to Senate Appropriations Committee: 

                                          Fiscal Impact (in 
          thousands)

           Major Provisions                    2011-12   2012-13       
           2013-14      Fund  

                                                           CONTINUED





                                                                SB 216
                                                                Page 
          6

          Development of standards                $240                
           Special* 
          Increased natural gas costs        Likely in the low 
          millions over             Various
             to state agencies                  the next several 
          years                    

          * Public Utilities Commission Utilities Reimbursement 
          Account

           SUPPORT  :   (Verified  5/27/11)

          American Red Cross, California Chapters
          Board of Supervisors, San Mateo County
          California Emergency Nurses Association
          California Professional Firefighters
          California State Firefighters Association
          Consumer Attorneys of California
          San Diego Gas & Electric Company (if amended)
          San Francisco Firefighters
          San Mateo County Board of Supervisors
          San Mateo County Community College District
          San Mateo County Firefighters, IAFF Local 2400
          Sempra Energy utilities 
          Southern California Gas Company 

           ARGUMENTS IN SUPPORT  :    According to the author's office, 
          this bill has two primary goals, to establish standards to 
          separate gas transmission pipelines from water mains and to 
          require the installation of automatic or 
          remotely-controlled valves on all pipelines that cross an 
          active seismic earthquake fault or are located within a 
          High Consequence Area.


          RM:rm  5/31/11   Senate Floor Analyses 

                         SUPPORT/OPPOSITION:  SEE ABOVE

                                ****  END  ****





                                                           CONTINUED





                                                                SB 216
                                                                Page 
          7














































                                                           CONTINUED