BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  SB 250
                                                                  Page  1

          Date of Hearing:   June 12, 2012

                   ASSEMBLY COMMITTEE ON WATER, PARKS AND WILDLIFE
                                Jared Huffman, Chair
                    SB 250 (Rubio) - As Amended:  August 29, 2011
           
          SUBJECT  :   Delta export water conveyance: statutory deadline 

           SUMMARY  :   Requires, by February 15, 2013, that environmental 
          review and permitting be concluded for some as-yet-unspecified 
          new export water conveyance through the Sacramento-San Joaquin 
          Delta (Delta) which must then be built by December 31, 2025.  
          Specifically,  this bill  :  

          1)Declares California's water infrastructure is antiquated and 
            vulnerable to hazards, including earthquake.

          2)Requires the Department of Water Resources (DWR) to complete, 
            by February 15, 2013, the environmental review and planning 
            for some type of new, unspecified, export water conveyance 
            facilities in the Delta, either separate from or as part of 
            the current Bay Delta Conservation Plan (BDCP) process, and 
            then construct those facilities by December 31, 2025.

           EXISTING LAW  :

          1)Specifies, in accordance with the California Environmental 
            Quality Act (CEQA), that a public agency is prohibited from 
            approving a project that could have significant effects on the 
            environment if there are feasible alternatives or feasible 
            mitigation measures available which would substantially lessen 
            the significant environmental effects of that project.

          2)Requires, under CEQA, that where a project will require a 
            joint Environmental Impact Report under CEQA and a federal 
            Environmental Impact Statement under the National 
            Environmental Policy Act (NEPA), the CEQA lead agency must 
            involve the federal agency in the preparation of the joint 
            document or federal law will prohibit the federal agency from 
            relying upon the state-prepared document.

          3)States it is the policy of the state to reduce reliance on the 
            Delta in meeting California's future water supply needs 
            through a statewide strategy of investing in improved regional 
            supplies, conservation and water use efficiency.








                                                                  SB 250
                                                                  Page  2


          4)Declares that the coequal goals for the Delta are providing a 
            more reliable water supply for California and protecting, 
            restoring, and enhancing the Delta ecosystem.  Requires that 
            the coequal goals be achieved in a way that protects and 
            enhances the unique cultural, recreational, natural resource, 
            and agricultural values of the Delta as an evolving place.

          5)Requires, under the Sacramento-San Joaquin Delta Reform Act of 
            2009 (Delta Reform Act), that the Delta Stewardship Council 
            (Council) adopt a long-term management plan for the Delta 
            (Delta Plan) that meets the coequal goals.  Requires that 
            projects in the Delta be consistent with the Delta Plan, as 
            determined by the Council upon the appeal of any party.

          6)Requires that if the BDCP is to be included in the Delta Plan 
            and eligible for public funding, it must meet the California 
            Natural Community Conservation Planning Act (NCCPA) and 
            incorporate, in its CEQA document, a comprehensive review and 
            analysis that addresses, but is not limited to, operational 
            requirements and flows necessary for recovering the Delta 
            ecosystem and restoring fisheries; a reasonable range of Delta 
            conveyance alternatives and their potential for resiliency and 
            recovery in the event of catastrophic loss caused by 
            earthquake or flood or other natural disasters; and, water 
            quality, flood management, and climate change impacts.
           
           FISCAL EFFECT  :   Unknown.  This bill has not undergone a 
          relevant fiscal analysis.  As introduced in the Senate this bill 
          made minor changes to the notice required when drilling a well.  
          It was then gutted and amended to create an exemption from 
          judicial review under CEQA for certain types of energy projects. 
           It was then gutted and amended to make technical, 
          nonsubstantive, nonfiscal changes regarding the addition or 
          deletion of a class of projects from the list of CEQA exemptions 
          and passed out of the Senate in that form.  

           COMMENTS  :   

          The BDCP process has encountered significant delays when best 
          available science has failed to demonstrate that the proposal is 
          scientifically supported.  Currently, the state and federal 
          agency leads for the BDCP process are reevaluating what elements 
          of a proposed project, including sizes of potential new 
          infrastructure, water operations, acreages of restoration, and 








                                                                  SB 250
                                                                  Page  3

          other actions, could constitute a project that meets the coequal 
          goals and can be permitted under the NCCPA, federal Endangered 
          Species Act (FESA), and other state and federal laws. 

           Background
           The environmental collapse of the Delta, particularly its 
          fisheries, is well-documented and has led to the listing of many 
          native fish species under FESA and the California Endangered 
          Species Act (CESA).  The Delta is also the hub of California's 
          water export infrastructure.  There have been many attempts to 
          address the conflict inherent in requiring an ecosystem that is 
          home to more than 750 animal and plant species to also provide 
          part of the export water supply for 25 million citizens in 
          southern California and 3 million acres of agricultural land, 
          principally in the San Joaquin Valley.  The BDCP is the most 
          recent.  

          The BDCP seeks to obtain 50-year authorizations that satisfy 
          FESA and CESA for State Water Project export facilities in the 
          Delta through a federal Habitat Conservation Plan (HCP) and 
          state Natural Community Conservation Plan (NCCP).  As explained 
          in more detail later, that would also result in new FESA 
          authorizations for the federal Central Valley Project (CVP).  
          Since 2006 the BDCP planning process, which began as an offshoot 
          to the CALFED Bay-Delta Program, has attempted to find the 
          appropriate mix of new infrastructure, ecosystem restoration, 
          and other actions that will both increase water exports out of 
          the Delta over the levels currently allowed by CESA permits and 
          FESA authorizations, and restore the Delta ecosystem.  That has 
          proven elusive despite the fact that, as the author of this bill 
          points out, the BDCP planning process has expended over $153 
          million for planning and held over 300 meetings.

          The level of time and money expended on BDCP combined with 
          growing likelihood that while there may be a more reliable 
          supply of water, exports may not increase, has caused intense 
          frustration on the part of the export water agencies that are 
          funding the planning process and at various times those agencies 
          have threatened to pull their support.  In response to one such 
          threat, on August 9, 2011, California Natural Resources Agency 
          Secretary John Laird sent a letter to Deputy Secretary of the 
          Interior David Hayes and Undersecretary for the Department of 
          Commerce Dr. Jane Lubchenco, thanking them for their leadership 
          and commitment to the BDCP process and confirming that the state 
          and federal agencies working on BDCP had agreed to an 








                                                                  SB 250
                                                                  Page  4

          "aggressive schedule" that would result in a completed "Effects 
          Analysis" of BDCP by March 2012 and "a draft EIS/EIR by June 
          2012 if not sooner."  Attached to Secretary Laird's letter was a 
          document entitled BDCP EIR/EIS Schedule 8/9/11 (EIR/EIS 
          Schedule) and a second document entitled BDCP Chapter 5 (Effects 
          Analysis) Schedule 8/9/11 (EA Schedule).

          The Effects Analysis is the heart of BDCP.  It is intended to 
          provide the best scientific assessment of the likely effects of 
          BDCP actions on the species of concern and ecological processes 
          of the Bay-Delta system.  In other words, it is the scientific 
          rationale and evidence that the approach taken in the BDCP can 
          be successful.  That means it is also the lynchpin of the BDCP 
          EIS/EIR.  The EA Schedule indicated a final Chapter 5 Effects 
          Analysis would be complete on April 9, 2012 and then the BDCP 
          public review draft of all Chapters could be released on June 
          22, 2012.  In keeping with that Schedule, a final draft of the 
          EIS/EIR would issue December of 2012 and, following required 
          hearings and response to comment, the agencies would certify and 
          approve a final document with a federal Record of Decision and 
          state Notice of Determination on February 2013.  This bill takes 
          the August 2011 Schedule and codifies that February date for 
          approving the project.  Less clear is what the 2025 construction 
          completion date in this bill is based upon.

           The Deadlines in this Bill Are Already Delayed
           Following release of the Schedules, the Natural Resources Agency 
          directed the BDCP consultant team to analyze only one project 
          alternative in the Effects Analysis:  1A.  The primary features 
          of Alternative 1A were five new intakes out of the Sacramento 
          River in the north Delta with new pipeline/tunnel diversions 
          capable of exporting up to 15,000 cubic feet per second (cfs) of 
          water (an increase over existing export rates) and up to 113,000 
          acres of habitat restoration and preservation.  By April 13, 
          2012, when the consultant team made various segments of the 
          Chapter 5 Effects Analysis publicly available, the BDCP was 
          already behind schedule.  More importantly, following a "Red 
          Flag" review of the Effects Analysis by the California 
          Department of Fish and Game, the U.S. Fish and Wildlife Service 
          (USFWS), the National Marine Fisheries Service (NMFS),  and the 
          U.S. Department of Interior, Bureau of Reclamation 
          (Reclamation), it was clear that many of the conclusions in the 
          Effects Analysis were "essentially unsupported," "unjustified," 
          "contradictory," and "not protective" of at-risk native fish and 
          that it was difficult to demonstrate that the proposed project, 








                                                                  SB 250
                                                                  Page  5

          when compared to existing conditions, would contribute to 
          species recovery -- which is the legally-required standard under 
          the NCCPA.  

          In response to the "Red Flag Review," Natural Resources 
          Secretary Laird sent a letter to Deputy Secretary of the 
          Interior Hayes on May 3, 2012 stating, "we have made significant 
          headway in formulating a proposed project for the �BDCP] that 
          will meet the dual goals of water supply reliability and Delta 
          ecosystem restoration. Thanks to our continued efforts together, 
          we are on track to present a real and workable plan?  That said 
          there will be some workable delays in the release of the 
          environmental documents.   From the outset, we have all agreed 
          that science should drive the design of the project and our 
          plans for its implementation. The fish and wildlife agencies are 
          currently reviewing and responding to a substantially improved 
          scientific analysis of habitat restoration, water flows, and 
          other ecological measures to achieve the regulatory standards of 
          �FESA and NCCPA].  As a result, we anticipate that we will soon 
          be able to announce some significant adjustments in the overall 
          program that will reflect our commitment to using the best 
          science." 
           
          The Legal Effect of this Bill is Unclear
           It is unclear what legal force and effect the deadlines in this 
          bill for completing environmental review and building a project 
          would have, if any.  With respect to CEQA, the lead agency deems 
          the environmental review complete when it is satisfied that 
          there is substantial evidence in the record that it has 
          incorporated project alternatives or mitigation measures that 
          have reduced potentially significant environmental impacts to 
          below a level of significance.  If it has identified impacts 
          which will still remain significant after all feasible 
          alternatives and mitigation, it must also adopt a statement of 
          overriding considerations.  Forcing an agency to deem a project 
          "complete" on a date certain whether or not its record is 
          complete would only create legal vulnerability.

           The State Legislature Cannot Set a Deadline for the Federal 
          Government
           The BDCP environmental review and analysis is occurring as a 
          joint federal and state EIS/EIR.  DWR operates the SWP and 
          Reclamation operates the CVP but, in fact, both projects are 
          operated jointly and have been since the state and federal 
          governments entered in to the 1986 Coordinated Operation 








                                                                  SB 250
                                                                  Page  6

          Agreement (COA).  So, while the BDCP contemplates potential new 
          export water conveyance facilities as units of the SWP, their 
          construction and operation would impact these joint operations 
          and trigger a federal ESA re-consultation on the CVP. In 
          addition, the USFWS and NMFS would need to approve the BDCP as 
          an HCP, which is a major federal action under NEPA.  Therefore, 
          while DWR is the state lead agency on the BDCP project, 
          Reclamation, USFWS and NMFS are all federal co-lead agencies as 
          well.

          The federal government is sovereign and cannot be subject to 
          state law without its consent.  This bill could cause additional 
          legal uncertainty, litigation, and policy confusion because the 
          deadlines it sets would be unenforceable on the parties 
          responsible for the EIS half of the EIS/EIR.  There was language 
          in federal legislation that instructed the federal agencies to 
          jointly coordinate their efforts with the state on BDCP with the 
          goal of reaching a February 15, 2013 deadline to complete the 
          EIS/EIR, but that language was advisory and specified that it 
          did not modify existing federal law requirements such as 
          adequate NEPA review.  If this bill forced the SWP to take a 
          separate approach from the CVP in meeting its CESA and ESA 
          obligations, or allowed the state to be compelled to do so by 
          court action, state and federal water operations could decouple 
          and become adversarial - an outcome it is unlikely that any 
          party would want. 

           The Legislature Has Already Weighed In
           In the past four years, the Assembly Water, Parks and Wildlife 
          Committee (AWPW) and the Senate Natural Resources and Water 
          Committee (SNRW) have held multiple oversight hearings on Delta 
          issues that included BDCP or addressed BDCP exclusively.  These 
          bipartisan oversight hearings have allowed members from both 
          houses and different regions of California to get up-to-date 
          information on the BDCP and address the state administration 
          directly.  In just the past two years these included a May 10, 
          2011 AWPW Delta Governance and the Delta Plan hearing, an 
          October 19, 2011 AWPW Bay Delta Conservation Plan Status and 
          Update, a February 28, 2012 SNRW Update on Delta Plans and a 
          March 13, 2012 SNRW Delta Plan and Bay-Delta Conservation Plan 
          hearing discussing the BDCP Effects Analysis, among other 
          topics. 

          On October 25, 2011, California Senator Michael Rubio, the 
          author of this bill, sent a letter to U.S. Department of the 








                                                                  SB 250
                                                                  Page  7

          Interior Secretary Ken Salazar and California Natural Resources 
          Secretary Laird expressing "strong support for the �BDCP 
          Schedule] to complete the effects analysis and draft �EIS/EIR] 
          by June 2012 and finalize the environmental review process by 
          February 2013."  Senator Rubio stated, "I also applaud your 
          efforts to maintain transparency and ensure that all interest 
          groups have a vested voice in the process. The BDCP is crucial 
          to protecting our state's water system and preserving the Delta. 
           It is also the single most important project for California's 
          economy as it is projected to create at least 129,000 jobs over 
          the next 7 years with no cost to the State General Fund."  
          Senator Rubio went on to advise that from his point of view "the 
          urgency of this issue stems from the risk of earthquake to the 
          Delta region."  On November 2, 2011, Senator Rubio then held a 
          "Town Hall" where constituents were able to speak directly to 
          State officials regarding the BDCP, including California Natural 
          Resources Agency Deputy Secretary Jerry Meral, and DWR Director 
          Mark Cowin, among others.  

          In contrast, on November 22, 2011, seventeen members of the 
          California Legislature wrote to U.S. Interior Secretary Salazar, 
          California Natural Resources Agency Secretary Laird, and Bureau 
          of Reclamation Commissioner Mike Connor, to express "serious 
          concerns" with the direction of the BDCP including "a failure of 
          transparency in the process; the limited set of alternatives 
          being considered; scientific inadequacy, including a lack of 
          flow criteria for the San Francisco Bay and Sacramento-San 
          Joaquin Delta Estuary; the absence of cost/benefit analyses; and 
          the undue influence granted to State and Federal export water 
          agencies �in the process] to the exclusion of a meaningful role 
          for other public interests."  These seventeen legislators were 
          concerned about "a rushed timeline for completing the plan, 
          making adequate scientific analysis and consensus-building 
          impossible."

          Thereafter, on December 19, 2011, Senator Rubio and twenty-one 
          other legislators sent a letter to Secretary of the Interior 
          Salazar, California Natural Resources Secretary Laird, and 
          Bureau of Reclamation Commission Connor urging them to "keep the 
          �BDCP] process on track toward the release of a draft �EIS/EIR] 
          next year and a final Record of Decision in February 2013" and 
          reiterating the amount of money spent on planning and the job 
          potential of the project.

           Supporting arguments  :  The author states that this bill is 








                                                                  SB 250
                                                                  Page  8

          necessary because "seismic activity could potentially devastate 
          California's Bay Delta Region and jeopardize the water supply 
          for 25 million people in Southern California and hundreds of 
          thousands of acres of highly productive farmland" and that 
          "building and improving our Delta conveyance will create jobs 
          and give a boost to California's economic recovery" and that 
          this bill will ensure that BDCP "remains on schedule."  
          Supporters state that "the timeline to finish BDCP is consistent 
          with the schedule endorsed by the California Natural Resources 
          Agency and the U.S. Department of Interior" and that the BDCP 
          will "be a significant step in restoring the ecosystem and 
          providing infrastructure improvements that are necessary to 
          protect public health and safety and revitalize California's 
          economy."  

           Opposing arguments  :  Opponents state that "any legislative 
          efforts to speed up the �BDCP] would preclude achieving the 
          coequal goals" for the Delta and that "the BDCP is a long way 
          from adopting a project alternative that will contribute to 
          recovery of the key fish species" including that the "draft 
          effects analysis finds that the project alternative would 
          actually increase the risk of extinction for some species."  
          Opponents also note that this bill, as currently drafted, 
          "requires the Department of Water Resources to complete its 
          development of conveyance facilities by February 2013 and 
          requires construction of such a facility by 2025.   However, a 
          legislatively mandated date for completion of BDCP could be read 
          to override the essential analysis required by state laws, 
          including the Delta Reform Act requirements regarding 
          development, review, and approval of BDCP...Ensuring that BDCP 
          uses sound science and analysis is critical to its success, and 
          the Administration has already acknowledged that more work (and 
          more time) is needed to complete development of BDCP.  By 
          imposing this unnecessary statutory deadline, �this bill] could 
          increase the challenges facing the BDCP process and decrease its 
          likelihood of success."

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           


          Alhambra Chamber of Commerce
          American Council of Engineering  Companies of California








                                                                  SB 250
                                                                  Page  9

          Association of California Water Agencies
          Bell Gardens Chamber of Commerce
          Burbank Chamber of Commerce
          Burbank Water and Power
          California Building Industry Association
          California Chamber of Commerce
          California-Nevada Conference of Operating   Engineers
          California State Council of Laborers
          Cerritos Regional Chamber of Commerce
          City of Arvin
          City of Avenal
          City of Burbank
          City of Coalinga
          City of Corcoran
          City of Delano
          City of Dinuba
          City of Downey
          City of Fowler
          City of Huron
          City of Kerman
          City of Lemoore
          City of Mendota
          City of Merced
          City of Orange Cove
          City of Parlier
          City of San Joaquin
          City of Selma
          City of South El Monte
          City of Wasco
          County of Fresno
          County of Kings
          County of Kern
          County of Tulare
          Calleguas Municipal Water District
          Construction Industry Coalition on Water Quality
          Cucamonga Valley Water District
          Downey Chamber of Commerce
          Eastern Municipal Water District
          El Monte/South El Monte Chamber of Commerce
          Fresno County Farm Bureau
          Gateway Chambers Alliance
          Irwindale Chamber of Commerce
          Kern County Water Agency
          Kings County Farm Bureau
          La Verne Chamber of Commerce








                                                                  SB 250
                                                                  Page  10

          Long Beach Area Chamber of Commerce
          Manhattan Beach Chamber of Commerce
          Mayor Bill Bogaard, City of Pasadena
          Metropolitan Water District of Southern California
          Mojave Water District
          Palmdale Water District
          Palos Verdes Peninsula Chamber of Commerce & Visitors' Center
          Redondo Beach Chamber of Commerce and Visitors Bureau
          Regional Chamber of Commerce - San Gabriel Valley
          San Diego County Water Authority
          San Gabriel Valley Council of Governments
          San Gabriel Valley Economic Partnership
          San Gabriel Valley Legislative Coalition of Chambers
          Santa Clara Valley Water District
          Simi Valley Chamber of Commerce
          South Bay Association of Chambers of Commerce
          South Gate Chamber of Commerce
          Southwest California Legislative Council
                                                                                     State Building and Construction Trades Council of California
           Support - continued
           
          Three Valleys Municipal Water District
          Torrance Area Chamber of Commerce
          Tulare County Farm Bureau
          United Chambers of Commerce San Fernando Valley and Region

          Upper San Gabriel Valley Municipal Water District
          Walnut Valley Water District
          Western Growers
          Western Municipal Water District
          Westlands Water District

           Opposition 
           

          Defenders of Wildlife 
          Delta Counties Coalition
          Natural Resources Defense Council
          Planning and Conservation League
          Sierra Club California
          Solano County Board of Supervisors
          Yolo County
           
          Analysis Prepared by  :    Tina Cannon Leahy / W., P. & W. / (916) 
          319-2096 








                                                                  SB 250
                                                                  Page  11