SB 674,
as amended, Corbett. begin deleteEnergy: renewable energy. end deletebegin insertCalifornia Environmental Quality Act: exemption: residential infill projects.end insert
(1) The California Environmental Quality Act, commonly referred to as CEQA, requires a lead agency, as defined, to prepare, or cause to be prepared, and certify the completion of, an environmental impact report on a project that it proposes to carry out or approve that may have a significant effect on the environment or to adopt a negative declaration if it finds that the project will not have that effect. CEQA also requires a lead agency to prepare a mitigated negative declaration for a project that may have a significant effect on the environment if revisions in the project would avoid or mitigate that effect and there is no substantial evidence that the project, as revised, would have a significant effect on the environment.
end insertbegin insertCEQA exempts from these requirements residential infill projects meeting specified criteria, including, among other things, that a community-level environmental review was adopted or certified within 5 years of the date that the application for the project is deemed complete and the project promotes higher density infill housing. For the purposes of this exemption, CEQA defines “residential” to include a use consisting of residential units and primarily neighborhood-serving goods, services, or retail uses that do not exceed 15% of the total floor area of the project.
end insertbegin insertThis bill would instead exempt as “residential” a use consisting of residential units and primarily neighborhood-serving goods, services, or retail uses that do not exceed 25% of the total building square footage of the project.
end insertbegin insert(2) Because this bill would require a lead agency to determine whether a project meets the above criteria to qualify for an exemption from CEQA, the bill would impose a state-mandated local program.
end insertbegin insert(3) The California Constitution requires the state to reimburse local agencies and school districts for certain costs mandated by the state. Statutory provisions establish procedures for making that reimbursement.
end insertbegin insertThis bill would provide that no reimbursement is required by this act for a specified reason.
end insertUnder existing law, the Public Utilities Commission has regulatory authority over public utilities. Existing law requires every electrical corporation to file with the commission a standard tariff for electricity generated by an electric generation facility, as defined, that qualifies for the tariff, is owned and operated by a retail customer of the electrical corporation, and is located within the service territory of, and developed to sell electricity to, the electrical corporation. Existing law requires an electrical corporation to make the tariff available to the owner or operator of an electric generation facility within the service territory of the electrical corporation, as specified, until the electrical corporation meets its proportionate share of a statewide cap of 750 megawatts, as specified.
end deleteThis bill would require the commission to adjust the payment rate for electricity purchased from electrical generation facility projects that integrate energy storage to adequately compensate for the additional value that energy storage system provides.
end deleteVote: majority.
Appropriation: no.
Fiscal committee: yes.
State-mandated local program: begin deleteno end deletebegin insertyesend insert.
The people of the State of California do enact as follows:
begin insertSection 21159.24 of the end insertbegin insertPublic Resources Codeend insert
2begin insert is amended to read:end insert
(a) Except as provided in subdivision (b), this
2division does not apply to a project if all of the following criteria
3are met:
4(1) The project is a residential project on an infill site.
5(2) The project is located within an urbanized area.
6(3) The project satisfies the criteria of Section 21159.21.
7(4) Within five years of the date that the application for the
8project is deemed complete pursuant to Section 65943 of the
9Government Code, community-level environmental review was
10certified or adopted.
11(5) The site of the project is not more than four acres in total
12area.
13(6) The project does not contain more than 100 residential units.
14(7) Either of the following criteria are met:
15(A) (i) At least 10 percent of the housing is sold to families of
16moderate income, or not less than 10 percent of the housing is
17rented to families of low income, or not less than 5 percent of the
18housing is rented to families of very low income.
19(ii) The project developer provides sufficient legal commitments
20to the appropriate local agency to ensure the continued availability
21and use of the housing units for very low, low-, and
22moderate-income households at monthly housing costs determined
23
pursuant to paragraph (3) of subdivision (h) of Section 65589.5 of
24the Government Code.
25(B) The project developer has paid or will pay in-lieu fees
26pursuant to a local ordinance in an amount sufficient to result in
27the development of an equivalent number of units that would
28otherwise be required pursuant to subparagraph (A).
29(8) The project is within one-half mile of a major transit stop.
30(9) The project does not include any single level building that
31exceeds 100,000 square feet.
32(10) The project promotes higher density infill housing. A
33project with a density of at least 20 units per acre shall be
34conclusively presumed to promote higher density infill housing.
35A project with a density of at least 10 units per acre and a density
36greater than the average
density of the residential properties within
371,500 feet shall be presumed to promote higher density housing
38unless the preponderance of the evidence demonstrates otherwise.
P4 1(b) Notwithstanding subdivision (a), this division shall apply
2to a development project that meets the criteria described in
3subdivision (a), if any of the following occur:
4(1) There is a reasonable possibility that the project will have
5a project-specific, significant effect on the environment due to
6unusual circumstances.
7(2) Substantial changes with respect to the circumstances under
8which the project is being undertaken that are related to the project
9have occurred since community-level environmental review was
10certified or adopted.
11(3) New information becomes available regarding
the
12circumstances under which the project is being undertaken and
13that is related to the project, that was not known, and could not
14have been known, at the time that community-level environmental
15review was certified or adopted.
16(c) If a project satisfies the criteria described in subdivision (a),
17but is not exempt from this division as a result of satisfying the
18criteria described in subdivision (b), the analysis of the
19environmental effects of the project in the environmental impact
20report or the negative declaration shall be limited to an analysis
21of the project-specific effect of the projects and any effects
22identified pursuant to paragraph (2) or (3) of subdivision (b).
23(d) For the purposes of this section, “residential” means a use
24consisting of either of the following:
25(1) Residential units only.
26(2) Residential units and primarily neighborhood-serving goods,
27services, or retail uses that do not exceedbegin delete 15end deletebegin insert 25end insert percent of the total
28begin delete floor areaend deletebegin insert building square footageend insert of the project.
No reimbursement is required by this act pursuant to
30Section 6 of Article XIII B of the California Constitution because
31a local agency or school district has the authority to levy service
32charges, fees, or assessments sufficient to pay for the program or
33level of service mandated by this act, within the meaning of Section
3417556 of the Government Code.
Section 399.20 of the Public Utilities Code is
36amended to read:
(a) It is the policy of this state and the intent of the
38Legislature to encourage electrical generation from eligible
39renewable energy resources.
P5 1(b) As used in this section, “electric generation facility” means
2an electric generation facility located within the service territory
3of, and developed to sell electricity to, an electrical corporation
4that meets all of the following criteria:
5(1) Has an effective capacity of not more than three megawatts.
6(2) Is interconnected and operates in parallel with the electrical
7transmission and distribution grid.
8(3) Is strategically
located and interconnected to the electrical
9transmission and distribution grid in a manner that optimizes the
10deliverability of electricity generated at the facility to load centers.
11(4) Is an eligible renewable energy resource.
12(c) Every electrical corporation shall file with the commission
13a standard tariff for electricity purchased from an electric
14generation facility. The commission may modify or adjust the
15requirements of this section for any electrical corporation with less
16than 100,000 service connections, as individual circumstances
17merit.
18(d) (1) The tariff shall provide for payment for every
19kilowatthour of electricity purchased from an electric generation
20facility for a period of 10, 15, or 20 years, as authorized by the
21commission. The payment shall be the market price determined
22by
the commission pursuant to paragraph (2) and shall include all
23current and anticipated environmental compliance costs, including,
24but not limited to, mitigation of emissions of greenhouse gases
25and air pollution offsets associated with the operation of new
26generating facilities in the local air pollution control or air quality
27management district where the electric generation facility is
28located.
29(2) The commission shall establish a methodology to determine
30the market price of electricity for terms corresponding to the length
31of contracts with an electric generation facility, in consideration
32of the following:
33(A) The long-term market price of electricity for fixed price
34contracts, determined pursuant to an electrical corporation’s general
35procurement activities as authorized by the commission.
36(B) The long-term
ownership, operating, and fixed-price fuel
37costs associated with fixed-price electricity from new generating
38facilities.
39(C) The value of different electricity products including
40baseload, peaking, and as-available electricity.
P6 1(3) The commission may adjust the payment rate to reflect the
2value of every kilowatthour of electricity generated on a
3time-of-delivery basis.
4(4) The commission shall ensure, with respect to rates and
5charges, that ratepayers that do not receive service pursuant to the
6tariff are indifferent to whether a ratepayer with an electric
7generation facility receives service pursuant to the tariff.
8(5) The commission shall adjust the payment rate for
electricity
9purchased from electrical generation facility projects that integrate
10energy storage to adequately compensate for the additional value
11that energy storage system provides. The adjustment shall reflect
12all the benefits that the energy storage system provides to the
13electrical corporation and the grid.
14(e) An electrical corporation shall provide expedited
15interconnection procedures to an electric generation facility located
16on a distribution circuit that generates electricity at a time and in
17a manner so as to offset the peak demand on the distribution circuit,
18if the electrical corporation determines that the electric generation
19facility will not adversely affect the distribution grid. The
20commission shall consider and may establish a value for an electric
21generation facility located on a distribution circuit that generates
22electricity at a time and in a manner so as to offset the peak demand
23on the
distribution circuit.
24(f) (1) An electrical corporation shall make the tariff available
25to the owner or operator of an electric generation facility within
26the service territory of the electrical corporation, upon request, on
27a first-come-first-served basis, until the electrical corporation meets
28its proportionate share of a statewide cap of 750 megawatts
29cumulative rated generation capacity served under this section and
30Section 387.6. The proportionate share shall be calculated based
31on the ratio of the electrical corporation’s peak demand compared
32to the total statewide peak demand.
33(2) By June 1, 2013, the commission shall, in addition to the
34750 megawatts identified in paragraph (1), direct the electrical
35corporations to collectively procure at least 250 megawatts of
36cumulative rated generating capacity from developers of bioenergy
37projects that commence
operation on or after June 1, 2013. The
38commission shall, for each electrical corporation, allocate shares
39of the additional 250 megawatts based on the ratio of each electrical
40corporation’s peak demand compared to the total statewide peak
P7 1demand. In implementing this paragraph, the commission shall do
2all of the following:
3(A) Allocate the 250 megawatts identified in this paragraph
4among the electrical corporations based on the following
5categories:
6(i) For biogas from wastewater treatment, municipal organic
7waste diversion, food processing, and codigestion, 110 megawatts.
8(ii) For dairy and other agricultural bioenergy, 90 megawatts.
9(iii) For bioenergy using byproducts of sustainable forest
10management, 50 megawatts. Allocations under this category
shall
11be determined based on the proportion of bioenergy that sustainable
12forest management providers derive from sustainable forest
13management in fire threat treatment areas, as designated by the
14Department of Forestry and Fire Protection.
15(B) Direct the electrical corporations to develop standard
16contract terms and conditions that reflect the operational
17characteristics of the projects, and to provide a streamlined
18contracting process.
19(C) Coordinate, to the maximum extent feasible, any incentive
20or subsidy programs for bioenergy with the agencies listed in
21subparagraph (A) of paragraph (3) in order to provide maximum
22benefits to ratepayers and to ensure that incentives are used to
23reduce contract prices.
24(D) The commission shall encourage gas and electrical
25corporations to develop and offer programs and services
to facilitate
26development of in-state biogas for a broad range of purposes.
27(3) (A) The commission, in consultation with the State Energy
28Resources Conservation and Development Commission, the State
29Air Resources Board, the Department of Forestry and Fire
30Protection, the Department of Food and Agriculture, and the
31Department of Resources Recycling and Recovery, may review
32the allocations of the 250 additional megawatts identified in
33paragraph (2) to determine if those allocations are appropriate.
34(B) If the commission finds that the allocations of the 250
35additional megawatts identified in paragraph (2) are not
36appropriate, the commission may reallocate the 250 megawatts
37among the categories established in subparagraph (A) of paragraph
38(2).
39(4) For the purposes of this subdivision, “bioenergy”
means
40biogas and biomass.
P8 1(g) The electrical corporation may make the terms of the tariff
2available to owners and operators of an electric generation facility
3in the form of a standard contract subject to commission approval.
4(h) Every kilowatthour of electricity purchased from an electric
5generation facility shall count toward meeting the electrical
6corporation’s renewables portfolio standard annual procurement
7targets for purposes of paragraph (1) of subdivision (b) of Section
8399.15.
9(i) The physical generating capacity of an electric generation
10facility shall count toward the electrical corporation’s resource
11adequacy requirement for purposes of Section 380.
12(j) (1) The commission shall establish performance standards
13for any
electric generation facility that has a capacity greater than
14one megawatt to ensure that those facilities are constructed,
15operated, and maintained to generate the expected annual net
16production of electricity and do not impact system reliability.
17(2) The commission may reduce the three megawatt capacity
18limitation of paragraph (1) of subdivision (b) if the commission
19finds that a reduced capacity limitation is necessary to maintain
20system reliability within that electrical corporation’s service
21territory.
22(k) (1) Any owner or operator of an electric generation facility
23that received ratepayer-funded incentives in accordance with
24Section 379.6 of this code, or with Section 25782 of the Public
25Resources Code, and participated in a net metering program
26pursuant to Sections 2827, 2827.9, and 2827.10 of this code prior
27to January 1, 2010, shall be eligible for a
tariff or standard contract
28filed by an electrical corporation pursuant to this section.
29(2) In establishing the tariffs or standard contracts pursuant to
30this section, the commission shall consider ratepayer-funded
31incentive payments previously received by the generation facility
32pursuant to Section 379.6 of this code or Section 25782 of the
33Public Resources Code. The commission shall require
34reimbursement of any funds received from these incentive
35programs to an electric generation facility, in order for that facility
36to be eligible for a tariff or standard contract filed by an electrical
37corporation pursuant to this section, unless the commission
38determines ratepayers have received sufficient value from the
39incentives provided to the facility based on how long the project
P9 1has been in operation and the amount of renewable electricity
2previously generated by the facility.
3(3) A
customer that receives service under a tariff or contract
4approved by the commission pursuant to this section is not eligible
5to participate in any net metering program.
6(l) An owner or operator of an electric generation facility
7electing to receive service under a tariff or contract approved by
8the commission shall continue to receive service under the tariff
9or contract until either of the following occurs:
10(1) The owner or operator of an electric generation facility no
11longer meets the eligibility requirements for receiving service
12pursuant to the tariff or contract.
13(2) The period of service established by the commission pursuant
14to subdivision (d) is completed.
15(m) Within 10 days of receipt of a request for a tariff pursuant
16to this section from an
owner or operator of an electric generation
17facility, the electrical corporation that receives the request shall
18post a copy of the request on its Internet Web site. The information
19posted on the Internet Web site shall include the name of the city
20in which the facility is located, but information that is proprietary
21and confidential, including, but not limited to, address information
22beyond the name of the city in which the facility is located, shall
23be redacted.
24(n) An electrical corporation may deny a tariff request pursuant
25to this section if the electrical corporation makes any of the
26following findings:
27(1) The electric generation facility does not meet the
28requirements of this section.
29(2) The transmission or distribution grid that would serve as the
30point of interconnection is inadequate.
31(3) The electric generation facility does not meet all applicable
32state and local laws and building standards and utility
33interconnection requirements.
34(4) The aggregate of all electric generating facilities on a
35distribution circuit would adversely impact utility operation and
36load restoration efforts of the distribution system.
37(o) Upon receiving a notice of denial from an electrical
38corporation, the owner or operator of the electric generation facility
39denied a tariff pursuant to this section shall have the right to appeal
40that decision to the commission.
P10 1(p) In order to ensure the safety and reliability of electric
2generation facilities, the owner of an electric generation facility
3receiving a tariff pursuant to this section shall provide an inspection
4
and maintenance report to the electrical corporation at least once
5every other year. The inspection and maintenance report shall be
6prepared at the owner’s or operator’s expense by a
7California-licensed contractor who is not the owner or operator of
8the electric generation facility. A California-licensed electrician
9shall perform the inspection of the electrical portion of the
10generation facility.
11(q) The contract between the electric generation facility
12receiving the tariff and the electrical corporation shall contain
13provisions that ensure that construction of the electric generating
14facility complies with all applicable state and local laws and
15building standards, and utility interconnection requirements.
16(r) (1) All construction and installation of facilities of the
17electrical corporation, including at the point of the output meter
18or at the transmission
or distribution grid, shall be performed only
19by that electrical corporation.
20(2) All interconnection facilities installed on the electrical
21corporation’s side of the transfer point for electricity between the
22electrical corporation and the electrical conductors of the electric
23generation facility shall be owned, operated, and maintained only
24by the electrical corporation. The ownership, installation, operation,
25reading, and testing of revenue metering equipment for electric
26generating facilities shall only be performed by the electrical
27corporation.
O
98