BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  AB 2471
                                                                  Page  1


          ASSEMBLY THIRD READING
          AB 2471 (Frazier)
          As Amended  May 23, 2014
          Majority vote 

           ADMINISTRATIVE REVIEW       13-0APPROPRIATIONS      14-0        
           
           ----------------------------------------------------------------- 
          |Ayes:|Frazier, Achadjian,       |Ayes:|Gatto, Bocanegra,         |
          |     |Buchanan,                 |     |Bradford,                 |
          |     |Ian Calderon, Cooley,     |     |Ian Calderon, Campos,     |
          |     |Gorell, Hagman,           |     |Eggman, Gomez, Holden,    |
          |     |Lowenthal, Medina, Olsen, |     |Linder, Pan, Quirk,       |
          |     |Quirk-Silva, Salas,       |     |Ridley-Thomas, Wagner,    |
          |     |Wagner                    |     |Weber                     |
          |     |                          |     |                          |
           ----------------------------------------------------------------- 
           SUMMARY  :  Requires state and local public entities engaged in a  
          public works contract awarded to the lowest bidder to promptly  
          issue change orders when extra work is required of the  
          contractor or subcontractor.  Specifically,  this bill  :  

          1)Requires public entities, when additional work is needed, to  
            issue change orders promptly, and generally within 60 days  
            after the extra work is performed as long as the contractor  
            submitted reasonable documentation to support the request for  
            a change order.

          2)Allows the original contractor to present to the public entity  
            a request for a change order for extra work from a  
            subcontractor.

          3)Makes the public entity liable to the original contractor for  
            payment of the contractor's invoice for the change order if  
            the 60-day requirement is not met.

          4)Sets an exception to the 60-day requirement if a change order  
            is subject to approval by the governing body of a public  
            entity and that body is not scheduled to meet in the 60 days  
            after the performance of the extra work.

          5)Specifies the process for meeting the 60-day requirement for  
            school districts and community colleges when change orders are  
            subject to approval by the Division of the State Architect  








                                                                  AB 2471
                                                                  Page  2


            (State Architect). 

          6)Sets rules related to disputes between the public entity and  
            contractor.  

           EXISTING LAW  contains various provisions related to contracts by  
          a public entity for the performance of public works projects.

           FISCAL EFFECT  :  According to the Assembly Appropriations  
          Committee, costs to state and local agencies cannot be  
          quantified, and would depend on the extent to which:  a) the  
          bill deviates from any agency's current contracting practices;  
          b) agencies are able to meet the required timelines and how much  
          interest costs would accrue for noncompliance; and c) agencies  
          incur additional administrative costs to comply with this bill's  
          requirements.  In general, agencies should be able to meet the  
          60-day review period.  

           COMMENTS  :  This bill requires public entities to issue change  
          orders for public works projects promptly.  When a public entity  
          asks for extra work beyond the original agreement with a  
          contractor, it must prepare and both parties must sign an  
          amendment to the contract.  Such an amendment is called a  
          "change order."  This bill specifies that "extra work" could  
          include work by the original contractor or subcontractors.   

          According to United Contractors, the sponsor of this bill,  
          contractors usually cannot bill for extra work until the agency  
          issues a change order.  The sponsor explains that if the agency  
          does not prepare a change order, it can delay paying for the  
          extra work, which can result in months or even years of payment  
          delays.  In such cases, the original contractor must continue to  
          pay employees and subcontractors for their work while waiting  
          for payment from public entities.

          This bill requires public entities, when additional work is  
          needed, to issue change orders promptly, and generally not later  
          than 60 days after the extra work is performed as long as the  
          contractor submitted reasonable documentation to support the  
          request for a change order.  If the public entity fails to issue  
          a change order within this timeframe, the original contractor  
          may bill for this work that has already been performed, and the  
          public entity shall be liable for that work.  Prejudgment  
          interest, which is interest from the time the amount was due  








                                                                  AB 2471
                                                                  Page  3


          until the case was resolved, would accrue at the rate of 7% per  
          year if the public entity fails to promptly issue a change order  
          or pay in compliance with this bill.  Additionally, an original  
          contractor may enforce requirements of this bill through a writ  
          of mandate, which is a court order to a government entity.

          This bill sets an exception to the 60-day requirement. If a  
          change order is subject to approval by the governing body of a  
          public entity and that body is not scheduled to meet in the 60  
          days after the performance of the extra work, then the entity  
          would be required to issue a change order within three days of  
          the next scheduled meeting of the governing body. 

          Additionally, this bill specifies the process for meeting the  
          60-day requirement for school districts and community colleges  
          when change orders are subject to approval by the State  
          Architect.  These entities are required to submit change orders  
          to the State Architect within 30 days of receiving reasonable  
          documentation to support the change orders.  The State Architect  
          is required to respond to requests for change order no later  
          than 30 days after receiving them.    

          If a dispute arises regarding the need for a change order for  
          extra work occurs, this bill requires the public entity to pay a  
          reasonable amount for the portion of the extra work that is not  
          in dispute.  If the dispute only relates to the amount that the  
          original contractor shall be paid, the public entity would be  
          required to promptly pay the greater of the reasonable value of  
          the work or the amount that the public entity does not dispute.   
          Both the public entity and original contractor may reserve their  
          rights on paid or unpaid amounts in dispute.
           

          Analysis Prepared by  :    Scott Herbstman / A. & A.R. / (916)  
          319-3600 


                                                                FN: 0003823