Amended in Senate June 30, 2014

Amended in Senate June 12, 2014

Amended in Assembly April 3, 2013

California Legislature—2013–14 Regular Session

Assembly BillNo. 365


Introduced by Assembly Member Mullin

February 14, 2013


An actbegin delete to add Section 354 to the Public Utilities Code,end delete relating to electricity.

LEGISLATIVE COUNSEL’S DIGEST

AB 365, as amended, Mullin. Electricity: distributed generation.

Under existing law, the Public Utilities Commission has regulatory authority over public utilities, including electrical corporations, as defined. Existing law authorizes the commission to fix the rates and charges for every public utility, and requires that those rates and charges be just and reasonable. Existing law requires the commission to require each electrical corporation under the operational control of the Independent System Operator as of January 1, 2001, to modify tariffs so that all customers that install new distributed energy resources, as defined, in accordance with specified criteria are served under rates, rules, and requirements identical to those of a customer within the same rate schedule that does not use distributed energy resources, and to withdraw any provisions in otherwise applicable tariffs that activate other tariffs, rates, or rules if a customer uses distributed energy resources. Existing law provides, notwithstanding these requirements, that a customer that installs new distributed energy resources not be exempted from (1) reasonable interconnection charges, (2) charges imposed pursuant to the Reliable Electric Service Investment Act, and (3) charges imposed to repay the Department of Water Resources for electricity procurement expenses incurred in response to the electricity crisis of 2000-01. Existing law requires the commission, in establishing the rates applicable to customers that install new distributed energy resources, to create a firewall that segregates distribution cost recovery so that any net costs, taking into account the actual costs and benefits of distributed energy resources, proportional to each customer class, as determined by the commission, resulting from the tariff modifications granted to members of each customer class may be recovered only from that class.

begin delete

This bill would, to the extent authorized by federal law, require the commission, by July 1, 2015, to do both of the following for those electrical corporation customers that have operational clean distributed energy resources, as defined: (1) require each electrical corporation to collect all applicable nonbypassable charges fixed or imposed by the commission based only on the actual metered consumption of electricity delivered to the customer through the electrical corporation’s transmission or distribution system, and (2) calculate a reservation capacity for standby service, if applicable, based on the capacity needed by an electrical corporation to serve a customer’s electrical demand during an outage of the clean distributed energy resource providing electric service for that customer.

end delete
begin delete

Under existing law, a violation of the Public Utilities Act or any order, decision, rule, direction, demand, or requirement of the commission is a crime.

end delete
begin delete

Because the provisions of this bill would be a part of the act and because a violation of an order or decision of the commission implementing its requirements would be a crime, the bill would impose a state-mandated local program by creating a new crime.

end delete
begin delete

The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.

end delete
begin delete

This bill would provide that no reimbursement is required by this act for a specified reason.

end delete
begin insert

This bill would make legislative findings and declarations as to clean onsite electricity generation and nonbypassable charges.

end insert

Vote: majority. Appropriation: no. Fiscal committee: begin deleteyes end deletebegin insertnoend insert. State-mandated local program: begin deleteyes end deletebegin insertnoend insert.

The people of the State of California do enact as follows:

P3    1

SECTION 1.  

The Legislature finds and declares all of the
2following:

3(a) Clean onsite generation of electricity yields multiple benefits,
4including increased electrical reliability, reduced emissions of
5greenhouse gases and oxides of nitrogen (NOx), and electrical grid
6resiliency.

7(b) Increased deployment of clean onsite electricity generation
8reduces the need for generation that emits higher levels of
9greenhouse gases that contribute to climate change and higher
10levels of NOx that contribute to smog formation.

11(c) Several types of clean onsite electrical generation
12technologies currently exist and others are being developed, with
13many being manufactured and developed in California.

begin delete

14(d) Nonbypassable charges applied by electrical corporations
15to electricity produced and consumed onsite are a major
16impediment to broader deployment of clean onsite generation
17technologies. Residential, commercial, and industrial customers
18are willing to invest their own capital to install clean onsite
19generation technologies. However, nonbypassable charges applied
20to electricity produced and consumed onsite create an economic
21barrier to these investments.

22(e) California is the only state that allows electrical corporations
23to apply nonbypassable charges to electricity produced and
24consumed onsite among those states with similarly high energy
25prices and environmental goals, including New York, New Jersey,
26Maryland, Vermont, Connecticut, and Hawaii.

27 (f)

end delete

28begin insert(d)end insert A recent study shows that all ratepayers would see a net cost
29savings from increased deployment of onsite electricity generation
30at customer sites that pay nonbypassable charges only on their
31electricity purchases from the grid. This ratepayer savings arises
32because onsite electricity generation reduces demand on the
33electrical grid, which reduces market electricity prices, and avoids
34transmission and distribution costs and energy losses. On average,
35all ratepayers in electrical corporation service areas would see an
36energy rate savings of between seventeen cents ($0.17) and
37thirty-seven cents ($0.37) per megawatt hour, which translates to
P4    1an average household savings of between nine cents ($0.09) and
2eighteen cents ($0.18) per month.

begin delete

3(g) Other cost-saving benefits to all ratepayers from clean onsite
4electrical generation include reductions in future generating
5capacity requirements, reductions in electrical grid congestion
6prices, reductions in emissions of greenhouse gases and criteria
7air pollutants, and increases in electrical grid resiliency and
8security.

end delete
begin delete

9(h) Nonbypassable charges create an economic barrier to the
10installation of clean onsite electrical generation and, as a result,
11prevent cost savings for all ratepayers and environmental benefits
12for all Californians.

end delete
begin delete
13

SEC. 2.  

Section 354 is added to the Public Utilities Code, to
14read:

15

354.  

(a) As used in this section, “clean distributed energy
16resource” means a facility that is located on the customer’s
17premises and generates electricity, or electricity and useful heat,
18where the electricity generated is used for a purpose described in
19paragraph (1) or (2) of subdivision (b) of Section 218, and that
20meets either of the following requirements:

21(1) It meets all of the following criteria:

22(A) Produces emissions of greenhouse gases at a rate per
23megawatthour, accounting for waste heat recovery, where
24applicable, and savings on transmission and distribution losses,
25that is less than or equal to an emissions rate determined by the
26Energy Commission by January 30, 2015, that represents the
27emissions of greenhouse gases from the marginal generating unit
28dispatched to meet the demand on the electrical grid that is avoided
29by the electricity generated by the clean distributed energy
30resource.

31(B) Has an oxide of nitrogen (NOx) emissions rate, including
32credit for waste heat recovery, when applicable, that is less than
33or equal to 0.07 pounds per megawatthour, or a lower NOx
34emissions rate that the State Air Resources Board determines
35reflects the best performance achieved in practice by existing
36electrical generation technologies pursuant to Section 41514.9 of
37the Health and Safety Code.

38(C) Has a nameplate rated generation capacity of 20 megawatts
39or less.

P5    1(2) It is an “eligible renewable energy resource” pursuant to the
2California Renewables Portfolio Standard Program (Article 16
3 (commencing with Section 399.11)) that has a nameplate rated
4generation capacity of 20 megawatts or less.

5(b) To the extent authorized by federal law, by July 1, 2015, the
6commission shall do both of the following for those electrical
7corporation customers served by clean distributed energy resources:

8(1) Require each electrical corporation to collect all applicable
9nonbypassable charges fixed or imposed by the commission based
10only on the actual metered consumption of electricity delivered to
11the customer through the electrical corporation’s transmission or
12distribution system. All charges shall be at the same rate per
13kilowatthour as paid by other customers that do not employ a clean
14distributed energy resource under the electrical corporation’s
15applicable rate schedule.

16(2) (A) Calculate a reservation capacity for standby service, if
17applicable, based on the capacity needed by an electrical
18corporation to serve a customer’s electrical demand during an
19outage of the clean distributed energy resource providing electric
20service for that customer.

21(B) Initial reservation capacity shall be established by the
22customer for a minimum of 12 months based on the clean
23distributed energy resource generation technology’s historical
24operation, the number, size, and outage diversity of the clean
25distributed energy resource, and the annual average reduction of
26customer load that could occur during an outage.

27(C) If after the initial 12-month period, the electrical corporation
28reasonably determines that the reservation capacity does not reflect
29the customer’s actual standby demand, averaged over the previous
3012 months, the electrical corporation shall modify the reservation
31capacity once every 12 months to reflect the customer’s actual
32average annual reservation capacity based on the same criteria
33used to establish the initial reservation capacity. Calculation of
34actual average annual reservation capacity shall exclude the
35customer’s electrical demand served by the electrical corporation
36within 24 hours following an outage of the clean distributed energy
37resource resulting from any event on the electrical corporation’s
38transmission or distribution grid that is outside of the customer’s
39control that requires the customer to reduce onsite generation.

P6    1

SEC. 3.  

No reimbursement is required by this act pursuant to
2Section 6 of Article XIII B of the California Constitution because
3the only costs that may be incurred by a local agency or school
4district will be incurred because this act creates a new crime or
5infraction, eliminates a crime or infraction, or changes the penalty
6for a crime or infraction, within the meaning of Section 17556 of
7the Government Code, or changes the definition of a crime within
8the meaning of Section 6 of Article XIII B of the California
9Constitution.

end delete


O

    96