Amended in Senate August 4, 2014

Amended in Senate June 30, 2014

Amended in Assembly May 23, 2014

Amended in Assembly April 24, 2014

Amended in Assembly April 7, 2014

California Legislature—2013–14 Regular Session

Assembly BillNo. 2471


Introduced by Assembly Member Frazier

(Coauthors: Senators Cannella and Galgiani)

February 21, 2014


An act to add Section 7204 to the Public Contract Code, relating to public contracts.

LEGISLATIVE COUNSEL’S DIGEST

AB 2471, as amended, Frazier. Public contracts: change orders.

Existing law contains various provisions relating to contracts by a public entity for the performance of public works of improvement, including provisions for the payment of progress payments and the disbursing and withholding of retention proceeds. Existing law, until January 1, 2016, prohibits progress payments upon state contracts from being made in excess of 100% of the percentage of actual work completed, and authorizes the Department of General Services to withhold not more than 5% of the contract price until final completion and acceptance of the project, except as specified.

This bill would require a public entity, as defined, when authorized to order changes or additions to the work in a public works contract awarded to the lowest bidder, to issue a change order promptly, and no later than 60 days after the extra work isbegin delete complete and a specified agreement is reached.end deletebegin insert performed and documentationend insertbegin insert has been submitted, as specified.end insert The bill would, if this requirement is not met, make the public entity liable to the original contractor for the completed extra workbegin delete in accordance with any provisions for change order work that may be contained in the public works contractend delete. The bill would require prejudgment interest to accrue on any amountbegin delete for which the public entity fails to issue a change order promptly or make a payment due pursuant to this bill.end deletebegin insert that this bill would require to be paid that the public entity fails to pay.end insert The bill would also authorize an original contractor to present to the public entity a request for a change order for extra work performed by a subcontractor, including a lower tier subcontractor. It would also authorize a subcontractor to request that an original contractor present a change order request for extra work directed by the public entity that was performed by the subcontractor or lower tier subcontractor. The bill would require the original contractor to notify the subcontractor as to whether the original contractor presented the request to the public entity, as specified.

Vote: majority. Appropriation: no. Fiscal committee: yes. State-mandated local program: no.

The people of the State of California do enact as follows:

P2    1

SECTION 1.  

Section 7204 is added to the Public Contract
2Code
, to read:

3

7204.  

(a) (1) Except as otherwise provided in paragraph (2),
4a public entity, when authorized to order changes or additions to
5the work in a public works contract awarded to the lowest bidder,
6shall, for extra work required of the original contractorbegin delete ordered by
7the dulyend delete
begin insert by anend insert authorized representative of the public entity,begin delete and
8subject to any limitations on that authorization,end delete
issue a change
9order for thebegin delete authorizedend deletebegin insert extraend insert work promptly, and in no event later
10than 60 days after the extra work isbegin delete complete and an agreement is
11reached concerning the merit, conditions, costs, and time for
12performance.end delete
begin insert performed and the original contractor has submitted
13documentation setting forth the reasons and providing sufficient
14support that a fair and equitable adjustment in the contractor’s
15compensation or time for performance, or both is warranted. For
16purposes of this section, extra work includes extra work performed
P3    1by the original contractor, a subcontractor, or a lower tier
2subcontractor. Extra work also includes work or requirements
3that differ from those under the public works contract with the
4public entity before the amendment of the contract by the change
5 order.end insert
An original contractor shall respond promptly to a request
6from thebegin delete dulyend delete authorized representative of the public entity for
7documentationbegin delete to support a request for aend deletebegin insert necessary to warrant theend insert
8 change order. Each public entity shall specify in the public works
9contract the information that shall be required from the contractor
10to support any requested change order.

11(2) begin delete(A)end deletebegin deleteend deleteWhen a change order is subject to approval by the
12governing body of a public entity, but the governing body is not
13scheduled to meet in the 60 days following the performance of
14extra work, and reasonable documentation to support the request
15for a change order for extra work has been submitted, the public
16entity shall have five days following the next scheduled meeting
17of the governing body to issue a change order for extra work
18performed.

begin delete

19(B) When a change order for extra work by a school district or
20community college district is subject to approval by the Division
21of the State Architect, the school district or community college
22district shall submit the change order to the division no later than
2330 days following receipt of reasonable documentation to support
24the change order for extra work. The Division of the State Architect
25shall respond to the request for the change order no later than 30
26days from receipt of the documentation.

end delete

27(3) Nothing in this section shall be construed to prohibit a public
28entity from issuing a change order in less than 60 days following
29 the completion of extra work, prior to the work being performed,
30or during the course of the work being performed.

31(4) An original contractor may present to the public entity a
32request for a change order for extra work performed by a
33subcontractor or a lower tier subcontractor. A subcontractor may
34request in writing that an original contractor present a change order
35request for extra work, directed by the public entity, that was
36performed by the subcontractor or by a lower tier subcontractor
37on behalf of the subcontractor. This subcontractor shall furnish
38reasonable documentationbegin delete to support the change order.end deletebegin insert setting
39forth the reasons and providing sufficient support to warrant that
40the change order be issued.end insert
Within 45 days of receipt of this
P4    1written request, the original contractor shall notify the
2subcontractor in writing as to whether the original contractor
3presented the request to the public entity and, if the original
4contractor did not present the request, provide the subcontractor
5with a statement of the reasons for not doing so.

6(b) Upon the failure of the public entity to issue a change
7orderbegin deletefor authorized workend deletebegin insert for extra work required by an authorized
8representative of the public entityend insert
within the time limits prescribed
9in subdivision (a), the original contractor may bill for thebegin deletecompletedend delete
10 extra workbegin delete in accordance with any provisions for change order
11work that may be contained in the public works contract.end delete
begin insert that has
12already been performed, and the public entity shall be liable for
13fair and equitable adjustments in the compensation or time for
14performance for the completed extra work.end insert

begin delete

15(c) If there is a dispute concerning the need for a change order
16for a portion of the extra work, the public entity shall promptly
17pay for the portion of the extra work that is not in dispute.

end delete
begin delete

12 18(d)

end delete

19begin insert(c)end insert When the dispute concerning the extra work relates only to
20the amount that the original contractor shall be paid, the public
21entity shall promptly pay thebegin insert reasonableend insert value of the work or the
22amount that the public entity does not dispute, whichever is greater.

begin delete

16 23(e)

end delete

24begin insert(d)end insert The public entity, and the original contractor, may reserve
25their respective rights as to any amount paid or unpaid that remains
26in dispute.

begin delete

19 27(f)

end delete

28begin insert(e)end insert Prejudgment interestbegin insert in accordance with applicable lawend insert
29 shall accrue on any amountbegin delete for which the public entity fails to
30issue a change order or fails to pay in accordance with this section
31at 7 percent per annum. This subdivision shall only apply to any
32amount that is not in dispute.end delete
begin insert this section requires to be paid that
33the public entity fails to pay.end insert

begin delete

34(g) In addition to any other remedies that may be available to
35it, an original contractor may enforce this section by way of
36mediation or other alternative dispute resolution process.

37(h) The public entity shall not require the original contractor to
38waive any provision of this section.

end delete
begin delete

38 39(i)

end delete

40begin insert(f)end insert For purposes of this section:

begin delete

P5    1(1) “Alternative dispute resolution process” means a process in
2which parties meet with a neutral third party to assist them in
3resolving their dispute outside of formal litigation.

4(2) “Duly authorized

end delete

5begin insert(1)end insertbegin insertend insertbegin insert“Authorizedend insert representative of the public entity” means an
6officer or employee of the public entity authorized to order extra
7work.

begin delete

7 8(3)

end delete

9begin insert(2)end insert “Extra work” includes extra work performed by the original
10contractor, a subcontractor, or a lower tier subcontractor. “Extra
11work” also includes work or requirements that differ from those
12under the public works contract with the public entity before the
13amendment of the contract by the change order.

begin delete

14(4) “Mediation” means a process in which a neutral person or
15persons facilitate communication between disputants to assist them
16in reaching a mutually acceptable agreement.

end delete
begin delete

15 17(5)

end delete

18begin insert(3)end insert “Public entity” means the state, including a state agency,
19department, office, division, bureau, board, or commission, the
20California State University, the University of California, a city,
21including a charter city, county, including a charter county, city
22and county, including a charter city and county, district, special
23district, public authority, political subdivision, public corporation,
24or nonprofit transit corporation wholly owned by a public agency
25and formed to carry out the purposes of the public agency.

begin delete

23 26(j)

end delete

27begin insert(g)end insert This section shall not prevent a public entity from prohibiting
28a contractor from performing extra work until after the public
29entity issues a change order.



O

    94