BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  SB 1549
                                                                  Page  1

          Date of Hearing:  June 27, 2012

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                                Cameron Smyth, Chair
                    SB 1549 (Vargas) - As Amended:  June 20, 2012

           SENATE VOTE  :  38-0
           
          SUBJECT  :  Transportation projects: alternative project delivery 
          methods.

           SUMMARY  :  Authorizes the San Diego Association of Governments 
          (SANDAG) to use specified alternative project delivery methods 
          for an unlimited number of transit projects.  Specifically,  this 
          bill  :

          1)Authorizes SANDAG to use alternative project delivery methods, 
            specifically design-sequencing and the Construction 
            Manager/General Contractor (CMGC) method, as defined, for 
            public transit projects within its jurisdiction.

          2)Requires SANDAG, if it desires to enter into an alternative 
            project delivery method contract, to first evaluate the 
            traditional design-bid-build process of construction and the 
            alternative project delivery method in a public meeting, and 
            make a written finding that use of the alternative project 
            delivery method on the specific project under consideration 
            will accomplish one or more of the following objectives: 
            reduce project costs, expedite the project's completion, or 
            provide features not achievable through the design-bid-build 
            method. 

          3)Requires SANDAG to do the following:

             a)   Subject all CMGC contracts to a provision of the Public 
               Utilities Code related to procurement method requirements 
               for professional services contracts for a consolidated 
               agency, as specified; and,

             b)   Subject all design-sequencing contracts to provisions of 
               the Government Code related to public contracts for 
               architectural, engineering, land surveying and construction 
               project management services, and also subject to the 
               provisions of the Public Contract Code governing 
               contracting by state and local agencies, as specified.  








                                                                  SB 1549
                                                                  Page  2


          4)Requires SANDAG, when using the CMGC method, to enter into a 
            contract with a construction manager for preconstruction 
            services that includes a fee for those services, but may not 
            include provisions for payment for construction services or 
            enter into a construction contract before entering into a 
            services contract. 

          5)Requires any preconstruction CMGC contract to provide for the 
            subsequent negotiation for construction of all or any discrete 
            phase or phases of the project, and further provides for 
            ownership by SANDAG of the design plans and other 
            preconstruction services work product.

          6)Requires a CMGC contract for construction services to be 
            awarded after plans are sufficiently developed and either a 
            fixed price or guaranteed maximum price has been negotiated, 
            although SANDAG may award the contract utilizing any other 
            permitted procurement method if negotiations are not 
            successfully concluded. 

          7)Requires a construction manager to perform not less than 30% 
            of the work covered by the negotiated price of a CMGC 
            contract, with the remainder being performed by subcontractors 
            pursuant to existing law. 

          8)Requires all subcontractors bidding on contracts pursuant to 
            this bill to be afforded the protections of the Subletting and 
            Subcontracting Fair Practices Act within the Public Contract 
            Code.  

          9)Clarifies that, where projects constructed pursuant to this 
            bill will be on a state-owned right of way, Caltrans shall be 
            responsible for the performance of project development 
            services, including performance specifications, preliminary 
            engineering, prebid services, the preparation of project 
            reports and environmental documents, and construction 
            inspection services, and will otherwise be deemed the 
            responsible agency for the preparation of documents.

          10)Authorizes Caltrans to use department employees or 
            consultants to perform the services required where projects 
            are on a state-owned right of way, as specified, and further 
            requires that Caltrans resources, including personnel 
            requirements, necessary for the performance of those services 








                                                                 SB 1549
                                                                  Page  3

            shall be included in the department's capital outlay support 
            program for workload purposes in the annual Budget Act.

          11)Requires SANDAG, upon completion of projects using an 
            alternative delivery method, to prepare a progress report for 
            its governing body that shall include a description of the 
            project, the entity awarded the contract, the estimated and 
            actual costs of the project, the estimated and actual schedule 
            for project completion, a description of any written protests, 
            an assessment of the prequalification process, a description 
            of the bid evaluation method, a description of challenges or 
            unexpected problems, and recommendations. 

          12)Requires SANDAG to post completed progress reports on its 
            website.

          13)Provides that nothing in this bill affects, expands, alters, 
            or limits any rights or remedies otherwise available at law.

          14)Defines the following key terms:

             a)   "Alternative project delivery method" means "either 
               Construction Manager/General Contractor method or design 
               sequencing";

             b)   "Construction Manager/General Contractor method" or 
               "CMGC" means "a project delivery method using a best value 
               procurement process in which a construction manager is 
               procured to provide preconstruction services during the 
               design phase of the project and construction services 
               during the construction phase of the project.  The 
               execution of the design and the construction of the project 
               may be in sequential phases or concurrent phases";

             c)   "Construction manager" means "a partnership, 
               corporation, or other legal entity that is able to provide 
               appropriately licensed contracting and engineering services 
               as needed pursuant to a CMGC contract"; and,

             d)   "Design sequencing" means "a method of project delivery 
               that enables the sequencing of design activities to permit 
               each construction phase to commence when the design for 
               that phase is complete, instead of requiring design for the 
               entire project to be completed before commencing 
               construction."








                                                                  SB 1549
                                                                  Page  4


          15)Declares that the provisions of this bill are severable.

          16)Makes findings and declarations relative to the need for and 
            benefits of alternative project delivery methods, specifically 
            design sequencing and the �CMGC] methodology, and further 
            declares that the bill espouses no preference over other 
            methods. 

          17)Makes findings and declarations that a special law is 
            necessary because of the unique need for alternative 
            contracting authority for local public transportation projects 
            under the jurisdiction of SANDAG.

          18)Declares that no reimbursement is required because the only 
            costs that may be incurred by a local agency or school 
            district will be because this bill creates, eliminates, or 
            changes the penalty or definition of, a crime. 

           EXISTING LAW  : 

          1)Provides requirements for the solicitation and evaluation of 
            bids and the awarding of contracts by state agencies for 
            projects, as specified, and for local agencies for public 
            works contracts, as specified.  
             
          2)Establishes the Design-Build Demonstration Program, which 
            authorizes local entities to use the design-build method of 
            procurement for up to five projects and Caltrans to use it for 
            up to ten projects, subject to the California Transportation 
            Commission (CTC) approval.  The design-build projects must be 
            in one of the following: State Transportation Improvement 
            Program, Traffic Congestion Relief Program, Proposition 1B, or 
            the State Highway Operations and Protection Program (SHOPP).  

          3)Authorizes the use of the best value selection method for 
            procuring design-build services.

          4)Permits regional transportation planning agencies and Caltrans 
            to enter into an unlimited number of public private 
            partnerships for transportation projects until January 1, 
            2017.  

           FISCAL EFFECT  :   According to the Senate Appropriations 
          Committee, this bill has the "�p]otential for increased transit 








                                                                  SB 1549
                                                                  Page  5

          project costs (Public Transportation Account, State Transit 
          Assistance Account, or Local Funds) to the extent that the 
          alternative project delivery method chosen by SANDAG results in 
          a higher overall project cost than the traditional 
          design-bid-build method."



           COMMENTS  :

          1)This bill would authorize SANDAG to use two new project 
            delivery methods for transit projects: design-sequencing and 
            CMGC.  That authorization requires, as a prerequisite, that 
            SANDAG evaluate in a public meeting the proposed alternative 
            method against the traditional construction process and adopt 
            written findings that the use of an alternative delivery 
            method would provide lower costs, an accelerated project 
            schedule, or features that not achievable through traditional 
            project delivery.  Each completed project must be followed by 
            a progress report to be posted on SANDAG's website.  There is 
            no limit on the number of such projects SANDAG may undertake, 
            nor any sunset date on the authority. The measure is sponsored 
            by SANDAG.  
          
          2)SANDAG is the regional transportation planning agency for San 
            Diego County under state and federal law, and is the 
            metropolitan planning organization for the region.  SANDAG has 
            a broad scope of authority, and manages a local voter approved 
             % transportation sales tax. Central to its activities is a 
            $214 billion regional transportation plan that it intends to 
            implement between now and 2050.  SANDAG contends that the 
            authorization provided by this bill provides it with new tools 
            for constructing transportation projects in San Diego County. 

          In sponsoring this measure, SANDAG notes that it "has an 
            ambitious Capital Improvement Program (CIP), comprising more 
            than $850 million of our FY 2012 Program Budget. We have 
            actively advanced our local TransNet transportation sales tax 
            measure - accelerating infrastructure projects during a low 
            construction cost environment, and providing mobility and 
            economic benefits to the region.  SB 1549 will provide SANDAG 
            with additional project delivery tools for our TransNet Early 
            Action Program as well as the transit CIP projects that we 
            implement on behalf of our two public transit operators." 









                                                                  SB 1549
                                                                  Page  6

          3)The traditional transit project delivery method is 
            "design-bid-build".  This method requires the public agency to 
            design a project and put the plans out to bid to general 
            contractors.  The agency then awards the contract to the 
            lowest responsible bidder.  Design-bid-build procurement 
            results in project risks being largely borne by the agency 
            that designs the project.  If plans are inadequate or there 
            are unanticipated construction issues, the agency bears the 
            financial burden through the issuance of change orders or 
            having to resolve construction claims by contractors. 

          In the last several years, public agencies have been adopting 
            alternative project delivery methods.  The principle reason 
            for this is the desire to shift construction risk from the 
            agency/owner to the project contractor.  The most widely used 
            alternative project delivery technique is "design-build", 
            which California uses in a variety of capacities. This method 
            requires the public agency to prepare plans to 30% completion 
            and then put them out to bid to teams of engineers and general 
            contractors.  The teams bid a fixed cost for the project.  The 
            bids are then evaluated using the "best value" methodology, 
            which looks at criteria beyond cost, including qualifications 
            of the bidders, proposed approach to design, experience, and 
            other factors.  The winning design-contractor team completes 
            the project and commences construction.  Because the team 
            finishes the design work, it carries more of the risk 
            associated with the adequacy of plans.  Construction time can 
            theoretically be reduced, because the coordinated team can 
            commence construction on a phase of the project before the 
            entire project is designed. 
          4)This bill authorizes the use of two alternative project 
            delivery methods: design-sequencing and CMGC. 

            Design-sequencing is a method of contracting that enables the 
            sequencing of design activities to permit each project 
            construction phase to commence when design for that phase is 
            complete, rather than requiring design for the entire project 
            to be completed before commencing construction.  As previously 
            used by Caltrans, when the contractor bids, the first phase of 
            the project is completed and the remaining phases must be at 
            30% completion. The award is then made to the lowest, 
            responsible bidder.  There is little risk transfer from the 
            public agency to the contractor because the public agency 
            remains responsible for design.  The benefit of 
            design-sequencing is assumed to be time savings.  State law 








                                                                  SB 1549
                                                                  Page  7

            previously authorized design-sequencing for Caltrans, but the 
            authority lapsed in 2010.  Final reports on its use on state 
            projects are pending. 

          5)The CMGC project delivery method allows an agency to engage a 
            construction manager during the design process to provide 
            assistance to the design team, including advice regarding 
            scheduling, pricing, phasing, and other input that helps the 
            agency design a more easily constructible project.  The agency 
            then selects a construction manager on a best-value basis.  As 
            the design approaches completion but before construction 
            begins, the agency and the construction manager negotiate a 
            fixed price or guaranteed maximum price for the construction 
            of the project based on the defined scope and schedule.  If 
            this price is acceptable to both parties, a contract is 
            executed for construction services, and the construction 
            manager becomes the general contractor.  The benefits of this 
            procurement method are that the public agency does not 
            sacrifice control over the design of the project, and the 
            contractor is very familiar with the project design during the 
            construction phase, resulting in fewer disputes over design 
            issues.

          The Legislature has previously authorized Caltrans to use 
            design-sequencing on a variety of projects (see comment #8 on 
            related legislation below), and evaluations are ongoing. The 
            Legislature has never authorized the use of the CMGC project 
            delivery methodology, although a bill that would do so �AB 
            2498 (Gordon)] is currently pending in the Senate.

          6)The Professional Engineers in California Government (PECG) 
            oppose this measure unless amended, stating "PECG does not 
            believe it is appropriate to provide region-specific 
            authorization on the State Highway System.  Instead, PECG 
            believes there should be a statewide authorization for 
            design-sequencing?.As for the �CMGC] project delivery method 
            ?PECG suggests limiting this new untested procurement 
            methodology to four projects statewide with a sunset of 
            January 1, 2018?PECG is opposed to using the �CMGC] project 
            delivery method on local streets and roads." 

          The American Council of Engineering Companies of California 
            (ACEC CA), also has an 'oppose unless amended' position.  
            Regarding the provisions in Section 6956 of this bill that 
            relate to projects on state-owned rights of way and Caltrans' 








                                                                  SB 1549
                                                                  Page  8

            role as the responsible agency, ACEC agrees with PECG that 
            "the terms and obligations assigning �Caltrans] as the 
            'responsible agency' are not fulfilled unless �Caltrans] is 
            the one actually performing the work" - a matter now in 
            question due to litigation related to the Doyle Drive/Presidio 
            Parkway project in San Francisco.  As a result, "PECG �and 
            ACEC] insist that work must be done by �Caltrans] personnel, 
            and that the local agency in charge of the project is not 
            entitled 

          to lead or oversee the mix of resources it deems appropriate to 
            accomplish its authorized projects."  ACEC requests that the 
            entirety of the current Section 6956 be deleted.

          ACEC also questions whether this bill's provisions for projects 
            on state-owned rights-of-way would even be affected by this 
            bill, given that the language of the bill restricts its 
            operation to the jurisdiction of SANDAG only. 

          7)This bill is double referred to the Assembly Committee on 
            Transportation, which will hear the measure should it be 
            approved by this Committee. 
           
          8)Current and previous related legislation include the following 
            measures:

             a)   AB 2498 (Gordon, 2012) authorizes Caltrans to use CMGC 
               as an alternative procurement method for up to four 
               projects.  The bill is scheduled to be heard in the Senate 
               Committee on Transportation and Housing on June 26, 2012;

             b)   AB 294 (Portantino, 2011) authorizes Caltrans to enter 
               into design-sequencing contracts until January 1, 2015.  
               The bill was ordered to the Senate Floor inactive file in 
               September 2011;
               
             c)   AB 1266 (Niello, 2005) would have allowed Caltrans to 
               add four transportation projects to a 12-project pilot 
               program testing the cost effectiveness and timeliness of 
               using design-sequencing contracts to complete 
               transportation projects, and would have extended to January 
               1, 2012, the sunset on the pilot program.  This bill was 
               held by the Assembly Committee on Appropriations in 2005;

             d)   AB 2607 (Knox and Torlakson), Chapter 340, Statutes of 








                                                                  SB 1549
                                                                  Page  9

               2000, authorized Caltrans to conduct a pilot program to use 
               design-sequencing contracts for the design and construction 
               of no more than 12 transportation projects, and extended 
               the authorization sunset date to 2005; and,

             e)   AB 405 (Knox and Torlakson), Chapter 378, Statutes of 
               1999, authorized Caltrans to conduct a pilot program for 
               the completion of up to six transportation projects using a 
                 specified design-sequencing process, and required 
               Caltrans to evaluate and report on the results of the 
               program when completed.

           9)Support arguments  :  The California Transit Association 
            contends that "�t]he design sequencing and �CMGC] project 
            delivery methods rely on existing design-bid-build and 
            design-build procurement methods, respectively, and have been 
            successfully used by both public and private sector entities 
            in California and other states for over a decade on projects 
            that require a quick startup as they allow construction to 
            begin before the design plans are complete for the entire 
            project.  Both methods also have the benefit of allowing for 
            earlier collaboration between the project owner and 
            construction contractor.  We believe this authorization will 
            help SANDAG reduce cost, time, and achieve other benefits in 
            completing public transit projects using alternative project 
            delivery methods." 

             Opposition arguments  :  According to PECG, the bill should be 
            amended to require statewide authorization for any 
            design-sequencing authority, limit any CMGC authority to four 
            projects statewide with a 2018 sunset date, and prohibit the 
            use of CMGC on local streets and roads.
           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          San Diego Association of Governments (SANDAG) �SPONSOR]
          California Transit Association
          Metropolitan Transit System (San Diego)
           North County Transit District
          Riverside County Transportation Commission

           Opposition 
           
          American Council of Engineering Companies (unless amended) (5/1)








                                                                  SB 1549
                                                                  Page  10

          Professional Engineers in California Government (unless amended) 
          (4/12)

           Analysis Prepared by :    Hank Dempsey / L. GOV. / (916) 319-3958