AB 1823, as introduced, Wagner. Contractors: payments.
Existing law allows specified persons to withhold from a contractor or subcontractor no more than 150% of the disputed amount if there is a good faith dispute over the amount due on a contract payment.
This bill would exclude the amount of specified claims from being considered disputed amounts, as provided.
Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.
The people of the State of California do enact as follows:
Section 7108.5 of the Business and Professions
2Code is amended to read:
(a) A prime contractor or subcontractor shall pay to
4any subcontractor, not later than seven days after receipt of each
5progress payment, unless otherwise agreed to in writing, the
6respective amounts allowed the contractor on account of the work
7performed by the subcontractors, to the extent of each
8subcontractor’s interest therein. In the event that there is a good
P2 1faith dispute over all or any portion of the amount due on a progress
2payment from the prime contractor or subcontractor to a
3subcontractor, the prime contractor or subcontractor may withhold
4no more than 150 percent of the disputed amount.
5(b) Any violation of this section shall constitute a cause for
6disciplinary action and shall subject the licensee to a penalty,
7payable to the subcontractor, of 2
percent of the amount due per
8month for every month that payment is not made.
9(c) In any action for the collection of funds wrongfully withheld,
10the prevailing party shall be entitled to his or herbegin delete attorney’send delete
11begin insert attorneysend insertbegin insert’end insert fees and costs.
12(d) The sanctions authorized under this section shall be separate
13from, and in addition to, all other remedies, either civil,
14administrative, or criminal.
15(e) This section applies to all private works of improvement
16and to all public works of improvement, except where Section
1710262 of the
Public Contract Code applies.
18(f) For purposes of this section, a “disputed amount” shall not
19include the amount of any claim for additional compensation by
20the subcontractor against the prime contractor.
Section 8800 of the Civil Code is amended to read:
(a) Except as otherwise agreed in writing by the owner
23and direct contractor, the owner shall pay the direct contractor,
24within 30 days after notice demanding payment pursuant to the
25contract is given, any progress payment due as to which there is
26no good faith dispute between them. The notice given shall comply
27with the requirements of Chapter 2 (commencing with Section
288100) of Title 1.
29(b) If there is a good faith dispute between the owner and direct
30contractor as to a progress payment due, the owner may withhold
31from the progress payment an amount not in excess of 150 percent
32of the disputed amount.
33(c) An owner that violates this section is liable to the direct
34contractor for a penalty of 2 percent
per month on the amount
35wrongfully withheld, in place of any interest otherwise due. In an
36action for collection of the amount wrongfully withheld, the
37prevailing party is entitled to costs andbegin delete aend delete reasonablebegin delete attorney’s feeend delete
38begin insert attorneys’ feesend insert.
P3 1(d) This section does not supersede any requirement of Article
22 (commencing with Section 8810) relating to the withholding of
3a retention.
4(e) For purposes of this section, a “disputed amount” shall not
5include the amount of any claim for additional compensation by
6the direct contractor
against the owner.
Section 8802 of the Civil Code is amended to read:
(a) This section applies to a contract between a public
9utility and a direct contractor for all or part of a work of
10improvement.
11(b) Unless the direct contractor and a subcontractor otherwise
12agree in writing, within 21 days after receipt of a progress payment
13from the public utility the direct contractor shall pay the
14subcontractor the amount allowed the direct contractor on account
15of the work performed by the subcontractor to the extent of the
16subcontractor’s interest in the work. If there is a good faith dispute
17over all or part of the amount due on a progress payment from the
18direct contractor to a subcontractor, the direct contractor may
19withhold an amount not in excess of 150 percent of the disputed
20amount.
21(c) A direct contractor that violates this section is liable to the
22subcontractor for a penalty of 2 percent of the disputed amount
23due per month for every month that payment is not made. In an
24action for collection of the amount wrongfully withheld, the
25prevailing party is entitled to costs andbegin delete aend delete reasonablebegin delete attorney’s feeend delete
26begin insert attorneys’ feesend insert.
27(d) This section does not limit or impair a contractual,
28administrative, or judicial remedy otherwise available to a
29contractor or subcontractor in a dispute involving late payment or
30nonpayment by the contractor or deficient performance or
31nonperformance by the subcontractor.
32(e) For purposes of this section, a “disputed amount” shall not
33include the amount of any claim for additional compensation by
34the subcontractor against the direct contractor.
Section 8812 of the Civil Code is amended to read:
(a) If an owner withholds a retention from a direct
37contractor, the owner shall, within 45 days after completion of the
38work of improvement, pay the retention to the contractor.
39(b) If part of a work of improvement ultimately will become
40the property of a public entity, the owner may condition payment
P4 1of a retention allocable to that part on acceptance of the part by
2the public entity.
3(c) If there is a good faith dispute between the owner and direct
4contractor as to a retention payment due, the owner may withhold
5from final payment an amount not in excess of 150 percent of the
6disputed amount.begin insert This withheld amount shall
not be considered
7wrongfully withheld.end insert
8(d) For purposes of this section, a “disputed amount” shall not
9include the amount of any claim for additional compensation by
10the direct contractor against the owner.
Section 8814 of the Civil Code is amended to read:
(a) If a direct contractor has withheld a retention from
13one or more subcontractors, the direct contractor shall, within 10
14days after receiving all or part of a retention payment, pay to each
15subcontractor from whom retention has been withheld that
16subcontractor’s share of the payment.
17(b) If a retention received by the direct contractor is specifically
18designated for a particular subcontractor, the direct contractor shall
19pay the retention payment to the designated subcontractor, if
20consistent with the terms of the subcontract.
21(c) If a good faith dispute exists between the direct contractor
22and a subcontractor, the direct contractor may withhold from the
23retention to the subcontractor an amount not
in excess of 150
24percent of the estimated value of the disputed amount.
25(d) For purposes of this section, a “disputed amount” shall not
26include the amount of any claim for additional compensation by
27the subcontractor against the direct contractor.
Section 7107 of the Public Contract Code is amended
29to read:
(a) This section is applicable with respect to all contracts
31entered into on or after January 1, 1993, relating to the construction
32of any public work of improvement.
33(b) The retention proceeds withheld from any payment by the
34public entity from the original contractor, or by the original
35contractor from any subcontractor, shall be subject to this section.
36(c) Within 60 days after the date of completion of the work of
37improvement, the retention withheld by the public entity shall be
38released. In the event of a dispute between the public entity and
39the original contractor, the public entity may withhold from the
40final payment an amount not to exceed 150 percent of
the disputed
P5 1amount. For purposes of this subdivision, “completion” means any
2of the following:
3(1) The occupation, beneficial use, and enjoyment of a work of
4improvement, excluding any operation only for testing, startup, or
5commissioning, by the public agency, or its agent, accompanied
6by cessation of labor on the work of improvement.
7(2) The acceptance by the public agency, or its agent, of the
8work of improvement.
9(3) After the commencement of a work of improvement, a
10cessation of labor on the work of improvement for a continuous
11period of 100 days or more, due to factors beyond the control of
12the contractor.
13(4) After the commencement of a work of improvement, a
14cessation of labor on the work of improvement for a continuous
15period of 30 days or
more, if the public agency files for record a
16notice of cessation or a notice of completion.
17(d) Subject to subdivision (e), within seven days from the time
18that all or any portion of the retention proceeds are received by
19the original contractor, the original contractor shall pay each of its
20subcontractors from whom retention has been withheld, each
21subcontractor’s share of the retention received. However, if a
22retention payment received by the original contractor is specifically
23designated for a particular subcontractor, payment of the retention
24shall be made to the designated subcontractor, if the payment is
25consistent with the terms of the subcontract.
26(e) The original contractor may withhold from a subcontractor
27its portion of the retention proceeds if a bona fide dispute exists
28between the subcontractor and the original contractor. The amount
29withheld from the retention
payment shall not exceed 150 percent
30of the estimated value of the disputed amount.
31(f) In the event that retention payments are not made within the
32time periods required by this section, the public entity or original
33contractor withholding the unpaid amounts shall be subject to a
34charge of 2 percent per month on the improperly withheld amount,
35in lieu of any interest otherwise due. Additionally, in any action
36for the collection of funds wrongfully withheld, the prevailing
37party shall be entitled tobegin delete attorney’send deletebegin insert attorneysend insertbegin insert’end insert fees and costs.
38(g) If a state agency retains an amount greater
than 125 percent
39of the estimated value of the work yet to be completed pursuant
40to Section 10261, the state agency shall distribute undisputed
P6 1retention proceeds in accordance with subdivision (c). However,
2notwithstanding subdivision (c), if a state agency retains an amount
3equal to or less than 125 percent of the estimated value of the work
4yet to be completed, the state agency shall have 90 days in which
5to release undisputed retentions.
6(h) Any attempted waiver of the provisions of this section shall
7be void as against the public policy of this state.
8(i) For purposes of this section, a “disputed amount” and “bona
9fide dispute” shall not include the amount of any claim for
10additional compensation by the original contractor or
11subcontractor.
Section 10262.5 of the Public Contract Code is
13amended to read:
(a) begin insert(1)end insertbegin insert end insert Notwithstanding any other law, a prime
15contractor or subcontractor shall pay to any subcontractor, not later
16than seven days after receipt of each progress payment, the
17respective amounts allowed the contractor on account of the work
18performed by the subcontractors, to the extent of each
19subcontractor’s interest therein. In the event that there is a good
20faith dispute over all or any portion of the amount due on a progress
21payment from the prime contractor or subcontractor to a
22subcontractor, then the prime contractor or subcontractor may
23withhold no more than 150 percent of the
disputed amount.
24Any
end delete
25begin insert(2)end insertbegin insert end insertbegin insertAnyend insert contractor who violates this section shall pay to the
26subcontractor a penalty of 2 percent of the amount due per month
27for every month that payment is not made. In any action for the
28collection of funds wrongfully withheld, the prevailing party shall
29be entitled to his or herbegin delete attorney’send deletebegin insert attorneysend insertbegin insert’end insert fees and costs.
30(b) This section shall not be construed to limit or impair any
31contractual, administrative, or judicial remedies otherwise available
32to a contractor or a subcontractor in the event of a dispute involving
33late payment or nonpayment by a contractor or deficient
34subcontract performance or nonperformance by a subcontractor.
35(c) On or before September 1 of each year, the head of each
36state agency shall submit to the Legislature a report on the number
37and dollar volume of written complaints received from
38subcontractors and prime contractors on contracts in excess of
39three hundred thousand dollars ($300,000), relating to violations
40of this section.
P7 1(d) For purposes of this section, a “disputed amount” shall not
2include the amount of any claim
for additional compensation by
3the subcontractor against the prime contractor.
O
99