BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  SB 293
                                                                  Page  1


          SENATE THIRD READING
          SB 293 (Padilla)
          As Amended August 26, 2011
          Majority vote 

           SENATE VOTE  :36-0

           BUSINESS & PROFESSIONS         8-0                  JUDICIARY   
          9-0                 
           
           ----------------------------------------------------------------- 
          |Ayes:|Hayashi, Bill Berryhill,  |Ayes:|Feuer, Wagner, Atkins,    |
          |     |Allen, Eng, Hagman, Hill, |     |Dickinson, Beth Gaines,   |
          |     |Ma, Smyth                 |     |Huber, Jones, Monning,    |
          |     |                          |     |Wieckowski                |
          |-----+--------------------------+-----+--------------------------|
          |     |                          |     |                          |
           ----------------------------------------------------------------- 
           APPROPRIATIONS      17-0                                        
           
           ----------------------------------------------------------------- 
          |Ayes:|Fuentes, Harkey,          |     |                          |
          |     |Blumenfield, Bradford,    |     |                          |
          |     |Charles Calderon, Campos, |     |                          |
          |     |Davis, Donnelly, Gatto,   |     |                          |
          |     |Hall, Hill, Lara,         |     |                          |
          |     |Mitchell, Nielsen, Norby, |     |                          |
          |     |Solorio, Wagner           |     |                          |
          |-----+--------------------------+-----+--------------------------|
          |     |                          |     |                          |
           ----------------------------------------------------------------- 
           SUMMARY  :  Adjusts the rights and time periods governing payment 
          and claims for payment between owners, contractors and 
          subcontractors by speeding the time period for contractors to 
          pay subcontractors, reducing the time by which a subcontractor 
          may make claims for nonpayment against a contractor on a public 
          works project, exempting laborers from preliminary notification 
          requirements and any deadline to enforce a claim for private 
          works of improvement, and prohibiting a public entity from 
          retaining more than 5% of a contract price until final 
          completion and acceptance of a project.  Specifically, this 
          bill  :   

          1)Decreases, from 10 to 7, the number of days by which a prime 








                                                                  SB 293
                                                                  Page  2


            contractor or subcontractor must pay a subcontractor after 
            receiving a progress payment, unless otherwise agreed to in 
            writing. 

          2)Requires a subcontractor to give written notice to the surety 
            and bond principal that he or she is enforcing a claim prior 
            to completion or recordation of the Notice of Completion (NOC) 
            of a project, except as specified, if the 20-day public works 
            preliminary notice was required by any person that has no 
            direct contractual relationship with the contractor and who 
            has not given notice as provided in Civil Code Section 3098, 
            that person may enforce a claim by giving written notice to 
            the surety and bond principal within 15 days after recordation 
            of a notice of completion.  If no notice of completion has 
            been recorded, the time for giving written notice to the 
            surety and the bond principal is extended to 75 days after 
            completion of the work of improvement.  This provision would 
            not apply in the event that all payments, other than those 
            disputed in good faith, have been made to a subcontractor who 
            has a direct contractual relationship with the general 
            contractor to whom the claimant has provided materials or 
            services.

          3)Exempts a laborer, as defined, from preliminary notice 
            requirements to a surety and bond principal and any deadline 
            to enforce a claim after the completion of a project for 
            private works of improvement.

          4)Prohibits a public entity from retaining more than 5% of a 
            contract price until final completion and acceptance of a 
            project.   

          5)Requires that retention proceeds between an original 
            contractor and a subcontractor, or between two subcontractors, 
            not exceed 5% of payment or contract price.  Does not apply if 
            the contractor provides written notice to the subcontractor, 
            prior to or at the time that the bid is requested, that a bond 
            may be required and the subcontractor subsequently is unable 
            or refuses to furnish to the contractor a performance or 
            payment bond issued by an admitted surety insurer.

          6)Prohibits progress payments on public works contracts from 
            being made in excess of 100% of the percentage of actual work 
            completed.








                                                                  SB 293
                                                                  Page  3



          7)Authorizes a public entity to retain more than 5% of the 
            contract price in public works projects under the following 
            conditions: 
                
             a)   For projects awarded by state departments, as defined, 
               the project is substantially complex and the department 
               includes this finding and the actual retention amount in 
               the bid documents; 

             b)   For projects awarded by local entities, as specified, 
               the governing body of the local public entity has approved 
               a majority vote during a properly noticed and normally 
               scheduled public hearing prior to bid that the project is 
               substantially complex, and includes this finding and the 
               actual retention amount in the bid documents; and, 

             c)   Retention proceeds between an original contractor and a 
               subcontractor, or between two subcontractors, shall not 
               exceed the specified retention percentage in the contract 
               between the public entity and the original contractor. 

          8)Sunsets these retention provisions on January 1, 2016.

          9)Defines "public entity" to mean the state, including every 
            state agency, office, department, division, bureau, board, or 
            commission, the California State University, the University of 
            California, a city, county, city and county, including 
            chartered cities and chartered counties, district, special 
            district, public authority, political subdivision, public 
            corporation, or nonprofit transit corporation wholly owned by 
            a public agency and formed to carry out the purposes of the 
            public agency.

           FISCAL EFFECT  :  According to the Assembly Appropriations, in 
          general, reducing the amount of retention that can be withheld 
          would to some extent increase the likelihood that a contractor 
          or subcontractor would fail to fully perform their work, and 
          thus could lead to higher costs to the contracting entity 
          related to the administrative burden, project delays, and 
          potential litigation associated with finding alternative means 
          to complete the work.

          1)In most cases, the fiscal impact to the state would likely be 








                                                                  SB 293
                                                                  Page  4


            minor. According to the Department of General Services, the 
            use of a retention amount exceeding 5% is an exception on 
            state projects, and is used generally only on smaller 
            projects. 

          2)The University of California has a 5% retention practice.  
            Caltrans contracts funded at least in part with federal monies 
            (85% of all Caltrans capital outlay) have no retention 
            provisions, as required by federal law.

          3)The exception at the state level is the California State 
            University (CSU), which is opposed to this bill and argues 
            that limiting retention will remove a tool available to 
            protect against contractor non-performance.  CSU cites the 
            example of an $18 million project that, based on the current 
            schedule is projected to finish two years behind schedule.  
            Were this bill in effect, about $900,000 in retention would be 
            withheld, but the university would be entitled to almost $2 
            million in liquidated damages for late completion.  This would 
            leave CSU $1.1 million short, which might have to be recovered 
            from the contractor through legal means, thus entailing even 
            more costs.  CSU argues that in these situations, it is 
            preferable to ratchet up the retention level above 5% rather 
            than attempt to seek reimbursement on the back end of a 
            project.

          4)The fiscal impact on local governments could be more 
            significant as they are generally more likely to use a 
            retention amount exceeding 5%, and thus would be restricted by 
            this bill.  Any additional costs associated with this 
            limitation would not be reimbursable, however.  In addition, 
            unlike previous legislation proposed to limit retention, this 
            bill allows local governments, as well as state agencies, to 
            establish higher retention on projects they deem to be 
            complex.

           COMMENTS  :  According to the author this bill presents a 
          multi-prong approach to assisting the state's ailing 
          construction industry.  

          The bill relates to payments made to individuals hired to 
          perform work on public and private construction projects, and 
          the cash flow between public entities and homeowners, general 
          contractors, subcontractors, and suppliers.  This bill also 








                                                                  SB 293
                                                                  Page  5


          revises the terms and conditions, as well as the timeframe in 
          which those payments must be made.  Below are the primary 
          components of the measure relating to payments discussed below:  
          progress payments, claims to the surety and bond principal for 
          both private and public works, and retention. 

          The bill reduces the time period a general contractor has to pay 
          his or her subcontractor after the general contractor has been 
          paid a progress payment from the owner.  This time period is 
          reduced from 10 to 7 days.  It is unclear what percentage of 
          payments occur in the last 3 days of this window, and whether 
          the reduction to seven days will have any significant impact.   

          In public works projects, instead of a lien claim, there are 
          claims that can be made against the surety and bond principal, 
          referred to as a bond claim.  Subcontractors routinely file this 
          preliminary notice prior to the commencement of work and 
          receiving payment for services as a protective measure to inform 
          the surety or public entity that work will be performed for 
          payment.  If a subcontractor files this 20-day preliminary 
          notice and is not paid after 10 days of supplying labor and 
          materials, the subcontractor can file a stop notice with the 
          public entity to withhold the disputed amount from the general 
          contractor.  The public entity will only release the withheld 
          amount to the general contractor once a stop notice release is 
          received from the claimant attesting that payment for service 
          has been rendered.  

          However, if a subcontractor does not file a 20-day preliminary 
          notice, provides labor and services, and is not paid, the 
          subcontractor is ineligible to file a stop notice with the 
          public entity.  The subcontractor must wait until the project is 
          completed or until a NOC is filed to submit a claim to the 
          surety for payment of services.  This means, that even if a 
          project is not completed until a year after an unpaid 
          subcontractor provides labor or materials, but the subcontractor 
          did not file a 20-day preliminary notice, that subcontractor 
          will have to wait a year before receiving payment through a 
          surety.  In this case, the subcontractor can make a claim within 
          15 days after recordation of a NOC, or if no NOC has been 
          recorded, up to 75 days after the NOC.  
          
          Many public entities require that contractors carry a payment 
          bond to ensure that contractors pay all debt related to a 








                                                                  SB 293
                                                                  Page  6


          construction project.  This bill would clarify the exemption for 
          public and private works project laborers from the preliminary 
          notice requirements regarding payment bond claims.  Under 
          existing law, laborers are exempt from the preliminary notice 
          requirements on private and public works projects.  Existing law 
          requires a preliminary notice to be served prior to enforcement 
          of a payment bond claim in accordance with Civil Code Sections 
          8200 (private works) or 9300 (public works).  

          Retention proceeds represent a percentage of the amount of a 
          contract that is withheld from a progress payment by the public 
          entity to the original contractor, or the original contractor to 
          one of its subcontractors.  By withholding a percentage of a 
          contract, the public entity or the original contractor maintains 
          a degree of financial control over a project.  In general, the 
          public entity or the original contractor withholds at least 5% 
          of payment until the contract is completed to the satisfaction 
          of the public entity or original contractor.  In practice, the 
          most common rule is said to be retention of 10%.  Under this 
          bill, the amount public entities could retain would be no more 
          than 5%.

          The bill is opposed by some local government groups.  The 
          California Coalition for Adequate School Housing (CASH) argues 
          that the bill improperly repeals current statutory flexibility 
          for public agencies to negotiate the conditions for retention 
          proceeds in their contracts.  School districts, in good faith, 
          negotiate contract provisions and typical retention amounts are 
          negotiated at approximately 10% of the contract value.  If a 
          contractor and a public agency wish to limit retention proceeds 
          to 5% - as the bill seeks to achieve - current law allows for 
          it.  CASH and others argue that retention is necessary for 
          public agencies to ensure:  1) prompt completion of a project; 
          2) that contractors return to a project to complete all contract 
          requirements, including small unprofitable punch-list items; 3) 
          there are sufficient funds for public agencies to correct 
          defective work if a contractor fails to do so; 4) to have 
          sufficient funds to honor Stop notice claims filed by 
          subcontractors and suppliers; and, 5) to have sufficient funds 
          withheld in order to pay workers in the event contractors have 
          failed to properly pay prevailing wage as determined by the 
          Department of Industrial Relations as required by state law.  By 
          prohibiting contract withholdings from exceeding 5%, and 
          removing the flexibility to negotiate a good faith provision 








                                                                  SB 293
                                                                  Page  7


          between a public agency and a contractor, this bill 
          significantly thwarts an agency's ability to ensure that the 
          provisions of their public works contracts are fully executed.


           Analysis Prepared by  :    Kevin G. Baker / JUD. / (916) 319-2334 


                                                                FN: 0002284