BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 536
                                                                  Page  1

          Date of Hearing:   January 14, 2014

              ASSEMBLY COMMITTEE ON BUSINESS, PROFESSIONS AND CONSUMER  
                                     PROTECTION
                               Susan A. Bonilla, Chair
                    AB 536 (Wagner) - As Amended:  January 6, 2014
           
          SUBJECT  :   Contractors: payments. 

           SUMMARY  :   Excludes claims for additional compensation from the  
          definition of a "disputed amount" for purposes of existing law  
          that authorizes, in the event of a good faith dispute, the  
          withholding of 150% of a disputed amount from certain payments  
          to contractors and subcontractors.  Specifically,  this bill  :  

          1)Prohibits a prime contractor from withholding the amount of a  
            subcontractor's claim for additional compensation against the  
            prime contractor from progress payments and retention proceeds  
            in public and private works, as specified.  

          2)Prohibits a property owner from withholding the amount of a  
            direct contractor's claim for additional compensation against  
            the owner from progress payments and retention proceeds in a  
            private work of improvement, as specified.

          3)Prohibits a public entity from withholding the amount of the  
            original contractor's claim for additional compensation  
            against the public entity, and prevents the original  
            contractor from withholding the amount of a subcontractor's  
            claim for additional compensation against the original  
            contractor from retention proceeds in a public works project,  
            as specified.

           EXISTING LAW  :

          1)Requires, in a public or private work of improvement, a prime  
            contractor or subcontractor to pay a subcontractor within  
            seven days after receiving a progress payment, unless  
            otherwise agreed to in writing, the respective amounts for the  
            work performed by the subcontractor, to the extent of each  
            subcontractor's interest in that work.  Authorizes the prime  
            contractor or subcontractor, in the event of a good faith  
            dispute over the amount due, to withhold from the progress  
            payment no more than 150% of the disputed amount.  Provides  
            that a prime contractor or subcontractor who violates these  








                                                                  AB 536
                                                                  Page  2

            provisions is liable to the subcontractor for a penalty of 2%  
            of the amount wrongfully withheld per month for every month  
            payment is not made.  (Business and Professions Code Section  
            (BPC) 7108.5; Public Contract Code Section (PCC) 10262.5)

             2)   Requires, in a work of improvement for a public utility,  
               the direct contractor to pay the subcontractor within 21  
               days after receiving a progress payment, unless otherwise  
               agreed to in writing, the respective amounts for the work  
               performed by the subcontractor, to the extent of each  
               subcontractor's interest in that work.  Authorizes the  
               direct contractor, in the event of a good faith dispute  
               over the amount due, to withhold from the progress payment  
               no more than 150% of the disputed amount.  Provides that a  
               contractor who violates those provisions is liable to the  
               subcontractor for a penalty of 2% of the amount wrongfully  
               withheld per month for every month payment is not made.   
               (Civil Code Section (CIV) 8802)

             3)   Requires, in a private work of improvement, the owner to  
               pay the direct contractor, within 30 days after notice is  
               given demanding payment pursuant to the contract, any  
               progress payments due for which there are no good faith  
               disputes.  Authorizes the owner, in the event of a good  
               faith dispute over the amount due, to withhold from the  
               progress payment no more than 150% of the disputed amount.   
               Provides that an owner who violates those provisions is  
               liable to the contractor for a penalty of 2% of the amount  
               wrongfully withheld per month for every month payment is  
               not made.  (CIV 8800)

             4)   Requires, in a private work of improvement, an owner to  
               pay any retention proceeds to the direct contractor within  
               45 days after completion of the work of improvement.   
               Authorizes the owner, in the event of a good faith dispute  
               over the amount due, to withhold from the final payment no  
               more than 150% of the disputed amount.  (CIV 8812) 

             5)   Requires, in a private work of improvement, a direct  
               contractor to pay any retention proceeds to the  
               subcontractor within 10 days of receiving all or part of a  
               retention payment.  Authorizes the direct contractor, in  
               the event of a good faith dispute over the amount due, to  
               withhold from the retention no more than 150% of the  
               disputed amount.  (CIV 8814)








                                                                  AB 536
                                                                  Page  3


             6)   Requires, in a public work of improvement, a public  
               entity to pay any retention proceeds to the original  
               contractor within 60 days after the completion of the work  
               of improvement.  Defines "completion" as, among other  
               things, the occupation, beneficial use, and enjoyment of a  
               work of improvement or acceptance by the public agency of  
               the work of improvement.  Requires the original contractor  
               to pay any retention proceeds to the subcontractor within 7  
               days of receiving all or part of a retention payment.   
               Authorizes the public entity or the original contractor, in  
               the event of a dispute over the amount due, to withhold  
               from the final payment an amount not to exceed 150% of the  
               disputed amount.  Provides that a public entity or  
               contractor that violates these provisions is liable for a  
               penalty of 2% of the amount wrongfully withheld per month  
               for every month payment is not made.  (PCC 7107)

           FISCAL EFFECT  :   None.  This bill is keyed non-fiscal by the  
          Legislative Counsel.  

           COMMENTS  :   

           1)Purpose of this bill  .  Under existing law, property owners,  
            public entities and contractors may withhold 150% of a  
            disputed amount from the progress payments or retention  
            proceeds otherwise due to a contractor or subcontractor.  This  
            bill would prohibit property owners, public entities and  
            contractors from including "any claim for additional  
            compensation" in the disputed amount subject to the 150%  
            withholding. The aim is to clarify existing law in light of a  
            2009 court case as to what may be treated as the "disputed  
            amount." 

            This bill is sponsored by the Engineering Contractors'  
            Association, California Fence Contractors' Association,  
            California Chapter of the American Fence Association, Marin  
            Builders Association, and the Flasher Barricade Association.    
             

           2)Author's statement  .  According to the author, "The Prompt Pay  
            statutes are turning into a mess of loopholes.  They provide  
            no relief to contractors against a sophisticated owner or a  
            prime contractor against his subcontractors.  Worse, they  
            provide those owners/prime contractors (or even upper tier  








                                                                  AB 536
                                                                  Page  4

            subcontractors against lower tier subcontractors) with excuses  
            for withholding more money due to a loophole within the  
            existing statute [that authorizes contractors to withhold 150%  
            of a disputed amount from the retention proceeds].  
            Unfortunately, 'disputed amount' is not defined in the  
            statute.

            The intent of the proposed amendments in AB 536 is to clarify  
            the law."
             
          3)Prompt payment statutes and disputed amounts  .  Progress  
            payments represent a percentage of the amount of a contract  
            that is paid by a property owner or public entity to an  
            original contractor as the work proceeds, in lieu of paying  
            the full contract price up front or only after the work is  
            completed.  After receiving a progress payment, the original  
            contractor typically pays subcontractors, if any, a portion of  
            that progress payment.  Retention proceeds represent a  
            percentage of the amount of a contract that is withheld from a  
            progress payment by the property owner or public entity from  
            the original contractor, or the original contractor from one  
            of its subcontractors.  By withholding a percentage of a  
            contract payment while the work progresses, the payor  
            maintains a degree of financial control over an incomplete  
            project.  

            Existing law requires these upper tier parties (property  
            owner, public entity, or prime contractor) to pay progress  
            payments and retention proceeds to lower tier parties  
            (contractor or subcontractor) within specified periods of  
            time, and in certain instances, imposes penalties for  
            violating those requirements, including a penalty of 2% of the  
            amount wrongfully withheld per month for every month payment  
            is not made.  

            Existing law also provides a "safe harbor" exception to these  
            provisions: in the event of a good faith dispute on the amount  
            due for progress payments or retention proceeds, upper tier  
            parties are authorized to withhold from the lower tier parties  
            up to 150% of the disputed amount from those progress payments  
            or retention proceeds.  While the intent of the prompt payment  
            statutes are to ensure timely payment for work, the purpose of  
            the 150% withholding is to ensure satisfactory completion of a  
            project and that funds are available to correct defective or  
            incomplete work until the dispute is resolved.  There is  








                                                                  AB 536
                                                                  Page  5

            nothing in statute, however, that defines a "disputed amount"  
            or limits the types of disputes that authorize the 150%  
            withholding.   

           4)Bill responds to lawsuit regarding meaning of "disputed  
            amount"  .  The sponsors assert that ambiguity over the precise  
            meaning of a "disputed amount" has resulted in legal action  
            over withheld amounts.  For example, in the case of Martin  
            Brothers Construction, Inc. v. Thompson Pacific Construction,  
            Inc. (2009) 179 Cal App. 4th 1401,  a subcontractor, Martin  
            Brothers, filed claims directly with the general contractor,  
            Thompson Pacific Construction, for extra work and change  
            orders valued at roughly $400,000.  Martin Brothers later  
            filed with the court an initial complaint, seeking over  
            $900,000 in damages, interests, penalties, and attorney fees,  
            although the amount was later reduced to roughly $630,000.   
            Thompson Pacic initially disputed Martin Brothers claims for  
            extra wo5)rk, but eventually paid more than $630,000 for all  
            outstanding progress payment retention and all extra work.  At  
            trial, Martin Brothers sought only statutory late payment  
            penalties, interest and attorney fees.  

            Thompson Pacific contended that "prompt payment" penalties  
            should not apply because the amount it withheld was a  
            "disputed amount."  Martin Brothers alleged that a "disputed  
            amount" applied only to "honest" disputes, such as when a  
            general contractor has a good faith belief that it does not  
            owe money because the subcontractor's work was substandard,  
            incomplete, or completed improperly, and did not apply to  
            disputes over change order work.  The court sided with  
            Thompson Pacific, reading the statute to be clear on its face  
            and inferring no restriction on the kinds of disputed amounts  
            covered by the statute.  The court affirmed that Thompson  
            Pacific was legally entitled to withhold payment from Martin  
            Brothers for a good faith dispute pursuant to existing law,  
            including for change orders and claims for additional or extra  
            work, even though there was no allegation that the change  
            orders and extra work were faulty. 

            In response to that finding, this bill would exclude from the  
            calculation of a disputed amount "any claims for additional  
            compensation", which is intended to exclude such things as  
            extra work that is not otherwise substandard, incomplete, or  
            completed improperly.









                                                                  AB 536
                                                                  Page  6

           6)Ability to withhold disputed amounts for legitimate disputes  .   
            Under this bill, the amount of a "claim for additional  
            compensation," or claim for compensation above what is  
            included in a contract or contract modification (such as a  
            change order), could not be withheld from progress payments or  
            retention proceeds.  Because these claims are for additional  
            compensation, and not for payment for work or compensation  
            that was already agreed to, there would be no associated  
            progress payments or retention proceeds due for them from  
            which to withhold.  

          As a result, the sponsors contend that this bill would only  
            prevent upper tier parties from withholding 150% of the amount  
            of these disputed claims from unrelated progress payments or  
            retention proceeds to prevent the mere existence of such a  
            claim from justifying a withholding.  In addition, upper tier  
            parties would still be able to use the safe harbor provisions  
            under the prompt payment statutes to withhold from lower tier  
            parties 150% of any other disputed amount from money that  
            would otherwise be due in a progress payment or retention  
            proceeds.

           7)Question for the Committee  .  While the phrase "claims for  
            additional compensation" may be understood to apply to claims  
            for compensation that are in addition to the amount within a  
            contract or contract modification, the exact meaning of the  
            term may not be obvious to all parties.  The author may wish  
            to consider whether it may be beneficial to further clarify  
            the term so there is no potential for confusion within the  
            contracting profession as to what types of payments would be  
            included or excluded.

           8)Arguments in Support  .  According to the sponsors, "[The] long  
            standing loophole [in Prompt Pay statutes] has now created an  
            even more untenable and highly unfair situation due to the  
            recent Martin Brothers [d]ecision.

            The losers in the recent court [c]ase, Martin Brothers, argued  
            good faith withholding cannot include undisputed retention  
            amounts.  The court disagreed because in their 'logic' the  
            extra 50% [an] upper tier contractor is allowed to withhold  
            necessarily has to come from undisputed retention based upon  
            current law.  Martin Brothers also argued retention can be  
            withheld only when the good faith dispute is over the amount  
            of retention owed and not over the amount owed for change  








                                                                  AB 536
                                                                  Page  7

            order work.  The court disagreed because the statute does not  
            use language restricting the word 'dispute.'  Therefore,  
            according to the court, any dispute, including a dispute over  
            extra work, may support withholding retention.

            This case is troubling for general contractors and  
            subcontractors alike.  Although Martin Brothers deals with a  
            subcontractor's claims to a general contractor, the statutes  
            and the case's reasoning apply equally to a general  
            contractor's claims to an owner.  If the paying party in 'good  
            faith' disputes the claims for extra work or change orders,  
            the paying party may withhold from retention the claimed  
            amount plus 50% until the matter is resolved or judgment is  
            entered; thus essentially giving the paying party an  
            interest-free loan for an extended period of time!

            This is absolutely a wrong interpretation which, if allowed to  
            prevail without clarification and guidance of the Legislature,  
            will result in the potential demise of many legitimate  
            contractors who employ thousands of workers statewide.  Now  
            more than ever, this is something that California cannot  
            afford to do for myriad reasons."

           9)Previous Legislation  .  AB 2021 (Wagner) of 2012 would have  
            revised the amount that an owner can withhold from a  
            contractor, and a contractor from a subcontractor, for  
            disputed private works of improvement.  AB 2021 limited the  
            total amount of withholding based on a formula that included,  
            among other things, the amount of liquidated damages assessed  
            against a contractor and 150% of the estimated cost to repair  
            or replace contract work that was not performed.  AB 2021 was  
            held on the Senate Floor.
             
             AB 2549 (Pacheco) of 2004 was similar to AB 2021 (Wagner) of  
            2012, and also limited the total amount of withholding for  
            public and private works of improvement based on a formula  
            that included, among other things, the amount of liquidated  
            damages assessed against a contractor and 150% of the  
            estimated cost to repair or replace contract work that was not  
            performed.  The Governor vetoed AB 2549 with the following  
            message:

               "Existing law, including lien protections and other  
               prompt pay requirements, afford most contractors with  
               sufficient protection to ensure payment on disputed  








                                                                  AB 536
                                                                  Page  8

               payments.   Additionally, I believe this bill will  
               only further complicate the various disparate statutes  
               regarding disputed payments between contractors and  
               owners.  This area of law that is very important to  
               both the consumer and contractor has been amended  
               piecemeal for far too long."

           10)Double-referred  .  This bill is double-referred, and if passed  
            by this Committee will be referred to Assembly Judiciary  
            Committee. 

           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Engineering Contractors' Association (sponsor) 
          California Fence Contractors' Association (sponsor) 
          California Chapter of the American Fence Association (sponsor)
          Marin Builders Association (sponsor) 
          Flasher Barricade Association (sponsor) 
          California Landscape Contractors Association 

           Opposition 
           
          None on file.  
           
          Analysis Prepared by  :    Eunie Linden / B.,P. & C.P. / (916)  
          319-3301