BILL ANALYSIS                                                                                                                                                                                                    �






                                                       Bill No:  AB  
          2471
          
                 SENATE COMMITTEE ON GOVERNMENTAL ORGANIZATION
                           Senator Lou Correa, Chair
                           2013-2014 Regular Session
                                 Staff Analysis



          AB 2471  Author:  Frazier
          As Proposed to be Amended in Committee
          Hearing Date:  June 24, 2014
          Consultant:  Paul Donahue


                                     SUBJECT  

                     Public works contracts: change orders

                                   DESCRIPTION
           
          Requires a public entity, when authorized to order changes  
          or additions to the work in a public works contract to  
          issue a change order promptly. Specifically, this bill:

          1)Requires a public entity or its representative,<1> when  
            additional work is needed, to issue change orders for  
            authorized work promptly, and in no event later than 60  
            days after the extra work is complete and an agreement is  
            reached concerning the merit, conditions, cost and time  
            for performance. 

          2)Specifies that the original contractor shall respond  
            promptly to a request from the public entity  
            representative for documentation to support a request for  
            a change order. 

          3)Requires each public agency to specify in the public  
            works contract the information that the contractor will  
            be required to provide in support of any requested change  
            order. 
          -------------------------
          <1> A duly authorized representative of the public entity  
          is defined to mean, in the case of a local public agency,  
          an officer or employee of the agency authorized to order  
          extra work. 




          AB 2471 (Frazier) continued                               
          PageB



          4)Authorizes the original contractor to present to the  
            public entity a request for a change order for extra work  
            from a subcontractor.

          5)Authorizes the original contractor, upon failure of the  
            public entity to issue a change order for authorized work  
            within specified time limits, to bill for the completed  
            extra work in accordance with any provisions governing  
            change orders contained in the public works contract. 

          6)Sets an exception to the 60-day requirement if a change  
            order is subject to approval by the governing body of a  
            public entity and that body is not scheduled to meet in  
            the 60 days after the performance of the extra work.

          7)Specifies the process for meeting the 60-day requirement  
            for school districts and community colleges when change  
            orders are subject to approval by the Division of the  
            State Architect within the Department of General Services  
            (DGS). 

          8)Specifies that, in addition to other remedies that may be  
            available to the original contractor, the contractor may  
            enforce the change order rules by writ of mandate. 

                                   EXISTING LAW

           The Public Contract Code contains a body of law relating to  
          contracts let by a public entity for the performance of  
          public works of improvement, including provisions for the  
          payment of progress payments and the disbursing and  
          withholding of retention proceeds. 

          Until January 1, 2016, existing law prohibits progress  
          payments upon state contracts from being made in excess of  
          100% of the percentage of actual work completed, and  
          authorizes DGS to withhold not more than 5% of the contract  
          price until final completion and acceptance of the project,  
          except as specified.

                                    BACKGROUND
           
           Purpose of the bill  : According to the author's office,  
          California businesses depend on being paid on time for  
          their survival. Delay by state or local public agencies in  





          AB 2471 (Frazier) continued                               
          PageC


          paying for construction work creates financial burdens on  
          construction contractors and subcontractors, many of which  
          are small businesses. Agency delays in approving and paying  
          change orders are a serious problem, according to the  
          author, who is concerned that some public agencies put off  
          approving and paying change orders for months, and  
          sometimes more than a year. The sponsors fear that some  
          contracting agencies delay approving and paying for change  
          orders to gain leverage so that they can demand that  
          legitimate bills for extra work be discounted to below  
          actual cost. 

           Change orders  : A change order is an amendment to the  
          original public contract that agencies must approve when  
          the scope of work needs to be adjusted. A change order  
          obviously increases the cost of the project, so public  
          agencies must review whether the additional work is  
          necessary, and negotiate a fair and reasonable price. Until  
          the change order is approved, no additional work has been  
          authorized, and the contractor is bound by the scope of the  
          original contract. AB 2471 does not address a "prompt  
          payment"<2> issue, because until the change order has been  
          issued, the contractor is under no obligation to perform  
          the extra work. Prompt payment only applies to work within  
          the scope of a contract. Until a change order is issued,  
          the work is not within the scope of work.

           Summary of the amendments  : In response to public agency  
          criticisms, the author and the sponsor have agreed to adopt  
          certain amendments to AB 2471, as it appeared in print on  
          May 23, 2014. The proposed amendments appear in the  
          attached mockup. It is unclear whether all parties have  
          agreed to all of the proposed changes, but it appears that  
          many of the reasonable objections of the parties will be  
          addressed by these amendments. 

          First and foremost, the public entities insisted on having  
          a change order process that specifies that an agreement  
          shall be reached between the contractor and the agency  
          concerning the merit of the change order, the conditions  
          -------------------------
          <2> The Prompt Payment Act requires State agencies to pay  
          properly submitted, undisputed invoices within 45 calendar  
          days of initial receipt. If the requirement is not met,  
          State departments must automatically calculate and pay the  
          appropriate late payment penalties. (See Govt. Code � 927  
          et seq.)





          AB 2471 (Frazier) continued                               
          PageD


          under which it will be carried out, the costs associated  
          with the change order, and the time for performance of the  
          extra work. Conversely, proponents of the bill prefer a  
          change order protocol which triggers the public agency  
          change order processing obligations once the original  
          contractor has submitted a clear and complete description  
          of the extra work sufficient to allow identification of the  
          claimed cost elements. This issue is of particular  
          importance to both proponents and opponents of AB 2471.

          Some opponents object to the amount of pre-judgment  
          interest (7%) because it allegedly creates an incentive to  
          withhold documentation to process the change order so that  
          it can go into the dispute resolution phase. However, the  
          mockup provides for a process that would require the  
          contractor and the agency to reach an agreement on the  
          terms and conditions of a change order, which would seem to  
          alleviate the concern that change orders will end up in  
          arbitration, alternative dispute resolution or the courts. 

          Some of the opponents to AB 2471 raise a continuing  
          objection to a provision that allows an aggrieved original  
          contractor to take up a writ of mandate to enforce the  
          provisions of the bill. Nevertheless, in the interests of  
          balancing the equities in order to advance the bill, this  
          provision remains in AB 2471.

                            PRIOR/RELATED LEGISLATION
           
          AB 1705 (Williams), 2013-2014 Session. Limits the  
          circumstances under which public agencies may withhold more  
          than 5% of total payment amounts for time and materials on  
          substantially complex public works projects. (Senate Third  
          Reading)

          AB 748 (Eggman), Chapter 424, Statutes of 2013. Provides  
          that, unless another provision of law provides a different  
          interest rate, interest accrues in a tax or fee claim  
          against a public entity that results in a judgment against  
          the public entity at a rate equal to the weekly average one  
          year constant maturity United States Treasury yield, not to  
          exceed 7% per annum. 

           SUPPORT:   

          Air Conditioning & Refrigeration Contractors Association





          AB 2471 (Frazier) continued                               
          PageE


          Air Conditioning Sheet Metal Association
          Air Conditioning Trade Association
          American Subcontractors Association California 
          Associated Builders and Contractors - San Diego Chapter
          Associated General Contractors
          Building Industry Credit Association
          California Concrete Contractors Association
          California Legislative Conference, Plumbing, Heating and  
          Piping Industry
          California Professional Association of Specialty  
          Contractors
          California State Association of Electrical Workers
          California State Council of Laborers
          California State Pipe Trades Council
          Construction Employers Association
          National Electrical Contractors Association, California  
          chapters
          Plumbing-Heating Cooling Contractors Association of  
          California
          Southern California Contractors Association
          State Building and Construction Trades Council
          Union Roofing Contractors Association
          United Contractors
          Western Electrical Contractors Association
          Western States Council of Sheet Metal Workers

           OPPOSE:   

          Association of California Cities - Orange County
          Association of California Healthcare Districts 
          Association of California School Administrators 
          California Airports Council
          California Association of Sanitation Agencies 
          California Association of School Business Officials
          California School Boards Association 
          California Special Districts Association
          California State Association of Counties 
          City of Concord
          Coalition for Adequate School Housing
          County of San Bernardino
          County School Facilities Consortium 
          East Valley Water District
          El Dorado Irrigation District
          Kern County Superintendent of Schools
          La Puente County Water District
          League of California Cities 





          AB 2471 (Frazier) continued                               
          PageF


          Newhall County water District
          Orange County Transportation Authority
          Pico Water District
          Rowland Water District
          Sonoma County Water Agency
          Urban Counties Caucus 

           FISCAL COMMITTEE:   Senate Appropriations Committee



                                   **********