BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 709
                                                                  Page  1

          Date of Hearing:   April 30, 2013

                   ASSEMBLY COMMITTEE ON WATER, PARKS AND WILDLIFE
                                Anthony Rendon, Chair
                   AB 709 (Nestande) - As Amended:  April 11, 2013
           
          SUBJECT  :   Salton Sea

           SUMMARY  :   Designates the Salton Sea Authority (SSA) as the lead  
          agency for restoration of the Salton Sea and requires the State  
          to grant the SSA a 99-year lease for all state-owned lands  
          within the Salton Sea ecosystem, including all state-owned lands  
          underlying the Salton Sea.  Specifically,  this bill :

          1)Designates the SSA as the lead agency for CEQA purposes for  
            restoration of the Salton Sea.

          2)Requires the State Lands Commission and any other applicable  
            state agencies to grant the SSA a 99-year lease for all  
            state-owned lands within the Salton Sea ecosystem, including  
            but not limited to all state-owned lands under the navigable  
            and tidal waterways of the Sea.

          3)Requires the SSA by April 1, 2014 to develop a restoration  
            plan for the Salton Sea that is financially feasible to  
            accomplish the goals of: a) restoring long-term stable aquatic  
            and shoreline habitat; b) mitigating air quality impacts from  
            restoration projects; and c) protecting water quality.

          4)Requires the restoration plan developed by the SSA to be  
            submitted to the Legislative Analyst's Office (LAO) for  
            review, and requires the LAO to complete his or her review by  
            June 1, 2014.

          5)Requires, if the LAO determines the plan is financially  
            feasible and the SSA is capable of implementing the plan, that  
            any bond moneys made available under Proposition 84 for the  
            Salton Sea be continuously appropriated to the SSA to  
            implement the plan.

          6)Requires, if the LAO determines the plan developed by the  
            Authority is financially feasible and the SSA is capable of  
            implementing the plan, that the plan be submitted to the  
            Wildlife Conservation Board (WCB).  Requires the WCB to review  
            the plan and determine whether the plan is an eligible project  








                                                                  AB 709
                                                                  Page  2

            under the federal Salton Sea Reclamation Act of 1998 to  
            receive federal matching funds.  Requires the WCB if it finds  
            that the plan is an eligible project, to seek federal matching  
            funds, and requires any federal funds received to be deposited  
            in the Salton Sea Restoration Fund (SSRF) and continuously  
            appropriated to the SSA to implement the plan.

           EXISTING LAW  :

          1)Establishes the Salton Sea Restoration Act which states  
            legislative intent that:  a) the State undertake the  
            restoration of the Salton Sea ecosystem and the permanent  
            protection of the wildlife dependent on that ecosystem;  b)  
            that restoration be based on the preferred alternative  
            developed as a result of a restoration study and alternative  
            selection process; and, c) that the preferred alternative  
            provide the maximum feasible attainment of specified  
            environmental objectives, including restoration of long-term  
            stable aquatic and shoreline habitat to historic levels and  
            diversity of fish and wildlife dependent on the Salton Sea,  
            elimination of air quality impacts from restoration projects,  
            and protection of water quality.  Provides that for purposes  
            of the restoration plan the Salton Sea ecosystem includes the  
            Salton Sea, agricultural lands surrounding the Sea, and the  
            tributaries and drains within Imperial and Coachella Valleys  
            that deliver water to the Sea.

          2)Requires the Secretary of the Natural Resources Agency, in  
            consultation with the Department of Fish and Wildlife (DFW),  
            the Department of Water Resources (DWR), the SSA, air quality  
            districts, and the Salton Sea Advisory Committee to undertake  
            a restoration study to determine a preferred alternative for  
            restoration of the Salton Sea, to prepare a Programmatic  
            Environmental Impact Report (PEIR) analyzing the alternatives,  
            and to submit a preferred alternative to the Legislature on or  
            before December 31, 2006.

          3)Establishes the SSRF which is administered by the director of  
            DFW.  Authorizes moneys deposited in the SSRF to be expended,  
            upon appropriation by the Legislature, for the following  
            purposes:  a) environmental and engineering studies related to  
            restoration of the Salton Sea and the protection of fish and  
            wildlife dependent on the Sea; b) implementation of  
            conservation measures necessary to protect fish and wildlife  
            dependent on the Sea; c) implementation of the preferred  








                                                                  AB 709
                                                                  Page  3

            Salton Sea restoration alternative; and d) administrative,  
            technical, and public outreach costs related to development  
            and selection of the preferred Salton Sea restoration  
            alternative.   

           FISCAL EFFECT  :   Unknown.   Requires, if certain conditions are  
          met, that any remaining bond funds in the SSRF be continuously  
          appropriated to the SSA.

           COMMENTS  :   The author indicates the purpose of this bill is to  
          designate the SSA as the lead agency for restoration efforts at  
          the Salton Sea, in order to get restoration activities going,  
          rather than continuing to wait for the State to find the money  
          and the political will to do so.  The SSA is a local Joint  
          Powers Authority (JPA) composed of Riverside County, Imperial  
          County, Imperial Irrigation District (IID), Coachella Valley  
          Water District (CVWD), and the Torres Martinez Desert Cahuilla  
          Indian Tribe.  The author asserts that "for far too long a  
          viable solution to the looming environmental and economic crisis  
          facing our region, the decline of the Salton Sea, has eluded  
          policy experts and elected officials?.Despite millions spent on  
          studies, congressional hearings, and federal and state  
          legislation, achieving consensus on how to save the Sea has  
          proved maddeningly elusive." The author notes that in spite of  
          studies, serious environmental concerns continue from lack of  
          action.  This bill would place control of restoration in the  
          hands of the SSA, which the author asserts will enable  
          restoration to begin to move forward.

           Background  :   The Salton Sea, California's largest lake, is  
          located in a low-lying trough or desert sink in Southern  
          California, much of which is below sea level.  The current sea  
          was formed in 1905 when the Colorado River flooded its banks at  
          a faulty irrigation diversion site.  However, the sea bed has  
          periodically filled and receded numerous times, from prehistoric  
          times through the 1800s.  The present sea is fed primarily by  
          agricultural runoff.  Since it has no natural outlet, it is  
          becoming increasingly saline and today is considerably saltier  
          than the ocean.  In 2003, the Legislature approved a package of  
          implementing legislation related to the Quantification  
          Settlement Agreement (QSA) and calling for restoration of the  
          Salton Sea.  The QSA is a collection of agreements between the  
          IID, Metropolitan Water District, San Diego County Water  
          Authority, the CVWD, and the State, that included approval of  
          water transfers from IID, settled a number of claims to the  








                                                                  AB 709
                                                                  Page  4

          Colorado River, and provided a transition period for the State  
          to reduce its consumption of Colorado River water to its 4.4  
          million acre feet entitlement.  Under the QSA, the amount of  
          water flowing into the Salton Sea will be significantly reduced  
          after 2017.  As a result, the Sea will shrink considerably in  
          size, increasing salinity and exposing large areas of dry sea  
          bed playa.

          The Salton Sea is one of the most important wetland areas in  
          California for migratory waterfowl and shorebirds, since over  
          95% of California's historical wetlands have been converted to  
          other land uses.  The Salton Sea supports over 400 species of  
          birds, and is an internationally significant stopover site for  
          hundreds of thousands of birds migrating along the Pacific  
          Flyway.  Recently, fishery resources in the sea have declined  
          significantly due to increasing salinity, evaporation and  
          declining water quality.  Once the QSA water transfers are fully  
          implemented, it is generally recognized that without restoration  
          efforts the ecosystem of the Salton Sea will collapse over the  
          next decade or two.

          The State Natural Resources Agency in 2007 completed a  
          restoration study and released the Salton Sea Ecosystem  
          Restoration Program Plan and Final PEIR.  The Agency estimated  
          that the preferred alternative identified in the PEIR would cost  
          over $8 billion, expended over a period of 75 years, to  
          implement.  The preferred alternative included a saline habitat  
          complex at the north and south end of the Sea, a Marine Sea  
          extending around the northern shoreline in a horseshoe shape,  
          air quality management facilities to reduce particulate  
          emissions from exposed playa, a brine sink for discharge of  
          salts, sedimentation distribution facilities, and early start  
          habitat projects to provide habitat pending completion of other  
          habitat components.  A detailed financing plan was never  
          developed for the preferred alternative, which has not been  
          endorsed by the Legislature.  The PEIR also noted that even the  
          "no project" alternative would cost the State over $1 billion,  
          due to state and federal requirements to address air quality,  
          water quality and habitat issues even if no restoration plan is  
          pursued.
            
          The State Natural Resources Agency, jointly with the U.S. Army  
          Corps of Engineers, in 2012 prepared and released a draft Salton  
          Sea Conservation Habitat (SCH) Project Environmental Impact  
          Statement/Environmental Impact Report (EIS/EIR).  The SCH  








                                                                  AB 709
                                                                 Page  5

          Project EIS/EIR proposes a range of aquatic habitats to support  
          fish and wildlife species dependent on the Salton Sea.  The  
          Natural Resources Agency's preferred alternative identified in  
          the EIS/EIR would include construction of 3,770 acres of habitat  
          ponds.  The Agency has identified this alternative as the  
          preferred alternative because it would provide greater long-term  
          benefits by restoring the greatest amount of habitat, while  
          minimizing environmental impacts to the extent feasible.  To  
          date, several million dollars in Proposition 84 bond funds made  
          available for the Salton Sea have been spent on habitat project  
          planning and environmental work, with some limited on the ground  
          restoration.  The Governor in his 2013-14 proposed budget  
          proposes a $12 million increase in the amount of funds  
          appropriated from the SSRF to fund the first phase of  
          implementation of the SCH Project, including on the ground  
          construction of 800 to 1,200 acres of habitat ponds.  Some  
          funding for implementation of the SCH Project has also been  
          authorized at the federal level but has not yet been  
          appropriated by Congress.

          In addition to the state bond funds made available for the  
          Salton Sea, the SSRF also contains some funding paid by the  
          water agencies that are parties to the QSA.  The water agencies  
          that are parties to the QSA are committed to funding $133  
          million in mitigation costs for habitat restoration and air  
          quality mitigation and monitoring at the Salton Sea (Note: the  
          $133 million is in 2003 dollars.  The actual total amount being  
          expended by the QSA water agencies, which is paid over time, is  
          closer to $300 million).  The State of California, under the  
          QSA-JPA agreement, agreed to assume the costs of mitigating the  
          effects of the QSA beyond the first $133 million.  However, the  
          Third District Court of Appeal has ruled that while the State is  
          contractually liable for the excess mitigation costs, neither  
          the parties to the QSA nor anyone else can compel the  
          Legislature to appropriate funds to pay for the mitigation.  In  
          other words, the State's contractual obligation under the QSA to  
          pay for excess mitigation costs may be unenforceable.

           Another New Plan?  :  This bill requires the SSA to develop yet  
          another new plan for restoration of the Salton Sea within 90  
          days after this bill is enacted.  The new plan would then be  
          submitted to the LAO, which would have 60 days to review the  
          plan and determine if it is financially feasible and if the SSA  
          is capable of implementing it. This bill does not specify where  
          the funding would come from for the SSA to develop the new plan,  








                                                                  AB 709
                                                                  Page  6

          but provides that after the plan is developed, if it is  
          determined by the LAO to be financially feasible and within the  
          capability of the SSA to implement, then any remaining  
          Proposition 84 bond funds in the SSRF would be continuously  
          appropriated to the SSA to implement the new plan.  The WCB  
          would also be required to seek federal matching funds for the  
          new plan, which would also be continuously appropriated to the  
          SSA if received.

           Related Legislation :  This Committee already heard and passed AB  
          71(V. Manuel P�rez), which takes a different approach than this  
          bill, on April 2, 2013.  AB 71 requires the Secretary of the  
          Natural Resources Agency, in consultation and coordination with  
          the SSA, to lead Salton Sea restoration efforts.  Rather than  
          leaving decisions totally up to the State, or transferring  
          authority completely to the local JPA, AB 71 takes a more  
          collaborative approach by providing that the State will continue  
          to have lead responsibility for restoration efforts but will  
          work in collaboration with the SSA.  AB 71 also calls for  
          creation of a technical advisory committee, and, as heard by  
          this committee, would have authorized $2 million from the SSRF  
          to go to the SSA to pay for development of a new feasibility and  
          funding study.  Amendments proposed by the author of AB 71 in  
          the Assembly Appropriations Committee removed the $2 million  
          expenditure authorization, and the author indicated he will  
          instead pursue funding for the study through the budget process.  
           

           Related Budget Actions  :  This bill would, if certain conditions  
          are met, require that any remaining Proposition 84 bond funds in  
          the SSRF be continuously appropriated to the SSA.   As explained  
          above, the Governor's 2013-14 budget proposes an increase of  
          $12.1 million in the amount of Proposition 84 bond funds  
          appropriated from the SSRF to DWR and DFW for the restoration of  
          between 800 and 1,200 acres of habitat. The proposal will  
          implement a pilot project to create habitat through the  
          construction of ponds at sites where the sea bed is exposed  
          because of evaporation. The proposal also requests  
          re-appropriation of funds to provide additional funding for the  
          restoration project, which is estimated to cost approximately  
          $28 million to complete. If this appropriation is approved as  
          part of the final 2013-14 state budget, the balance of the  
          original $47 million in Proposition 84 bond funds made available  
          for the Salton Sea, and still unappropriated and available for  
          purposes of this , would only be about $3 million.  It is also  








                                                                  AB 709
                                                                  Page  7

          worth noting that the Governor's budget only appropriates  
          funding for implementation of a portion of the SCH Project.   

           Additional Issues for committee consideration  :  While it is  
          understandable that local communities and groups at the Salton  
          Sea are frustrated with the lack of progress on Salton Sea  
          restoration efforts, the committee may wish to consider whether  
          shifting all state responsibility and authority to the SSA, a  
          local JPA, is the most appropriate solution.  Even if the state  
          transfers authority and funding to the SSA to undertake  
          restoration activities at the Salton Sea, the state would  
          presumably still be responsible for ensuring that state laws  
          requiring compliance with air quality standards, habitat  
          mitigation, and water quality laws are met, but would have given  
          up control over the limited state funding currently available  
          for these purposes.  In addition, this bill requires that the  
          State grant a 99-year lease to the SSA of all state lands in the  
          Salton Sea ecosystem.  The Salton Sea ecosystem, as currently  
          defined in the Fish and Game Code, includes the Salton Sea, the  
          agricultural lands surrounding the Sea, and the tributaries and  
          drains within the Imperial and Coachella Valleys that deliver  
          water to the Salton Sea.  The state lands required to be leased  
          to the SSA would also include all state owned lands that  
          underlie the navigable and tidal waterways of the Salton Sea.

          This bill further requires that any remaining state bond funds  
          in the SSRF be continuously appropriated to the SSA if the LAO  
          makes certain findings.  This raises several issues.  First, the  
          Legislature has generally disfavored continuous appropriations  
          because they diminish state oversight over the expenditure and  
          accountability of state funds.  Second, while the LAO fulfills  
          an important and valued role in providing advice and analysis to  
          the Legislature, the Legislature does not generally give the LAO  
          the authority to determine future state expenditure decisions  
          for the Legislature.  This bill would require that existing  
          state funds be continuously appropriated to a local JPA for  
          implementation of a future plan that has yet to be developed,  
          with the only precondition being that the LAO make a  
          determination that the plan is financially feasible and capable  
          of being implemented by the SSA.  Third, if all of the limited  
          state bond funds remaining in the SSRF are appropriated to the  
          SSA, these funds would not be available to implement the SCH  
          Plan already prepared by the State, which even some of the  
          members of the SSA agree should be implemented, and includes  
          shovel ready habitat conservation projects which the Governor is  








                                                                  AB 709
                                                                  Page  8

          proposing to fund in the 2013-14 state budget. 

          Additional questions the committee may wish to consider include:  
           In light of the various feasibility issues, complexities and  
          questions that have arisen regarding the 2007 proposed  
          restoration plan, does the SSA have the capacity and resources  
          to develop a new financially feasible restoration plan within  
          just 90 days?  How would the development of the plan be paid  
          for?  Is it realistic to assume that the LAO could review the  
          proposed plan and make a determination as to feasibility and  
          capacity within just 60 days?  Assuming a viable restoration  
          plan could be developed by the SSA in 90 days, if there is only  
          $3 million in unappropriated Proposition 84 bond funds left  
          available for the Salton Sea, is this the best use of those  
          funds?

          Finally, since this bill takes a different approach to  
          governance of Salton Sea restoration activities than AB 71 (V.  
          Manuel P�rez), which this committee already approved, the  
          committee may wish to consider that if the committee were to  
          pass this bill as well it would be taking a position  
          inconsistent with the policy approach already approved by the  
          committee in AB 71. 

           Support Arguments  :  Supporters assert this bill will kick start  
          restoration of the Salton Sea and is crucial to the future of  
          the Salton Sea and the communities around the Sea.  

           REGISTERED SUPPORT / OPPOSITION  :

           Support                                   Opposition  
          Coachella Valley Economic PartnershipNone on file.
          Indio Chamber of Commerce
          Palm Springs Chamber of Commerce
           
          Analysis Prepared by  :    Diane Colborn / W., P. & W. / (916)  
          319-2096