Amended in Assembly March 28, 2014

California Legislature—2013–14 Regular Session

Assembly BillNo. 1705


Introduced by Assembly Member Williams

February 13, 2014


An act to amend Sections 7201 and 10261 of the Public Contract Code, relating to public contracts.

LEGISLATIVE COUNSEL’S DIGEST

AB 1705, as amended, Williams. Public contracts:begin delete paymentend deletebegin insert payment.end insert

Existing law authorizes the retention proceeds withheld from any payment by an awarding entity, as described, from the original contractor, by the original contractor from any subcontractor, and by a subcontractor from any subcontractor to exceed 5% on specific projects where the director of thebegin insert applicableend insert departmentbegin insert, as specified,end insert has made, or the governing body of the public entity or designated official of the public entity has approved, a finding prior to the bid that the project is substantially complex and requires a higher retentionbegin delete, as specified.end deletebegin insert and the department or public entity includes both this finding and the actual retention amount in the bid documents.end insert

This billbegin delete would indicate the intent of the Legislature to define the term “substantially complex” for purposes of these provisions.end deletebegin insert, instead of requiring that the finding and actual retention amount be included in the bid documents, would require that the bid documents include details explaining the basis for the finding in addition to the actual retention amount. The bill would also define projects that are not “substantially complex.”end insert

Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.

The people of the State of California do enact as follows:

P2    1

SECTION 1.  

Section 7201 of the Public Contract Code is
2amended to read:

3

7201.  

(a) (1) This section shall apply with respect to all
4contracts entered into on or after January 1, 2012, between a public
5entity and an original contractor, between an original contractor
6and a subcontractor, and between all subcontractors thereunder,
7relating to the construction of any public work of improvement.

8(2) Under no circumstances shall any provision of this section
9be construed to limit the ability of any public entity to withhold
10150 percent of the value of any disputed amount of work from the
11final payment, as provided for in subdivision (c) of Section 7107.
12In the event of a good faith dispute, nothing in this section shall
13be construed to require a public entity to pay for work that is not
14approved or accepted in accordance with the proper plans or
15specifications.

16(3) For purposes of this section, “public entity” means the state,
17including every state agency, office, department, division, bureau,
18board, or commission, the California State University, the
19University of California, a city, county, city and county, including
20charter cities and charter counties, district, special district, public
21authority, political subdivision, public corporation, or nonprofit
22transit corporation wholly owned by a public agency and formed
23to carry out the purposes of the public agency.

24(b) (1) The retention proceeds withheld from any payment by
25a public entity from the original contractor, by the original
26contractor from any subcontractor, and by a subcontractor from
27any subcontractor thereunder shall not exceed 5 percent of the
28payment. In no event shall the total retention proceeds withheld
29exceed 5 percent of the contract price. In a contract between the
30original contractor and a subcontractor, and in a contract between
31a subcontractor and any subcontractor thereunder, the percentage
32of the retention proceeds withheld shall not exceed the percentage
33specified in the contract between the public entity and the original
34contractor.

35(2) This subdivision shall not apply if the contractor provides
36written notice to the subcontractor, pursuant to subdivision (c) of
37Section 4108, prior to, or at, the time that the bid is requested, that
38bonds shall be required, and the subcontractor subsequently is
P3    1unable or refuses to furnish to the contractor a performance and
2payment bond issued by an admitted surety insurer.

3(3) Notwithstanding any other provision of this subdivision, the
4retention proceeds withheld from any payment by an awarding
5entity set forth in paragraphs (1) to (5), inclusive, of subdivision
6(a) of Section 10106, from the original contractor, by the original
7contractor from any subcontractor, and by a subcontractor from
8any subcontractor thereunder, may exceed 5 percent on specific
9projects where the director of the department has made a finding
10prior to the bid that the project is substantially complex, as defined,
11and therefore requires a higher retention amount than 5 percent
12and the department includesbegin delete both this finding and the actual
13retention amount in the bid documents.end delete
begin insert in the bid documents details
14 explaining the basis for the finding and the actual retention
15amount.end insert
In a contract between the original contractor and a
16subcontractor, and in a contract between a subcontractor and any
17subcontractor thereunder, the percentage of the retention proceeds
18withheld shall not exceed the percentage specified in the contract
19between the department and the original contractor.

20(4) Notwithstanding any other provision of this subdivision, the
21retention proceeds withheld from any payment by the awarding
22entity of a city, county, city and county, including charter cities
23and charter counties, district, special district, public authority,
24political subdivision, public corporation, or nonprofit transit
25corporation wholly owned by a public agency and formed to carry
26out the purposes of the public agency, from the original contractor,
27by the original contractor from any subcontractor, and by a
28subcontractor from any subcontractor thereunder, may exceed 5
29percent on specific projects where the governing body of the public
30entity or designee, including, but not limited to, a general manager
31or other director of an appropriate department, has approved a
32findingbegin insert, on a project by project basis,end insert during a properly noticed
33and normally scheduled public hearing and prior to bid that the
34project is substantially complex, as defined, and therefore requires
35a higher retention amount than 5 percent and the awarding entity
36includesbegin delete both this finding and the actual retention amount in the
37bid documents.end delete
begin insert in the bid documents details explaining the basis
38for the finding and the actual retention amount.end insert
In a contract
39between the original contractor and a subcontractor, and in a
40contract between a subcontractor and any subcontractor thereunder,
P4    1the percentage of the retention proceeds withheld shall not exceed
2the percentage specified in the contract between the department
3and the original contractor.

4(5) As used in this subdivision,begin insert projects are notend insert “substantially
5complex”begin delete means ______.end deletebegin insert if they are either of the following:end insert

begin insert

6(A) Regularly, customarily, or routinely performed by the agency
7or by licensed contractors.

end insert
begin insert

8(B) Maintenance projects.

end insert

9(c) A party identified in subdivision (a) shall not require any
10other party to waive any provision of this section.

11(d) This section shall remain in effect only until January 1, 2016,
12and as of that date is repealed, unless a later enacted statute, that
13is enacted before January 1, 2016, deletes or extends that date.

14

SEC. 2.  

Section 10261 of the Public Contract Code, as amended
15by Section 6 of Chapter 700 of the Statutes of 2011, is amended
16to read:

17

10261.  

(a) Payments upon contracts shall be made as the
18department prescribes upon estimates made and approved by the
19department, but progress payments shall not be made in excess of
20100 percent of the percentage of actual work completed plus a like
21percentage of the value of material delivered on the ground or
22stored subject to or under the control of the state, and unused,
23except as otherwise provided in this section. The department shall
24withhold not more than 5 percent of the contract price until final
25completion and acceptance of the project. However, at any time
26after 95 percent of the work has been completed, the department
27may reduce the funds withheld to an amount not less than 125
28percent of the estimated value of the work yet to be completed, as
29determined by the department, if the reduction has been approved,
30in writing, by the surety on the performance bond and by the surety
31on the payment bond. The Controller shall draw his or her warrants
32upon estimates so made and approved by the department and the
33Treasurer shall pay them. The funds may be released by electronic
34transfer if that procedure is requested by the contractor, in writing,
35and if the public entity has, in place at the time of the request, the
36mechanism for the transfer.

37(b) (1) Notwithstanding this section, when the director of the
38department has made a finding prior to the bid that a specified
39project is substantially complex, as defined, and therefore requires
40a higher retention amount than 5 percent, and the department
P5    1includesbegin delete both this finding and the actual retention amount in the
2bid documents,end delete
begin insert in the bid documents details explaining the basis
3for the finding and the actual retention amount,end insert
then payments
4upon contracts by the department shall be made as the department
5prescribes upon estimates made and approved by the department.
6However, progress payments shall not be made in excess of 95
7percent of the percentage of actual work completed, plus a like
8percentage of the value of material delivered on the ground or
9stored, subject to, or under the control of the state, and unused,
10except as otherwise provided in this section. At any time after 95
11percent of the work has been completed, the department may reduce
12the funds withheld to an amount not less than 125 percent of the
13estimated value of the work yet to be completed, as determined
14by the department, if the reduction has been approved, in writing,
15by the surety on the performance bond and by the surety on the
16payment bond. The Controller shall draw his or her warrants upon
17estimates so made and approved by the department and the
18Treasurer shall pay them with funds appropriated therefor. The
19funds may be released by electronic transfer if that procedure is
20requested by the contractor, in writing, and if the public entity has,
21in place at the time of the request, the mechanism for the transfer.

22(2) As used in this subdivision,begin insert projects are notend insert “substantially
23complex”begin delete means ______.end deletebegin insert if they are either of the following:end insert

begin insert

24(A) Regularly, customarily, or routinely performed by the agency
25or by licensed contractors.

end insert
begin insert

26(B) Maintenance projects.

end insert

27(c) This section shall remain in effect only until January 1, 2016,
28and as of that date is repealed, unless a later enacted statute, that
29is enacted before January 1, 2016, deletes or extends that date.



O

    98