AB 536, as amended, Wagner. Contractors: payments.
Existing law allows specified persons to withhold from a contractor or subcontractor no more than 150% of the disputed amount if there is a good faith dispute over the amount due on a contract payment.
This bill would excludebegin delete specified amountsend deletebegin insert the amount of specified claimsend insert from being considered disputed amountsbegin insert, as providedend insert.
Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.
The people of the State of California do enact as follows:
Section 7108.5 of the Business and Professions
2Code is amended to read:
(a) A prime contractor or subcontractor shall pay to
4any subcontractor, not later than seven days after receipt of each
5progress payment, unless otherwise agreed to in writing, the
P2 1respective amounts allowed the contractor on account of the work
2performed by the subcontractors, to the extent of each
3subcontractor’s interest therein. In the event that there is a good
4faith dispute over all or any portion of the amount due on a progress
5payment from the prime contractor or subcontractor to a
6subcontractor, the prime contractor or subcontractor may withhold
7no more than 150 percent of the disputed amount.
8(b) Any violation of this section shall constitute a cause for
9disciplinary action
and shall subject the licensee to a penalty,
10payable to the subcontractor, of 2 percent of the amount due per
11month for every month that payment is not made.
12(c) In any action for the collection of funds wrongfully withheld,
13the prevailing party shall be entitled to his or her attorneys’ fees
14and costs.
15(d) The sanctions authorized under this section shall be separate
16from, and in addition to, all other remedies, either civil,
17administrative, or criminal.
18(e) This section applies to all private works of improvement
19and to all public works of improvement, except where Section
2010262 of the Public Contract Code applies.
21(f) For purposes of this section, a
“disputed amount” shall not
22includebegin delete any of the following:end deletebegin insert the amount of any claim for
23additional compensation by the subcontractor against the prime
24contractor.end insert
25(1) With respect to liquidated damages assessed by the owner
26against the prime contractor, any amount in excess of the liquidated
27damages that are owed by the subcontractor.
28(2) With respect to mechanics liens and stop payment notices
29for which the subcontractor is responsible, any amount in excess
30of what the owner is permitted by law to withhold from the prime
31contractor on account of the mechanics lien or stop payment notice.
32(3) The amount of any claim for additional compensation by
33the subcontractor against the prime contractor.
Section 8800 of the Civil Code is amended to read:
(a) Except as otherwise agreed in writing by the owner
36and direct contractor, the owner shall pay the direct contractor,
37within 30 days after notice demanding payment pursuant to the
38contract is given, any progress payment due as to which there is
39no good faith dispute between them. The notice given shall comply
P3 1with the requirements of Chapter 2 (commencing with Section
28100) of Title 1.
3(b) If there is a good faith dispute between the owner and direct
4contractor as to a progress payment due, the owner may withhold
5from the progress payment an amount not in excess of 150 percent
6of the disputed amount.
7(c) An owner that
violates this section is liable to the direct
8contractor for a penalty of 2 percent per month on the amount
9wrongfully withheld, in place of any interest otherwise due. In an
10action for collection of the amount wrongfully withheld, the
11prevailing party is entitled to costs and reasonable attorneys’ fees.
12(d) This section does not supersede any requirement of Article
132 (commencing with Section 8810) relating to the withholding of
14a retention.
15(e) For purposes of this section, a “disputed amount” shall not
16includebegin delete any of the following:end deletebegin insert the amount of any claim for
17additional compensation by the direct contractor against the
18owner.end insert
19(1) With respect to liquidated damages assessed by the owner,
20any amount in excess of the liquidated damages assessment.
21(2) With respect to mechanics liens and stop payment notices,
22any amount in excess of what the owner is permitted by law to
23withhold from the direct contractor on account of the mechanics
24lien or
stop payment notice.
25(3) The amount of any claim for additional compensation by
26the direct contractor against the owner.
Section 8802 of the Civil Code is amended to read:
(a) This section applies to a contract between a public
29utility and a direct contractor for all or part of a work of
30improvement.
31(b) Unless the direct contractor and a subcontractor otherwise
32agree in writing, within 21 days after receipt of a progress payment
33from the public utility the direct contractor shall pay the
34subcontractor the amount allowed the direct contractor on account
35of the work performed by the subcontractor to the extent of the
36subcontractor’s interest in the work. If there is a good faith dispute
37over all or part of the amount due on a progress payment from the
38direct contractor to a subcontractor, the direct contractor may
39withhold an amount not in excess of 150
percent of the disputed
40amount.
P4 1(c) A direct contractor that violates this section is liable to the
2subcontractor for a penalty of 2 percent of the disputed amount
3due per month for every month that payment is not made. In an
4action for collection of the amount wrongfully withheld, the
5prevailing party is entitled to costs and reasonable attorneys’ fees.
6(d) This section does not limit or impair a contractual,
7administrative, or judicial remedy otherwise available to a
8contractor or subcontractor in a dispute involving late payment or
9nonpayment by the contractor or deficient performance or
10nonperformance by the subcontractor.
11(e) For purposes of this section, a “disputed amount” shall not
12includebegin delete any of the following:end deletebegin insert
the amount of any claim for
13additional compensation by the subcontractor against the direct
14contractor.end insert
15(1) With respect to liquidated damages assessed by the public
16utility against the direct contractor, any amount in excess of the
17liquidated damages that are owed by the subcontractor.
18(2) With respect to mechanics liens and stop payment notices
19for which the subcontractor is responsible, any amount in excess
20of what the public utility is permitted by law to withhold from the
21direct contractor on account of the mechanics lien or stop payment
22notice.
23(3) The amount of any claim for additional compensation
by
24the subcontractor against the direct contractor.
Section 8812 of the Civil Code is amended to read:
(a) If an owner withholds a retention from a direct
27contractor, the owner shall, within 45 days after completion of the
28work of improvement, pay the retention to the contractor.
29(b) If part of a work of improvement ultimately will become
30the property of a public entity, the owner may condition payment
31of a retention allocable to that part on acceptance of the part by
32the public entity.
33(c) If there is a good faith dispute between the owner and direct
34contractor as to a retention payment due, the owner may withhold
35from final payment an amount not in excess of 150 percent of the
36disputed amount. This withheld amount shall not
be considered
37wrongfully withheld.
38(d) For purposes of this section, a “disputed amount” shall not
39includebegin delete any of the following:end deletebegin insert the amount of any claim for
P5 1additional compensation by the direct contractor against the
2owner.end insert
3(1) With respect to liquidated damages assessed by the owner,
4any amount in excess of the liquidated damages assessment.
5(2) With respect to mechanics liens and stop payment notices,
6any amount in excess of what the owner is permitted by law to
7withhold from the direct contractor on account of the mechanics
8lien or stop payment notice.
9(3) The amount of any claim for additional compensation by
10the direct contractor against
the owner.
Section 8814 of the Civil Code is amended to read:
(a) If a direct contractor has withheld a retention from
13one or more subcontractors, the direct contractor shall, within 10
14days after receiving all or part of a retention payment, pay to each
15subcontractor from whom retention has been withheld that
16subcontractor’s share of the payment.
17(b) If a retention received by the direct contractor is specifically
18designated for a particular subcontractor, the direct contractor shall
19pay the retention payment to the designated subcontractor, if
20consistent with the terms of the subcontract.
21(c) If a good faith dispute exists between the direct contractor
22and a subcontractor, the direct
contractor may withhold from the
23retention to the subcontractor an amount not in excess of 150
24percent of the estimated value of the disputed amount.
25(d) For purposes of this section, a “disputed amount” shall not
26includebegin delete any of the following:end deletebegin insert the amount of any claim for
27additional compensation by the subcontractor against the direct
28contractor.end insert
29(1) With respect to liquidated damages assessed by the owner
30against the direct contractor, any amount in excess of the liquidated
31damages that are owed by the subcontractor.
32(2) With respect to mechanics liens and stop payment notices
33for which the subcontractor is responsible, any amount in excess
34of what the owner is permitted by law to withhold from the direct
35contractor on account of the mechanics lien or stop payment notice.
36(3) The amount of any claim for additional compensation by
37the subcontractor
against the direct contractor.
Section 7107 of the Public Contract Code is amended
39to read:
(a) This section is applicable with respect to all contracts
2entered into on or after January 1, 1993, relating to the construction
3of any public work of improvement.
4(b) The retention proceeds withheld from any payment by the
5public entity from the original contractor, or by the original
6contractor from any subcontractor, shall be subject to this section.
7(c) Within 60 days after the date of completion of the work of
8improvement, the retention withheld by the public entity shall be
9released. In the event of a dispute between the public entity and
10the original contractor, the public entity may
withhold from the
11final payment an amount not to exceed 150 percent of the disputed
12amount. For purposes of this subdivision, “completion” means any
13of the following:
14(1) The occupation, beneficial use, and enjoyment of a work of
15improvement, excluding any operation only for testing, startup, or
16commissioning, by the public agency, or its agent, accompanied
17by cessation of labor on the work of improvement.
18(2) The acceptance by the public agency, or its agent, of the
19work of improvement.
20(3) After the commencement of a work of improvement, a
21cessation of labor on the work of improvement for a continuous
22period of 100 days or more, due to factors beyond the control of
23the contractor.
24(4) After the commencement of a work of improvement, a
25cessation of labor on the work of improvement for a continuous
26period of 30 days or more, if the public agency files for record a
27notice of cessation or a notice of completion.
28(d) Subject to subdivision (e), within seven days from the time
29that all or any portion of the retention proceeds are received by
30the original contractor, the original contractor shall pay each of its
31subcontractors from whom retention has been withheld, each
32subcontractor’s share of the retention received. However, if a
33retention payment received by the original contractor is specifically
34designated for a particular subcontractor, payment of the retention
35shall be made to the designated subcontractor, if the payment is
36consistent with the terms of the
subcontract.
37(e) The original contractor may withhold from a subcontractor
38its portion of the retention proceeds if a bona fide dispute exists
39between the subcontractor and the original contractor. The amount
P7 1withheld from the retention payment shall not exceed 150 percent
2of the estimated value of the disputed amount.
3(f) In the event that retention payments are not made within the
4time periods required by this section, the public entity or original
5contractor withholding the unpaid amounts shall be subject to a
6charge of 2 percent per month on the improperly withheld amount,
7in lieu of any interest otherwise due. Additionally, in any action
8for the collection of funds wrongfully withheld, the prevailing
9party shall be entitled to attorneys’ fees and costs.
10(g) If a state agency retains an amount greater than 125 percent
11of the estimated value of the work yet to be completed pursuant
12to Section 10261, the state agency shall distribute undisputed
13retention proceeds in accordance with subdivision (c). However,
14notwithstanding subdivision (c), if a state agency retains an amount
15equal to or less than 125 percent of the estimated value of the work
16yet to be completed, the state agency shall have 90 days in which
17to release undisputed retentions.
18(h) Any attempted waiver of the provisions of this section shall
19be void as against the public policy of this state.
20(i) For purposes of this section, a “disputed amount” and “bona
21fide dispute” shall not includebegin delete any of the following:end deletebegin insert
the amount
22of any claim for additional compensation by the original contractor
23or subcontractor.end insert
24(1) With respect to liquidated damages assessed by the public
25entity, any amount in excess of the liquidated damages assessment.
26(2) With respect to mechanics liens and stop payment notices
27for which the subcontractor is responsible, any amount in excess
28of what the owner is permitted by law to withhold from the prime
29contractor on account of the mechanics lien or stop payment notice.
30(3) The amount of any claim for additional compensation by
31the original contractor or
subcontractor.
Section 10262.5 of the Public Contract Code is
33amended to read:
(a) (1) Notwithstanding any other law, a prime
35contractor or subcontractor shall pay to any subcontractor, not later
36than seven days after receipt of each progress payment, the
37respective amounts allowed the contractor on account of the work
38performed by the subcontractors, to the extent of each
39subcontractor’s interest therein. In the event that there is a good
40faith dispute over all or any portion of the amount due on a progress
P8 1payment from the prime contractor or subcontractor to a
2subcontractor, then the prime contractor or subcontractor may
3withhold no more than 150 percent of the disputed amount.
4(2) Any contractor who violates this section shall pay to the
5subcontractor
a penalty of 2 percent of the amount due per month
6for every month that payment is not made. In any action for the
7collection of funds wrongfully withheld, the prevailing party shall
8be entitled to his or her attorneys’ fees and costs.
9(b) This section shall not be construed to limit or impair any
10contractual, administrative, or judicial remedies otherwise available
11to a contractor or a subcontractor in the event of a dispute involving
12late payment or nonpayment by a contractor or deficient
13subcontract performance or nonperformance by a subcontractor.
14(c) On or before September 1 of each year, the head of each
15state agency shall submit to the Legislature a report on the number
16and dollar volume of written complaints received from
17subcontractors and prime contractors on contracts in
excess of
18three hundred thousand dollars ($300,000), relating to violations
19of this section.
20(d) For purposes of this section, a “disputed amount” shall not
21includebegin delete any of the following:end deletebegin insert the amount of any claim for
22additional compensation by the subcontractor against the prime
23contractor.end insert
24(1) With respect to liquidated damages assessed by the public
25entity against the prime contractor, any amount in excess of the
26liquidated damages that are owed by the subcontractor.
27(2) With respect to stop payment notices for which the
28subcontractor is responsible, any amount in excess of what the
29public entity is permitted by law to withhold from the prime
30contractor on account of the stop payment notice.
31(3) The amount of any claim for additional compensation
by
32the subcontractor against the prime contractor.
O
97