AB 365,
as amended, Mullin. begin deleteCourt reporting.end deletebegin insertElectricity: distributed generation.end insert
Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, as defined. Existing law authorizes the commission to fix the rates and charges for every public utility, and requires that those rates and charges be just and reasonable. Existing law requires the commission to require each electrical corporation under the operational control of the Independent System Operator as of January 1, 2001, to modify tariffs so that all customers that install new distributed energy resources, as defined, in accordance with specified criteria are served under rates, rules, and requirements identical to those of a customer within the same rate schedule that does not use distributed energy resources, and to withdraw any provisions in otherwise applicable tariffs that activate other tariffs, rates, or rules if a customer uses distributed energy resources. Existing law provides, notwithstanding these requirements, that a customer that installs new distributed energy resources not be exempted from (1) reasonable interconnection charges, (2) charges imposed pursuant to the Reliable Electric Service Investment Act, and (3) charges imposed to repay the Department of Water Resources for electricity procurement expenses incurred in response to the electricity crisis of 2000-01. Existing law requires the commission, in establishing the rates applicable to customers that install new distributed energy resources, to create a firewall that segregates distribution cost recovery so that any net costs, taking into account the actual costs and benefits of distributed energy resources, proportional to each customer class, as determined by the commission, resulting from the tariff modifications granted to members of each customer class may be recovered only from that class.
end insertbegin insertThis bill would, to the extent authorized by federal law, require the commission, by July 1, 2015, to do both of the following for those electrical corporation customers that have operational clean distributed energy resources, as defined: (1) require each electrical corporation to collect all applicable nonbypassable charges fixed or imposed by the commission based only on the actual metered consumption of electricity delivered to the customer through the electrical corporation’s transmission or distribution system, and (2) calculate a reservation capacity for standby service, if applicable, based on the capacity needed by an electrical corporation to serve a customer’s electrical demand during an outage of the clean distributed energy resource providing electric service for that customer.
end insertbegin insertUnder existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.
end insertbegin insertBecause the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime.
end insertbegin insertThe California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
end insertbegin insertThis bill would provide that no reimbursement is required by this act for a specified reason.
end insertExisting law provides that the report of the official court reporter or official court reporter pro tempore, of any court, duly appointed and sworn, when transcribed and certified as being a correct transcript of the testimony and proceedings in the case, is prima facie evidence of that testimony and proceeding.
end deleteThe bill would make clarifying changes to those provisions.
end deleteVote: majority.
Appropriation: no.
Fiscal committee: begin deleteno end deletebegin insertyesend insert.
State-mandated local program: begin deleteno end deletebegin insertyesend insert.
The people of the State of California do enact as follows:
The Legislature finds and declares all of the
2following:
3(a) Clean onsite generation of electricity yields multiple benefits,
4including increased electrical reliability, reduced emissions of
5greenhouse gases and oxides of nitrogen (NOx), and electrical
6grid resiliency.
7(b) Increased deployment of clean onsite electricity generation
8reduces the need for generation that emits higher levels of
9greenhouse gases that contribute to climate change and higher
10levels of NOx that contribute
to smog formation.
11(c) Several types of clean onsite electrical generation
12technologies currently exist and others are being developed, with
13many being manufactured and developed in California.
14(d) Nonbypassable charges applied by electrical corporations
15to electricity produced and consumed onsite are a major
16impediment to broader deployment of clean onsite generation
17technologies. Residential, commercial, and industrial customers
18are willing to invest their own capital to install clean onsite
19generation technologies. However, nonbypassable charges applied
20to electricity produced and consumed onsite create an economic
21barrier to these investments.
22(e) California is the only state that allows electrical corporations
23to apply nonbypassable charges to electricity produced and
24consumed onsite among those states with
similarly high energy
25prices and environmental goals, including New York, New Jersey,
26Maryland, Vermont, Connecticut, and Hawaii.
27(f) A recent study shows that all ratepayers would see a net cost
28savings from increased deployment of onsite electricity generation
29at customer sites that pay nonbypassable charges only on their
30electricity purchases from the grid. This ratepayer savings arises
31because onsite electricity generation reduces demand on the
32electrical grid, which reduces market electricity prices, and avoids
P4 1transmission and distribution costs and energy losses. On average,
2all ratepayers in electrical corporation service areas would see
3an energy rate savings of between seventeen cents ($0.17) and
4thirty-seven cents ($0.37) per megawatt hour, which translates to
5an average household savings of between nine cents ($0.09) and
6eighteen cents ($0.18) per month.
7(g) Other
cost-saving benefits to all ratepayers from clean onsite
8electrical generation include reductions in future generating
9capacity requirements, reductions in electrical grid congestion
10prices, reductions in emissions of greenhouse gases and criteria
11air pollutants, and increases in electrical grid resiliency and
12security.
13(h) Nonbypassable charges create an economic barrier to the
14installation of clean onsite electrical generation and, as a result,
15prevent cost savings for all ratepayers and environmental benefits
16for all Californians.
begin insertSection 354 is added to the end insertbegin insertPublic Utilities Codeend insertbegin insert, to
18read:end insert
(a) As used in this section, “clean distributed energy
20resource” means a facility that is located on the customer’s
21premises and generates electricity, or electricity and useful heat,
22where the electricity generated is used for a purpose described in
23paragraph (1) or (2) of subdivision (b) of Section 218, and that
24meets either of the following requirements:
25(1) It meets all of the following criteria:
26(A) Produces emissions of greenhouse gases at a rate per
27megawatthour, accounting for waste heat recovery, where
28applicable, and savings on transmission and distribution losses,
29that is less than or equal to an emissions rate determined by the
30Energy Commission by January 30, 2015,
that represents the
31emissions of greenhouse gases from the marginal generating unit
32dispatched to meet the demand on the electrical grid that is avoided
33by the electricity generated by the clean distributed energy
34resource.
35(B) Has an oxide of nitrogen (NOx) emissions rate, including
36credit for waste heat recovery, when applicable, that is less than
37or equal to 0.07 pounds per megawatthour, or a lower NOx
38emissions rate that the State Air Resources Board determines
39reflects the best performance achieved in practice by existing
P5 1electrical generation technologies pursuant to Section 41514.9 of
2the Health and Safety Code.
3(C) Has a nameplate rated generation capacity of 20 megawatts
4or less.
5(2) It is an “eligible renewable energy resource” pursuant to
6the California Renewables Portfolio Standard Program (Article
716
(commencing with Section 399.11)) that has a nameplate rated
8generation capacity of 20 megawatts or less.
9(b) To the extent authorized by federal law, by July 1, 2015, the
10commission shall do both of the following for those electrical
11corporation customers served by clean distributed energy
12resources:
13(1) Require each electrical corporation to collect all applicable
14nonbypassable charges fixed or imposed by the commission based
15only on the actual metered consumption of electricity delivered to
16the customer through the electrical corporation’s transmission or
17distribution system. All charges shall be at the same rate per
18kilowatthour as paid by other customers that do not employ a clean
19distributed energy resource under the electrical corporation’s
20applicable rate schedule.
21(2) (A) Calculate a
reservation capacity for standby service, if
22applicable, based on the capacity needed by an electrical
23corporation to serve a customer’s electrical demand during an
24outage of the clean distributed energy resource providing electric
25service for that customer.
26(B) Initial reservation capacity shall be established by the
27customer for a minimum of 12 months based on the clean
28distributed energy resource generation technology’s historical
29operation, the number, size, and outage diversity of the clean
30distributed energy resource, and the annual average reduction of
31customer load that could occur during an outage.
32(C) If after the initial 12-month period, the electrical corporation
33reasonably determines that the reservation capacity does not reflect
34the customer’s actual standby demand, averaged over the previous
3512 months, the electrical corporation shall modify the reservation
36capacity
once every 12 months to reflect the customer’s actual
37average annual reservation capacity based on the same criteria
38used to establish the initial reservation capacity. Calculation of
39actual average annual reservation capacity shall exclude the
40customer’s electrical demand served by the electrical corporation
P6 1within 24 hours following an outage of the clean distributed energy
2resource resulting from any event on the electrical corporation’s
3transmission or distribution grid that is outside of the customer’s
4control that requires the customer to reduce onsite generation.
No reimbursement is required by this act pursuant to
6Section 6 of Article XIII B of the California Constitution because
7the only costs that may be incurred by a local agency or school
8district will be incurred because this act creates a new crime or
9infraction, eliminates a crime or infraction, or changes the penalty
10for a crime or infraction, within the meaning of Section 17556 of
11the Government Code, or changes the definition of a crime within
12the meaning of Section 6 of Article XIII B of the California
13Constitution.
Section 273 of the Code of Civil Procedure, as
15amended by Section 1 of Chapter 87 of the Statutes of 2009, is
16amended to read:
(a) Notwithstanding any other provision of law, the report
18of the official reporter, or official reporter pro tempore, of any
19court, duly appointed and sworn, when transcribed and certified
20as being a correct transcript of the testimony and proceedings in
21the case, is prima facie evidence of that testimony and proceedings.
22(b) The report of the official reporter, or official reporter pro
23tempore, of any court, duly
appointed and sworn, when prepared
24as a rough draft transcript, shall not be certified and cannot be
25used, cited, distributed, or transcribed as the official certified
26transcript of the proceedings. A rough draft transcript shall not be
27cited or used in any way or at any time to rebut or contradict the
28official certified transcript of the proceedings as provided by the
29official reporter or official reporter pro tempore. The production
30of a rough draft transcript shall not be required.
31(c) The instant visual display of the testimony or proceedings,
32or both, shall not be certified and cannot be used, cited, distributed,
33or transcribed as the official certified transcript of the proceedings.
34The instant visual display of the testimony or proceedings, or both,
35shall not be cited or used in any way or at any time to rebut or
36contradict the
official certified transcript of the proceedings as
37provided by the official reporter or official reporter pro tempore.
38(d) This section shall remain in effect only until January 1, 2017,
39and as of that date is repealed, unless a later enacted statute, that
40is enacted before January 1, 2017, deletes or extends that date.
Section 273 of the Code of Civil Procedure, as added by
2Section 2 of Chapter 87 of the Statutes of 2009, is amended to
3read:
(a) Notwithstanding any other provision of law, the report
5of the official reporter, or official reporter pro tempore, of any
6court, duly appointed and sworn, when transcribed and certified
7as being a correct transcript of the testimony and proceedings in
8the case, is prima facie evidence of that testimony and proceedings.
9(b) The report of the official reporter, or official reporter pro
10tempore, of any court, duly
appointed and sworn, when prepared
11as a rough draft transcript, shall not be certified and cannot be
12used, cited, distributed, or transcribed as the official certified
13transcript of the proceedings. A rough draft transcript shall not be
14cited or used in any way or at any time to rebut or contradict the
15official certified transcript of the proceedings as provided by the
16official reporter or official reporter pro tempore. The production
17of a rough draft transcript shall not be required.
18(c) This section shall become operative on January 1, 2017.
Section 275 is added to the Code of Civil Procedure,
20to read:
For the purposes of this chapter, an official reporter or an
22official reporter pro tempore shall be appointed as provided by
23Section 69942 of the Government Code.
O
97