BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 1939
                                                                  Page  1

          Date of Hearing:  April 29, 2014

                           ASSEMBLY COMMITTEE ON JUDICIARY
                                Bob Wieckowski, Chair
                     AB 1939 (Daly) - As Amended:  April 24, 2014
           
                                   PROPOSED CONSENT
           
          SUBJECT  :  PUBLIC WORKS: CONTRACTOR COSTS

           KEY ISSUE  :  SHOULD CONTRACTORS HAVE ADDITIONAL REMEDIES FOR COST  
          RECOVERY WHEN A PROJECT IS DEEMED TO BE A PUBLIC WORK? 

                                      SYNOPSIS

          This is a non-controversial bill to extend an existing principle  
          regarding the recovery of increased costs when a project is  
          deemed to be a public work.  Under existing law, contractors are  
          generally required to pay prevailing wages to workers on public  
          works projects.  However, situations sometimes arise in which  
          the contractor was not informed that the project would be a  
          public works project, or a subsequent administrative or court  
          decision classifies the project, or a portion of the project, as  
          a public works project.  In such a situation, the contractor may  
          be responsible for the payment of the difference between the  
          prevailing wages and the wages actually paid, and associated  
          penalties and other sums.  This bill proposes to establish  
          similar remedies for a contractor to recover increased costs  
          from the party it directly contracts with (such as a private  
          developer) under similar circumstances.

           SUMMARY  :  Authorizes a contractor to bring an action against a  
          party (such as a developer) to recover increased costs as a  
          result of a subsequent decision that classifies a project, or  
          any portion thereof, as a public work, as specified.   
          Specifically,  this bill  :  

          1)Authorizes a contractor to bring an action to recover from the  
            party it directly contracts with, any specified increased  
            costs as a result of any decision by the Department of  
            Industrial Relations, the Labor and Workforce Development  
            Agency, or a court that classifies, after the time at which  
            the contracting party accepts the contractor's bid, awards the  
            contractor a contract under circumstances where no bid is  
            solicited, or otherwise allows construction by the contractor  








                                                                  AB 1939
                                                                  Page  2

            to proceed, the work covered by the project, or any portion  
            thereof, as a public work.

          2)Provides that this authorization does not apply if either of  
            the following is true:

             a)   The developer of a construction project or its agent  
               expressly advised the contractor that the work to be  
               covered by the contract would be a public work.

             b)   A contractor on the developer's construction project  
               expressly advised the contractor that the work subject to  
               the contract would be a public work.

          3)Specifies that, in order to be entitled to the recovery of  
            increased costs, the contractor shall notify the developer  
            within 30 days after receipt of the notice of a decision by  
            the Department of Industrial Relations or the Labor and  
            Workforce Development Agency, or the initiation of any action  
            in a court alleging, that the work covered by the project, or  
            any portion thereof, is a public work.

          4)Provides that a contractor is not required to list any  
            prevailing wages or apprenticeship standard violations on a  
            prequalification questionnaire that are the direct result of  
            the failure of the developer of a construction project or its  
            agent, or a contractor, to notify contractors that the  
            project, or any portion thereof, should have been a public  
            work.

          5)Provides that these provisions do not apply to private  
            residential projects built on private property unless the  
            project is built pursuant to an agreement with a state agency,  
            redevelopment agency, or local public housing authority.

          6)Provides that these provisions do not apply if the conduct of  
            the contractor caused the project to be a "public work," or if  
            the contractor has actual knowledge that the work is a public  
            work.

           EXISTING LAW  generally requires the payment of prevailing wages  
          to workers employed on public works projects of greater than  
          $1,000.  (Labor Code section 1781.)

           FISCAL EFFECT  :  As currently in print this bill is keyed  








                                                                  AB 1939
                                                                  Page  3

          non-fiscal.

           COMMENTS  :  Under existing law, contractors are generally  
          required to pay prevailing wages to workers on "public works"  
          projects.  However, situations sometimes arise in which the  
          contractor was not informed that the project would be a "public  
          works" project, or a subsequent administrative or court decision  
          classifies the project, or a portion of the project, as a public  
          works project.  In such a situation, the contractor may be  
          responsible for the payment of the difference between the  
          prevailing wages and the wages actually paid, and associated  
          penalties and other sums.

          Existing law already provides remedies to contractors to recover  
          such increased costs on contracts awarded by an "awarding body"  
          (generally a public agency) under certain circumstances.  For  
          example, existing law already authorizes a contractor to bring  
          an action to recover from an awarding body specified increased  
          costs if either the awarding body previously affirmatively  
          represented to the contractor that the work to be covered by the  
          bid or contract was not a "public work" or the awarding body  
          received actual written notice from the Department of Industrial  
          Relations that the work to be covered by the bid or contract is  
          a "public work" and failed to disclose that information to the  
          contractor.

          In addition, current law authorizes a contractor to bring an  
          action to recover from an awarding body specified increased  
          costs incurred by the contractor as a result of a decision of  
          the awarding body, the Department of Industrial Relations, or a  
          court that classifies the work as a "public work," if that body,  
          before the bid opening or awarding of the contract, failed to  
          identify the project as a "public work" in the bid specification  
          or in the contract documents that portion of the work that the  
          decision classifies as a "public work."

          This bill proposes to establish similar remedies for a  
          contractor to recover increased costs from the party it directly  
          contracts with (such as a private developer) under similar  
          circumstances.

           ARGUMENTS IN SUPPORT  :  This bill is jointly sponsored by the  
          Associated General Contractors (AGC) and the Construction  
          Employers' Association (CEA).  They argue that, because  
          developers have no legal obligation to inform contractors if  








                                                                  AB 1939
                                                                  Page  4

          they took public subsidies, contractors have no way of knowing  
          if prevailing wages are required.  This means that workers may  
          not receive the correct wages until and if an enforcement action  
          or legal action is taken.  Additionally, the contractor and  
          subcontractors may be subject to prevailing wage penalties,  
          liquidated damages and legal fees, simply because they were not  
          informed that the developer took a public subsidy that triggered  
          a prevailing wage requirement.

          The sponsors point to a recent case involving Hensel Phelps  
          Construction Company and the Hilton San Diego Bayfront Hotel as  
          highlighting the need for this bill.  According to the sponsors,  
          Hensel Phelps (the prime contractor) asked the San Diego Port  
          District and the hotel developer in writing if the project  
          involved the use of public funds and if prevailing wages would  
          be required to be paid.  The sponsors allege that the contractor  
          was told that the project would not be a public works project.   
          However, subsequently the Department of Industrial Relations  
          (DIR) determined that the project was a public work due to a  
          $46.5 million rent credit provided by the San Diego Port  
          District.  As the prime contractor, Hensel Phelps was liable for  
          the payment of prevailing wages and associated penalties and  
          costs, ultimately paying over $8 million in a payment plan with  
          DIR.  The contractor is reportedly engaged in litigation at this  
          time to recover increased costs from the San Diego Port  
          District.

          Therefore, in order to address this situation in future cases,  
          the sponsors state that this bill provides that if a developer  
          fails to inform a contractor that prevailing wages are required  
          and it is subsequently determined that prevailing wages are  
          required, the owner or developer must reimburse the contractor  
          for unpaid wages, sums incurred pursuant to the Labor Code and  
          attorney's fees associated with their failure to provide  
          direction to the contractor.  If an owner or developer does  
          inform a contractor that prevailing wages are required, and the  
          contractor fails to inform subcontractors about the prevailing  
          wage requirement, the contractor then will be liable for unpaid  
          wages, sums incurred pursuant to the Labor Code and attorney's  
          fees associated with their failure to provide direction to the  
          subcontractors.

          The sponsors conclude that this bill will ensure the timely  
          payment of prevailing wages and reduce enforcement actions by  
          the Department of Industrial Relations.








                                                                  AB 1939
                                                                  Page  5


           REGISTERED SUPPORT / OPPOSITION  :   

           Support 
           
          Air Conditioning Trade Association
          Associated Builders and Contractors - San Diego Chapter
          Associated General Contractors of California (co-sponsor)
          California Professional Association of Specialty Contractors
          Construction Employers' Association (co-sponsor)
          Plumbing-Heating-Cooling Contractors Association of California
          Western Electrical Contractors Association

           Opposition 
           
          None on file
           
          Analysis Prepared by  :   Kevin G. Baker / JUD. / (916) 319-2334