BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 2471
                                                                  Page  1

          Date of Hearing:   May 14, 2014

                        ASSEMBLY COMMITTEE ON APPROPRIATIONS
                                  Mike Gatto, Chair

                   AB 2471 (Frazier) - As Amended:  April 24, 2014 

          Policy Committee:                               
          AccountabilityVote:13-0

          Urgency:     No                   State Mandated Local Program:  
          No     Reimbursable:               

           SUMMARY  

          This bill requires prompt payment of change orders on public  
          works contracts. Specifically, this bill:

             1)   Requires any state or local public entity to issue  
               change orders on public works contracts promptly, or no  
               later than 60 days after the extra work is performed.

             2)   Authorizes a prime contractor to present to the public  
               entity a change order request for extra work performed by a  
               subcontractor.

             3)   Stipulates that, upon failure of a public entity to  
               promptly issue a change order per (1), the contractor may  
               bill for work already performed and the public entity shall  
               be liable for that work.

             4)   Stipulates that, if there is a dispute regarding the  
               need for the change order, the public entity must pay for  
               the portion of the work not in dispute.

             5)   Provides that prejudgment interest shall accrue at 10%  
               annually on any amount that a public entity fails to issue  
               a change order or fails to pay.

             6)   Authorizes a contractor to enforce the above through a  
               writ of mandate.

           FISCAL EFFECT  

          Costs to state and local agencies cannot be quantified, and  








                                                                  AB 2471
                                                                  Page  2

          would depend on the extent to which: (a) the bill deviates from  
          any agency's current contracting practices; (b) agencies are  
          able to meet the required timelines and how much interest costs  
          would accrue for noncompliance; and (c) agencies incur  
          additional administrative costs to comply with the bill's  
          requirements. The bill could also subject agencies to additional  
          litigation costs. Given the tens of billions of dollars in  
          annual public works contracting throughout California, these  
          costs would likely be at least in the tens of millions of  
          dollars.

           COMMENTS  

           1)Purpose  . According to United Contractors (sponsor),  
            contractors usually cannot bill for extra work until the  
            agency issues a change order. The sponsor explains that if the  
            agency does not prepare a change order, it can delay paying  
            for the extra work, which can result in months or even years  
            of payment delays. In such cases, the original contractor must  
            continue to pay employees and subcontractors for their work  
            while waiting for payment from public entities.

           2)Opposition  . Local governments contend this bill places an  
            unreasonable burden on local agencies with the 60-day  
            requirement, raises the financial risk associated with public  
            works contracts, and would lead to unnecessary and costly  
            litigation. The California State University raises similar  
            concerns.

            At the time of this analysis, the parties were attempting to  
            reach agreement on amendments. One apparent flaw in the bill  
            is tying the deadline for issuing a change order to the  
            performance of the work without placing any onus on the  
            contractor to timely submit their costs for the work along  
            with adequate supporting documentation.

           Analysis Prepared by  :    Chuck Nicol / APPR. / (916) 319-2081