SB 1195, as introduced, Padilla. Electrical restructuring.
The existing restructuring of the electrical industry within the Public Utilities Act provides for the establishment of an Independent System Operator and a Power Exchange as nonprofit public benefit corporations. Existing law requires the Independent System Operator, within 6 months after receiving approval for its operation by the Federal Energy Regulatory Commission, to provide a report to the Legislature and the Electricity Oversight Board containing specified matter.
This bill would repeal this reporting requirement.
Electrical restructuring states the intent of the Legislature that individual customers not experience rate increases as a result of the allocation of transition costs, as specified, and requires the Public Utilities Commission to implement a methodology for calculating certain Power Exchange energy credits.
This bill would repeal this provision.
Electrical restructuring requires each electrical corporation to propose a cost recovery plan to the commission for the recovery of the uneconomic costs of an electrical corporation’s generation-related assets and obligations, requires that the plan contain specified matter, and requires that the plan set rates for each customer class, rate schedule, contract, or tariff option, at levels equal to the level as shown on electric rate schedules as of June 10, 1996, provided that rates for residential and small commercial customers be reduced so that these customers receive rate reductions of no less than 10% for 1998 continuing through 2002. Electrical restructuring prohibits the commission, upon the termination of the 10% rate reduction for residential and small commercial customers, from subjecting those residential and small commercial customers to any rate increase or future rate obligations solely as a result of the termination of the 10% rate reduction.
This bill would repeal these provisions.
Electrical restructuring requires any electrical corporation serving agricultural customers with multiple meters to conduct research based on a statistically valid sample of those customers and meters to determine the typical simultaneous peak load of those customers and to report the results to those customers and the commission by July 1, 2001. Electrical restructuring requires the commission to consider the research results in setting future electrical distribution rates for those customers.
This bill would repeal this provision.
Electrical restructuring requires the commission to allow recovery of reasonable employee related transition costs incurred and projected for severence, retraining, early retirement, outplacement, and related expenses for the employees in order to mitigate potential negative impacts on utility personnel directly affected by restructuring.
This bill would repeal this provision.
This bill would strike references to these repealed statutes.
Vote: majority. Appropriation: no. Fiscal committee: no. State-mandated local program: no.
The people of the State of California do enact as follows:
Section 332.1 of the Public Utilities Code is
2amended to read:
(a) (1) It is the intent of the Legislature to enact Item
41 (revised) on the commission’s August 21, 2000begin insert,end insert agenda, entitled
5“Opinion Modifying Decision (D.) D.00-06-034 and D.00-08-021
6to Regarding Interim Rate Caps for San Diego Gas and Electric
7Company,” as modified below.
8(2) It is also the intent of the Legislature that to the extent that
9the Federal Energy Regulatory Commission orders refunds to
P3 1electrical corporations pursuant to their findings, the commission
2shall ensure that any refunds are returned to customers.
3(b) The
commission shall establish a ceiling of six and
4five-tenths cents ($0.065) per kilowatthour on the energy
5component of electric bills for electricity supplied to residential,
6small commercial, and street lighting customers by the San Diego
7Gas and Electric Company, through December 31, 2002, retroactive
8to June 1, 2000. If the commission finds it in the public interest,
9this ceiling may be extended through December 2003 and may be
10adjusted as provided in subdivision (d).
11(c) The commission shall establish an accounting procedure to
12track and recover reasonable and prudent costs of providing electric
13energy to retail customers unrecovered through retail bills due to
14the application of the ceiling provided for in subdivision (b). The
15accounting procedure shall utilize revenues associated with sales
16of energy from utility-owned or managed generation assets to
17offset an undercollection, if undercollection occurs. The accounting
18procedure shall be
reviewed periodically by the commission, but
19not less frequently than semiannually. The commission may utilize
20an existing proceeding to perform the review. The accounting
21procedure and review shall provide a reasonable opportunity for
22San Diego Gas and Electric Company to recover its reasonable
23and prudent costs of service over a reasonable period of time.
24(d) If the commission determines that it is in the public interest
25to do so, the commission, after the date of the completion of the
26proceeding described in subdivision (g), may adjust the ceiling
27from the level specified in subdivision (b), and may adjust the
28frozen rate from the levels specified in subdivision (f), consistent
29with the Legislature’s intent to provide substantial protections for
30customers of the San Diego Gas and Electric Company and their
31interest in just and reasonable rates and adequate service.
32(e) For
purposes of this section, “small commercial customer”
33includes, but is not limited to, all San Diego Gas and Electric
34Company accounts on Rate Schedule A of the San Diego Gas and
35Electric Company, all accounts of customers who are “general
36acute care hospitals,” as defined in Section 1250 of the Health and
37Safety Code, all San Diego Gas and Electric Company accounts
38of customers who are public or private schools for pupils in
39kindergarten or any of grades 1 to 12, inclusive, and all accounts
40on Rate Schedule AL-TOU under 100 kilowatts.
P4 1(f) The commission shall establish an initial frozen rate of six
2and five-tenths cents ($0.065) per kilowatthour on the energy
3component of electric bills for electricity supplied to all customers
4by the San Diego Gas and Electric Company not subject to
5subdivision (b), for the time period ending with the end of the rate
6freeze for the Pacific Gas and Electric Company and the Southern
7California Edison Companybegin delete pursuant to Section 368end delete,
retroactive
8to February 7, 2001. The commission shall consider the comparable
9energy components of rates for comparable customer classes served
10by the Pacific Gas and Electric Company and the Southern
11California Edison Company and, if it determines it to be in the
12public interest, the commission may adjust this frozen rate, and
13may do so, retroactive to the date that rate increases took effect
14for customers of Pacific Gas and Electric Company and Southern
15California Edison Company pursuant to the commission’s March
1627, 2001, decision. The commission shall determine the Fixed
17Department of Water Resources Set-Aside pursuant to Section
18360.5 for customers subject to this section, reflecting a retail rate
19consistent with the rate for the energy component of electric bills
20as determined in this subdivision, in place of the retail rate in effect
21on January 5, 2001. This section shall be construed to modify the
22payment provisions, but may not be construed to modify the
23electric procurement obligations of the
Department of Water
24Resources, pursuant to any contract or agreement in accordance
25with Division 27 (commencing with Section 80000) of the Water
26Code, and in effect as of February 7, 2001, between the Department
27of Water Resources and San Diego Gas and Electric Company.
28(g) The commission shall institute a proceeding to examine the
29prudence and reasonableness of the San Diego Gas and Electric
30Company in the procurement of wholesale energy on behalf of its
31customers, for a period beginning, at the latest, on June 1, 2000.
32If the commission finds that San Diego Gas and Electric Company
33acted imprudently or unreasonably, the commission shall issue
34orders that it determines to be appropriate affecting the retail rates
35of San Diego Gas and Electric Company customers including, but
36not limited to, refunds.
37(h) Nothing in this section may be construed to limit the
38authority of the
Department of Water Resources pursuant to
39Division 27 (commencing with Section 80000) of the Water Code.
Section 350 of the Public Utilities Code is repealed.
The Independent System Operator, in consultation with
2the California Energy Resources Conservation and Development
3Commission, the Public Utilities Commission, the Western
4Electricity Coordinating Council, and concerned regulatory
5agencies in other western states, shall within six months after the
6Federal Energy Regulatory Commission approval of the
7Independent System Operator, provide a report to the Legislature
8and to the Oversight Board that does the following:
9(a) Conducts an independent review and assessment of Western
10Electricity Coordinating Council operating reliability criteria.
11(b) Quantifies the economic cost of major transmission outages
12relating to the Pacific Intertie, Southwest Power Link, DC link,
13and other important high voltage lines that carry power both into
14and from California.
15(c) Identifies the range of cost-effective options that would
16prevent or mitigate the consequences of major transmission
17outages.
18(d) Identifies communication protocols that may be needed to
19be established to provide advance warning of incipient problems.
20(e) Identifies the need for additional generation reserves and
21other voltage support equipment, if any, or other resources that
22may be necessary to carry out its functions.
23(f) Identifies transmission capacity additions that may be
24necessary at certain times of the year or under certain conditions.
25(g) Assesses the adequacy of current and prospective
26institutional provisions for the maintenance of reliability.
27(h) Identifies mechanisms to enforce transmission right-of-way
28maintenance.
29(i) Contains recommendations regarding cost-beneficial
30improvements to electric system reliability for the citizens of
31California.
Section 367 of the Public Utilities Code is amended
33to read:
The commission shall identify and determine those costs
35and categories of costs for generation-related assets and obligations,
36consisting of generation facilities, generation-related regulatory
37assets, nuclear settlements, and power purchase contracts,
38including, but not limited to, restructurings, renegotiations or
39terminations thereof approved by the commission, that were being
40collected in commission-approved rates on December 20, 1995,
P6 1and that may become uneconomic as a result of a competitive
2generation market, in that these costs may not be recoverable in
3market prices in a competitive market, and appropriate costs
4incurred after December 20, 1995, for capital additions to
5generating facilities existing as of December 20, 1995, that the
6commission determines are reasonable and should be recovered,
7provided
that these additions are necessary to maintain the facilities
8through December 31, 2001. These uneconomic costs shall include
9transition costs as defined in subdivision (f) of Section 840, and
10shall be recovered from all customers or in the case of fixed
11transition amounts, from the customers specified in subdivision
12(a) of Section 841, on a nonbypassable basis and shall:
13(a) Be amortized over a reasonable time period, including
14collection on an accelerated basis, consistent with not increasing
15rates for any rate schedule, contract, or tariff option above the
16levels in effect on June 10, 1996; provided that, the recovery shall
17not extend beyond December 31, 2001, except as follows:
18(1) Costs associated with employee-related transition costsbegin delete as shall
continue until fully
19set forth in subdivision (b) of Section 375end delete
20collected; provided, however, that the cost collection shall not
21extend beyond December 31, 2006.
22(2) Power purchase contract obligations shall continue for the
23duration of the contract. Costs associated with any buy-out,
24buy-down, or renegotiation of the contracts shall continue to be
25collected for the duration of any agreement governing the buy-out,
26buy-down, or renegotiated contract; provided, however, no power
27purchase contract shall be extended as a result of the buy-out,
28buy-down, or renegotiation.
29(3) Costs associated with contracts approved by the commission
30to settle issues associated with the Biennial Resource Plan Update
31may be collected through March 31, 2002; provided that only 80
32percent of the balance of the costs remaining after December 31,
332001, shall be eligible for recovery.
34(4) Nuclear incremental cost incentive plans for the San Onofre
35nuclear generating station shall continue for the full term as
36authorized by the commission in Decision 96-01-011 and Decision
3796-04-059; provided that the recovery shall not extend beyond
38December 31, 2003.
39(5) Costs associated with the exemptions provided in subdivision
40(a) of Section 374 may be collected through March 31, 2002,
P7 1provided that only fifty million dollars ($50,000,000) of the balance
2of the costs remaining after December 31, 2001, shall be eligible
3for recovery.
4(6) Fixed transition amounts, as defined in subdivision (d) of
5Section 840, may be recovered from the customers specified in
6subdivision (a) of Section 841 until all rate reduction bonds
7associated with the fixed transition amounts have been paid in full
8by the financing entity.
9(b) Be based on a calculation mechanism that nets the negative
10value of all above market utility-owned generation-related assets
11against the positive value of all below market utility-owned
12generation related assets. For those assets subject to valuation, the
13valuations used for the calculation of the uneconomic portion of
14the net book value shall be determined not later than December
1531, 2001, and shall be based on appraisal, sale, or other divestiture.
16The commission’s determination of the costs eligible for recovery
17and of the valuation of those assets at the time the assets are
18exposed to market risk or retired, in a proceeding under Section
19455.5, 851, or otherwise, shall be final, and notwithstanding Section
201708 or any other provision of law, may not be rescinded, altered
21or amended.
22(c) Be limited in the case of utility-owned fossil generation to
23the uneconomic portion of the net book value of the fossil capital
24investment
existing as of January 1, 1998, and appropriate costs
25incurred after December 20, 1995, for capital additions to
26generating facilities existing as of December 20, 1995, that the
27commission determines are reasonable and should be recovered,
28provided that the additions are necessary to maintain the facilities
29through December 31, 2001. All “going forward costs” of fossil
30plant operation, including operation and maintenance,
31administrative and general, fuel and fuel transportation costs, shall
32be recovered solely from independent Power Exchange revenues
33or from contracts with the Independent System Operator, provided
34that for the purposes of this chapter, the following costs may be
35recoverable pursuant to this section:
36(1) Commission-approved operating costs for particular
37utility-owned fossil powerplants or units, at particular times when
38reactive power/voltage support is not yet procurable at
39market-based rates in locations where it is deemed
needed for the
40reactive power/voltage support by the Independent System
P8 1Operator, provided that the units are otherwise authorized to
2recover market-based rates and provided further that for an
3electrical corporation that is also a gas corporation and that serves
4at least four million customers as of December 20, 1995, the
5commission shall allow the electrical corporation to retain any
6earnings from operations of the reactive power/voltage support
7plants or units and shall not require the utility to apply any portions
8to offset recovery of transition costs. Cost recovery under the cost
9recovery mechanism shall end on December 31, 2001.
10(2) An electrical corporation that, as of December 20, 1995,
11served at least four million customers, and that was also a gas
12corporation that served less than four thousand customers, may
13recover, pursuant to this section, 100 percent of the uneconomic
14portion of the fixed costs paid under fuel and fuel
transportation
15contracts that were executed prior to December 20, 1995, and were
16subsequently determined to be reasonable by the commission, or
17100 percent of the buy-down or buy-out costs associated with the
18contracts to the extent the costs are determined to be reasonable
19by the commission.
20(d) Be adjusted throughout the period through March 31, 2002,
21to track accrual and recovery of costs provided for in this
22subdivision. Recovery of costs prior to December 31, 2001, shall
23include a return as provided for in Decision 95-12-063, as modified
24by Decision 96-01-009, together with associated taxes.
25(e) (1) Be allocated among the various classes of customers,
26rate schedules, and tariff options to ensure that costs are recovered
27from these classes, rate schedules, contract rates, and tariff options,
28including self-generation deferral, interruptible, and standby
rate
29options in substantially the same proportion as similar costs are
30recovered as of June 10, 1996, through the regulated retail rates
31of the relevant electric utility, provided that there shall be a firewall
32segregating the recovery of the costs of competition transition
33charge exemptions such that the costs of competition transition
34charge exemptions granted to members of the combined class of
35residential and small commercial customers shall be recovered
36only from these customers, and the costs of competition transition
37charge exemptions granted to members of the combined class of
38customers, other than residential and small commercial customers,
39shall be recovered only from these customers.
P9 1(2) Individual customers shall not experience rate increases as
2a result of the allocation of transition costs. However, customers
3who elect to purchase energy from suppliers other than the Power
4Exchange through a direct transaction, may incur increases
in the
5total price they pay for electricity to the extent the price for the
6energy exceeds the Power Exchange price.
7(3) The commission shall retain existing cost allocation
8authority, provided the firewall and rate freeze principles are not
9violated.
Section 367.7 of the Public Utilities Code is repealed.
(a) It is the intent of the Legislature in enacting this
12section to ensure that individual customers do not experience rate
13increases as a result of the allocation of transition costs, in
14accordance with paragraph (2) of subdivision (e) of Section 367.
15(b) The commission shall implement a methodology whereby
16the Power Exchange energy credit for a customer with a meter
17installed on or after June 30, 2000, that is capable of recording
18hourly data is calculated based on the actual hourly data for that
19customer. The Power Exchange energy credit for a customer with
20a meter installed before June 30, 2000, that is capable of recording
21hourly data shall, at the election of the customer, on a one-time
22basis before June 30, 2000, be calculated based on either (1) the
23actual hourly data for that customer or (2) the average load profile
24for that customer class. If the customer fails to make an election,
25that customer’s Power Exchange energy credit shall continue to
26be based on the average load profile for that customer class.
27(c) Additional incremental billing costs incurred as a result of
28the methodology implemented by the commission pursuant to
29subdivision (b) may be recoverable through rates for that customer
30class, if the commission finds that the costs are reasonable.
31(d) The methodology implemented by the commission pursuant
32to subdivisions (b) and (c) shall not result in any shifts in cost
33between customer classes and shall be consistent with the firewall
34provision set forth in subdivision (e) of Section 367.
Section 368 of the Public Utilities Code is repealed.
Each electrical corporation shall propose a cost recovery
37plan to the commission for the recovery of the uneconomic costs
38of an electrical corporation’s generation-related assets and
39obligations identified in Section 367. The commission shall
P10 1authorize the electrical corporation to recover the costs pursuant
2to the plan if the plan meets the following criteria:
3(a) The cost recovery plan shall set rates for each customer class,
4rate schedule, contract, or tariff option, at levels equal to the level
5as shown on electric rate schedules as of June 10, 1996, provided
6that rates for residential and small commercial customers shall be
7reduced so that these customers shall receive rate reductions of no
8less than 10 percent for 1998 continuing through 2002. These rate
9levels for each customer class, rate schedule, contract, or tariff
10option shall remain in effect until the earlier of March 31, 2002,
11or the date on which the commission-authorized costs for utility
12generation-related assets and obligations have been fully recovered.
13The electrical corporation shall be at risk for those costs not
14recovered during that time period. Each utility shall amortize its
15total uneconomic costs, to the extent possible, such that for each
16year during the transition period its recorded rate of return on the
17remaining uneconomic assets does not exceed its authorized rate
18of return for those assets. For purposes of determining the extent
19to which the costs have been recovered, any over-collections
20recorded in Energy Costs Adjustment Clause and Electric Revenue
21Adjustment Mechanism balancing accounts, as of December 31,
221996, shall be credited to the recovery of the costs.
23(b) The cost recovery plan shall provide for identification and
24separation of individual rate components such as charges for
25energy, transmission, distribution, public benefit programs, and
26recovery of uneconomic costs. The separation of rate components
27required by this subdivision shall be used to ensure that customers
28of the electrical corporation who become eligible to purchase
29electricity from suppliers other than the electrical corporation pay
30the same unbundled component charges, other than energy, that a
31bundled service customer pays. No cost shifting among customer
32classes, rate schedules, contract, or tariff options shall result from
33the separation required by this subdivision. Nothing in this
34provision is intended to affect the rates, terms, and conditions or
35to limit the use of any Federal Energy Regulatory
36Commission-approved contract entered into by the electrical
37corporation prior to the effective date of this provision.
38(c) In consideration of the risk that the uneconomic costs
39identified in Section 367 may not be recoverable within the period
40identified in subdivision (a) of Section 367, an electrical
P11 1corporation that, as of December 20, 1995, served more than four
2million customers, and was also a gas corporation that served less
3than four thousand customers, shall have the flexibility to employ
4risk management tools, such as forward hedges, to manage the
5market price volatility associated with unexpected fluctuations in
6natural gas prices, and the out-of-pocket costs of acquiring the risk
7management tools shall be considered reasonable and collectible
8within the transition freeze period. This subdivision applies only
9to the transaction costs associated with the risk management tools
10and shall not include any losses from changes in market prices.
11(d) In order to ensure implementation of the cost recovery plan,
12the limitation on the maximum amount of cost recovery for nuclear
13facilities that may be collected in any year adopted by the
14commission in Decision 96-01-011 and Decision 96-04-059 shall
15be eliminated to allow the maximum opportunity to collect the
16nuclear costs within the transition cap period.
17(e) As to an electrical corporation that is also a gas corporation
18serving more than four million California customers, so long as
19any cost recovery plan adopted in accordance with this section
20satisfies subdivision (a), it shall also provide for annual increases
21in base revenues, effective January 1, 1997, and January 1, 1998,
22equal to the inflation rate for the prior year plus two percentage
23points, as measured by the consumer price index. The increase
24shall do both of the following:
25(1) Remain in effect pending the next general rate case review,
26which shall be filed not later than December 31, 1997, for rates
27that would become effective in January 1999. For purposes of any
28commission-approved performance-based ratemaking mechanism
29or general rate case review, the increases in base revenue authorized
30by this subdivision shall create no presumption that the level of
31base revenue reflecting those increases constitute the appropriate
32starting point for subsequent revenues.
33(2) Be used by the utility for the purposes of enhancing its
34transmission and distribution system safety and reliability,
35including, but not limited to, vegetation management and
36emergency response. To the extent the revenues are not expended
37for system safety and reliability, they shall be credited against
38subsequent safety and reliability base revenue requirements. Any
39excess revenues carried over shall not be used to pay any monetary
40sanctions imposed by the commission.
P12 1(f) The cost recovery plan shall provide the electrical corporation
2with the flexibility to manage the renegotiation, buy-out, or
3buy-down of the electrical corporation’s power purchase
4obligations, consistent with review by the commission to assure
5that the terms provide net benefits to ratepayers and are otherwise
6reasonable in protecting the interests of both ratepayers and
7shareholders.
8(g) An example of a plan authorized by this section is the
9document entitled “Restructuring Rate Settlement” transmitted to
10the commission by Pacific Gas and Electric Company on June 12,
111996.
Section 368.5 of the Public Utilities Code is repealed.
(a) Notwithstanding any other provision of law, upon
14the termination of the 10-percent rate reduction for residential and
15small commercial customers set forth in subdivision (a) of Section
16368, the commission may not subject those residential and small
17commercial customers to any rate increases or future rate
18obligations solely as a result of the termination of the 10-percent
19rate reduction.
20(b) The provisions of subdivision (a) do not affect the authority
21of the commission to raise rates for reasons other than the
22termination of the 10-percent rate reduction set forth in subdivision
23(a) of Section 368.
24(c) Nothing in this section shall further extend the authority to
25impose fixed transition amounts, as defined in subdivision (d) of
26Section 840, or further authorize or extend rate reduction bonds,
27as defined in subdivision (e) of Section 840.
Section 369 of the Public Utilities Code is amended
29to read:
The commission shall establish an effective mechanism
31that ensures recovery of transition costs referred to in Sections
32367begin delete, 368, 375,end delete and 376, and subject to the conditions in Sections
33371 to 374, inclusive, from all existing and future consumers in
34the service territory in which the utility provided electricity services
35as of December 20, 1995; provided, that the costs shall not be
36recoverable for new customer load or incremental load of an
37existing customer where the load is being met through a direct
38transaction and the transaction does not otherwise require the use
39of transmission or distribution facilities owned by the utility.
40However, the obligation to pay the competition transition charges
P13 1cannot be avoided by the
formation of a local publicly owned
2electrical corporation on or after December 20, 1995, or by
3annexation of any portion of an electrical corporation’s service
4area by an existing local publicly owned electric utility.
5This section shall not apply to service taken under tariffs,
6contracts, or rate schedules that are on file, accepted, or approved
7by the Federal Energy Regulatory Commission, unless otherwise
8authorized by the Federal Energy Regulatory Commission.
Section 370 of the Public Utilities Code is amended
10to read:
The commission shall require, as a prerequisite for any
12consumer in California to engage in direct transactions permitted
13in Section 365, that beginning with the commencement of these
14direct transactions, the consumer shall have an obligation to pay
15the costs provided in Sections 367begin delete, 368, 375,end delete and 376, and subject
16to the conditions in Sections 371 to 374, inclusive, directly to the
17electrical corporation providing electricity service in the area in
18which the consumer is located. This obligation shall be set forth
19in the applicable rate schedule, contract, or tariff option under
20which the customer is receiving service from the electrical
21corporation. To the extent the consumer does not use the electrical
22corporation’s facilities
for direct transaction, the obligation to pay
23shall be confirmed in writing, and the customer shall be advised
24by any electricity marketer engaged in the transaction of the
25requirement that the customer execute a confirmation. The
26requirement for marketers to inform customers of the written
27requirement shall cease on January 1, 2002.
Section 371 of the Public Utilities Code is amended
29to read:
(a) Except as provided in Sections 372 and 374, the
31uneconomic costs provided in Sections 367begin delete, 368, 375,end delete and 376
32shall be applied to each customer based on the amount of electricity
33purchased by the customer from an electrical corporation or
34alternate supplier of electricity, subject to changes in usage
35occurring in the normal course of business.
36(b) Changes in usage occurring in the normal course of business
37are those resulting from changes in business cycles, termination
38of operations, departure from the utility service territory, weather,
39reduced production, modifications to production equipment or
40operations, changes in production or
manufacturing processes,
P14 1fuel switching, including installation of fuel cells pending a
2contrary determination by the California Energy Resources
3Conservation and Development Commission in Section 383,
4enhancement or increased efficiency of equipment or performance
5of existing self-cogeneration equipment, replacement of existing
6cogeneration equipment with new power generation equipment of
7similar size as described in paragraph (1) of subdivision (a) of
8Section 372, installation of demand-side management equipment
9or facilities, energy conservation efforts, or other similar factors.
10(c) Nothing in this section shall be interpreted to exempt or alter
11the obligation of a customer to comply with Chapter 5
12(commencing with Section 119075) of Part 15 of Division 104 of
13the Health and Safety Code. Nothing in this section shall be
14construed as a limitation on the ability of residential customers to
15alter their pattern of electricity purchases by
activities on the
16customer side of the meter.
Section 372 of the Public Utilities Code is amended
18to read:
(a) It is the policy of the state to encourage and support
20the development of cogeneration as an efficient, environmentally
21beneficial, competitive energy resource that will enhance the
22reliability of local generation supply, and promote local business
23growth. Subject to the specific conditions provided in this section,
24the commission shall determine the applicability to customers of
25uneconomic costs as specified in Sections 367begin delete, 368, 375,end delete and 376.
26Consistent with this state policy, the commission shall provide
27that these costs shall not apply to any of the following:
28(1) To load served onsite or under an over the fence arrangement
29by a
nonmobile self-cogeneration or cogeneration facility that was
30operational on or before December 20, 1995, or by increases in
31the capacity of a facility to the extent that the increased capacity
32was constructed by an entity holding an ownership interest in or
33operating the facility and does not exceed 120 percent of the
34installed capacity as of December 20, 1995, provided that prior to
35June 30, 2000, the costs shall apply to over the fence arrangements
36entered into after December 20, 1995, between unaffiliated parties.
37For the purposes of this subdivision, “affiliated” means any person
38or entity that directly, or indirectly through one or more
39intermediaries, controls, is controlled by, or is under common
P15 1control with another specified entity. “Control” means either of
2the following:
3(A) The possession, directly or indirectly, of the power to direct
4or to cause the direction of the management or policies of a person
5or entity, whether through an
ownership, beneficial, contractual,
6or equitable interest.
7(B) Direct or indirect ownership of at least 25 percent of an
8entity, whether through an ownership, beneficial, or equitable
9interest.
10(2) To load served by onsite or under an over the fence
11arrangement by a nonmobile self-cogeneration or cogeneration
12facility for which the customer was committed to construction as
13of December 20, 1995, provided that the facility was substantially
14operational on or before January 1, 1998, or by increases in the
15capacity of a facility to the extent that the increased capacity was
16constructed by an entity holding an ownership interest in or
17operating the facility and does not exceed 120 percent of the
18installed capacity as of January 1, 1998, provided that prior to June
1930, 2000, the costs shall apply to over the fence arrangements
20entered into after December 20, 1995, between unaffiliated
parties.
21(3) To load served by existing, new, or portable emergency
22generation equipment used to serve the customer’s load
23requirements during periods when utility service is unavailable,
24provided the emergency generation is not operated in parallel with
25the integrated electric grid, except on a momentary parallel basis.
26(4) After June 30, 2000, to any load served onsite or under an
27over the fence arrangement by any nonmobile self-cogeneration
28or cogeneration facility.
29(b) Further, consistent with state policy, with respect to
30self-cogeneration or cogeneration deferral agreements, the
31commission shall do the following:
32(1) Provide that a utility shall execute a final self-cogeneration
33or cogeneration deferral agreement with any customer that, on or
34
before December 20, 1995, had executed a letter of intent (or
35similar documentation) to enter into the agreement with the utility,
36provided that the final agreement shall be consistent with the terms
37and conditions set forth in the letter of intent and the commission
38shall review and approve the final agreement.
39(2) Provide that a customer that holds a self-cogeneration or
40cogeneration deferral agreement that was in place on or before
P16 1December 20, 1995, or that was executed pursuant to paragraph
2(1) in the event the agreement expires, or is terminated, may do
3any of the following:
4(A) Continue through December 31, 2001, to receive utility
5service at the rate and under terms and conditions applicable to
6the customer under the deferral agreement that, as executed,
7includes an allocation of uneconomic costs consistent with
8subdivision (e) of Section 367.
9(B) Engage in a direct transaction for the purchase of electricity
10and pay uneconomic costs consistent with Sections 367begin delete, 368, 375,end delete
11 and 376.
12(C) Construct a self-cogeneration or cogeneration facility of
13approximately the same capacity as the facility previously deferred,
14provided that the costs provided in Sections 367begin delete, 368, 375,end delete and
15376 shall apply consistent with subdivision (e) of Section 367,
16unless otherwise authorized by the commission pursuant to
17subdivision (c).
18(3) Subject to the firewall described in subdivision (e) of Section
19367, provide that the ratemaking treatment for self-cogeneration
20or cogeneration deferral agreements executed prior to
December
2120, 1995, or executed pursuant to paragraph (1) shall be consistent
22with the ratemaking treatment for the contracts approved before
23January 1995.
24(c) The commission shall authorize, within 60 days of the receipt
25of a joint application from the serving utility and one or more
26interested parties, applicability conditions as follows:
27(1) The costs identified in Sections 367begin delete, 368, 375,end delete and 376 shall
28not, prior to June 30, 2000, apply to load served onsite by a
29nonmobile self-cogeneration or cogeneration facility that became
30operational on or after December 20, 1995.
31(2) The costs identified in Sections 367begin delete, 368, 375,end delete and 376 shall
32not, prior to
June 30, 2000, apply to any load served under over
33the fence arrangements entered into after December 20, 1995,
34between unaffiliated entities.
35(d) For the purposes of this subdivision, all onsite or over the
36fence arrangements shall be consistent with Section 218 as it
37existed on December 20, 1995.
38(e) To facilitate the development of new microcogeneration
39applications, electrical corporations may apply to the commission
P17 1for a financing order to finance the transition costs to be recovered
2from customers employing the applications.
3(f) To encourage the continued development, installation, and
4interconnection of clean and efficient self-generation and
5cogeneration resources, to improve system reliability for consumers
6by retaining existing generation and encouraging new generation
7to connect to the electric grid, and
to increase self-sufficiency of
8consumers of electricity through the deployment of self-generation
9and cogeneration, both of the following shall occur:
10(1) The commission and the Electricity Oversight Board shall
11determine if any policy or action undertaken by the Independent
12System Operator, directly or indirectly, unreasonably discourages
13the connection of existing self-generation or cogeneration or new
14self-generation or cogeneration to the grid.
15(2) If the commission and the Electricity Oversight Board find
16that any policy or action of the Independent System Operator
17unreasonably discourages the connection of existing self-generation
18or cogeneration or new self-generation or cogeneration to the grid,
19the commission and the Electricity Oversight Board shall undertake
20all necessary efforts to revise, mitigate, or eliminate that policy or
21action of the Independent System
Operator.
Section 373 of the Public Utilities Code is amended
23to read:
(a) Electrical corporations may apply to the commission
25for an order determining that the costs identified in Sections 367begin delete, and 376 not be collected from a particular class of
26368, 375,end delete
27customer or category of electricity consumption.
28(b) Subject to the fire wall specified in subdivision (e) of Section
29367, the provisions of this section and Sections 372 and 374 shall
30apply in the event the commission authorizes a nonbypassable
31charge prior to the implementation of an Independent System
32Operator and Power Exchange referred to in subdivision (a) of
33Section 365.
Section 374 of the Public Utilities Code is amended
35to read:
(a) In recognition of statutory authority and past
37investments existing as of December 20, 1995, and subject to the
38firewall specified in subdivision (e) of Section 367, the obligation
39to pay the uneconomic costs identified in Sections 367begin delete, 368, 375,end delete
40 and 376 shall not apply to the following:
P18 1(1) One hundred ten megawatts of load served by irrigation
2districts, as hereafter allocated by this paragraph:
3(A) The 110 megawatts of load shall be allocated among the
4service territories of the three largest electrical corporations in the
5ratio of the number of irrigation districts in the
service territory of
6each utility to the total number of irrigation districts in the service
7territories of all three utilities.
8(B) The total amount of load allocated to each utility service
9area shall be phased in over five years beginning January 1, 1997,
10so that one-fifth of the allocation is allocated in each of the five
11years. Any allocation that remains unused at the end of any year
12shall be carried over to the succeeding year and added to the
13allocation for that year.
14(C) The load allocated to each utility service territory pursuant
15to subparagraph (A) shall be further allocated among the respective
16irrigation districts within that service territory by the California
17Energy Resources Conservation and Development Commission.
18An individual irrigation district requesting an allocation shall
19submit to the commission by January 31, 1997, detailed plans that
20show the load that
it serves or will serve and for which it intends
21to utilize the allocation within the timeframe requested. These
22plans shall include specific information on the irrigation districts’
23organization for electric distribution, contracts, financing and
24engineering plans for capital facilities, as well as detailed
25information about the loads to be served, and shall not be less than
26eight megawatts or more than 40 megawatts, provided, however,
27that any portion of the 110 megawatts that remains unallocated
28may be reallocated to projects without regard to the 40 megawatts
29limitation. In making an allocation among irrigation districts, the
30Energy Resources Conservation and Development Commission
31shall assess the viability of each submission and whether it can be
32accomplished in the timeframe proposed. The Energy Resources
33Conservation and Development Commission shall have the
34discretion to allocate the load covered by this section in a manner
35that best ensures its usage within the allocation period.
36(D) At least 50 percent of each year’s allocation to a district
37shall be applied to that portion of load that is used to power pumps
38for agricultural purposes.
39(E) Any load pursuant to this subdivision shall be served by
40distribution facilities owned by, or leased to, the district in question.
P19 1(F) Any load allocated pursuant to paragraph (1) shall be located
2within the boundaries of the affected irrigation district, or within
3the boundaries specified in an applicable service territory boundary
4agreement between an electrical corporation and the affected
5irrigation district; additionally, the provisions of subparagraph (C)
6of paragraph (1) shall be applicable to any load within the Counties
7of Stanislaus or San Joaquin, or both, served by any irrigation
8district that is currently serving or will be serving retail
customers.
9(2) Seventy-five megawatts of load served by the Merced
10Irrigation District hereafter prescribed in this paragraph:
11(A) The total allocation provided by this paragraph shall be
12phased in over five years beginning January 1, 1997, so that
13one-fifth of the allocation is received in each of the five years. Any
14allocation that remains unused at the end of any year shall be
15carried over to the succeeding year and added to the allocation for
16that year.
17(B) Any load to which the provision of this paragraph is
18applicable shall be served by distribution facilities owned by, or
19leased to, Merced Irrigation District.
20(C) A load to which the provisions of this paragraph are
21applicable shall be located within the boundaries of Merced
22Irrigation District
as those boundaries existed on December 20,
231995, together with the territory of Castle Air Force Base that was
24located outside of the district on that date.
25(D) The total allocation provided by this paragraph shall be
26phased in over five years beginning January 1, 1997, with the
27exception of load already being served by the district as of June
281, 1996, which shall be deducted from the total allocation and shall
29not be subject to the costs provided in Sections 367begin delete, 368, 375,end delete and
30376.
31(3) To loads served by irrigation districts, water districts, water
32storage districts, municipal utility districts, and other water agencies
33that, on December 20, 1995, were members of the Southern San
34Joaquin Valley Power Authority, or the Eastside Power Authority,
35provided, however, that this paragraph shall be
applicable only to
36that portion of each district or agency’s load that is used to power
37pumps that are owned by that district or agency as of December
3820, 1995, or replacements thereof, and is being used to pump water
39for district purposes. The rates applicable to these districts and
40agencies shall be adjusted as of January 1, 1997.
P20 1(4) The provisions of this subdivision shall no longer be
2operative after March 31, 2002.
3(5) The provisions of paragraph (1) shall not be applicable to
4any irrigation district, water district, or water agency described in
5paragraph (2) or (3).
6(6) Transmission services provided to any irrigation district
7described in paragraph (1) or (2) shall be provided pursuant to
8otherwise applicable tariffs.
9(7) Nothing in this chapter
shall be deemed to grant the
10commission any jurisdiction over irrigation districts not already
11granted to the commission by existing law.
12(b) To give the full effect to the legislative intent in enacting
13Section 701.8, the costs provided in Sections 367begin delete, 368, 375,end delete and
14376 shall not apply to the load served by preference power
15purchased from a federal power marketing agency, or its successor,
16pursuant to Section 701.8 as it existed on January 1, 1996, provided
17that the power is used solely for the customer’s own systems load
18and not for sale. The costs of this provision shall be borne by all
19ratepayers in the affected service territory, notwithstanding the
20firewall established in subdivision (e) of Section 367.
21(c) To give effect to an existing relationship, the obligation to
22pay the uneconomic
costs specified in Sections 367begin delete, 368, 375,end delete and
23376 shall not apply to that portion of the load of the University of
24California campus situated in Yolo County that was being served
25as of May 31, 1996, by preference power purchased from a federal
26marketing agency, or its successor, provided that the power is used
27solely for the facility load of that campus and not, directly or
28indirectly, for sale.
Section 374.5 of the Public Utilities Code is repealed.
Any electrical corporation serving agricultural customers
31that have multiple electric meters shall conduct research based on
32a statistically valid sample of those customers and meters to
33determine the typical simultaneous peak load of those customers.
34The results of the research shall be reported to the customers and
35the commission not later than July 1, 2001. The commission shall
36consider the research results in setting future electric distribution
37rates for those customers.
Section 375 of the Public Utilities Code is repealed.
(a) In order to mitigate potential negative impacts on
40utility personnel directly affected by electric industry restructuring,
P21 1as described in Decision 95-12-063, as modified by Decision
296-01-009, the commission shall allow the recovery of reasonable
3employee related transition costs incurred and projected for
4severance, retraining, early retirement, outplacement and related
5expenses for the employees.
6(b) The costs, including employee related transition costs for
7employees performing services in connection with Section 363,
8shall be added to the amount of uneconomic costs allowed to be
9recovered pursuant to this section and Sections 367, 368, and 376,
10provided recovery of these employee related transition costs shall
11extend beyond December 31, 2001, provided recovery of the costs
12shall not extend beyond December 31, 2006. However, there shall
13be no recovery for employee related transition costs associated
14with officers, senior supervisory employees, and professional
15employees performing predominantly regulatory functions.
Section 379 of the Public Utilities Code is amended
17to read:
Nuclear decommissioning costs shall not be part of the
19costs described in Sections 367begin delete, 368, 375,end delete and 376, but shall be
20recovered as a nonbypassable charge until the time as the costs
21are fully recovered. Recovery of decommissioning costs may be
22accelerated to the extent possible.
Section 397 of the Public Utilities Code is amended
24to read:
(a) begin deleteNotwithstanding subdivision (a) of Section 368, to end delete
26begin insertTo end insertensure the continued safe and reliable provision of electric
27service during the transition to competition, and to limit the effect
28of fuel price volatility in electric rates paid by California
29consumers, it is in the public interest to allow an electrical
30corporation which is also a gas corporation and served fewer than
31four million customers as of December 20, 1995, to file with the
32commission a rate cap mechanism which shall include a Fuel Price
33Index Mechanism requiring limited adjustments in an electrical
34corporation’s authorized System
Average Rate in effect on June
3510, 1996, to reflect price changes in the fuel market. The
36commission shall authorize an electrical corporation to implement
37a rate cap mechanism which includes a Fuel Price Index
38Mechanism provided the following criteria are met:
39(1) The Fuel Price Index Mechanism shall be based on the
40Southern California Border Index price for natural gas as published
P22 1periodically in Natural Gas Intelligence Magazine. The “Starting
2Point” of the Fuel Price Index Mechanism shall be defined as the
3California Border Index price as published in Natural Gas
4Intelligence for January 1, 1996.
5(2) The Fuel Price Index Mechanism shall include a “deadband”
6defined as a price range for natural gas that is any price up to 10
7percent higher, or lower, than the Starting Point.
8(3) The electrical corporation shall
not file for a change in its
9authorized System Average Rate unless the California Border
10Index price, on a 12-month, rolling average basis, is outside the
11deadband. If the published California Border Index is outside of
12the deadband, the electrical corporation shall increase, or decrease,
13its authorized System Average Rate by an amount equal to the
14product of 25 percent multiplied by the percentage by which the
1512-month rolling average natural gas price is higher, or lower, than
16the deadband.
17(4) In no case shall an electrical corporation’s authorized System
18Average Rate under the Fuel Price Index Mechanism exceed the
19average of the authorized system average rates for the two largest
20electrical corporations as of June 10, 1996.
21(5) This section shall become inoperative on December 31,
222001.
Section 846.2 of the Public Utilities Code is amended
24to read:
(a) Notwithstanding subdivision (c) of Section 841, for
26any electrical corporation that ended its rate freeze periodbegin delete described prior to July 15, 1999, the
27in subdivision (a) of Section 368end delete
28commission may order a fair and reasonable credit to ratepayers
29of any excess rate reduction bond proceeds.
30(b) “Excess rate reduction bond proceeds,” as used in this
31section, means proceeds from the sale of rate reduction bonds
32authorized by commission financing orders issued pursuant to this
33article that are subsequently determined by the commission to be
34in excess of the amounts necessary to provide the 10-percent rate
35reduction during the period when the
rates werebegin delete frozen pursuant begin insert
frozen.end insert
36to subdivision (a) of Section 368.end delete
Section 9600 of the Public Utilities Code is amended
38to read:
(a) It is the intent of the Legislature that California’s
40local publicly owned electric utilities and electric corporations
P23 1should commit control of their transmission facilities to the
2Independent System Operator as described in Chapter 2.3
3(commencing with Section 330) of Part 1 of Division 1. These
4utilities should jointly advocate to the Federal Energy Regulatory
5Commission a pricing methodology for the Independent System
6Operator that results in an equitable return on capital investment
7in transmission facilities for all Independent System Operator
8participants and is based on the following principles:
9(1) Utility specific access charge rates as proposed in Docket
10No. EC96-19-000 as finally approved by the Federal Energy
11
Regulatory Commission reflecting the costs of that utility’s
12transmission facilities shall go into effect on the first day of the
13Independent System Operator operation. The utility specific rates
14shall honor all of the terms and conditions of existing transmission
15service contracts and shall recognize any wheeling revenues of
16existing transmission service arrangements to the transmission
17owner.
18(2) (A) No later than two years after the initial operation of the
19Independent System Operator, the Independent System Operator
20shall recommend for adoption by the Federal Energy Regulatory
21Commission a rate methodology determined by a decision of the
22Independent System Operator governing board, provided that the
23decision shall be based on principles approved by the governing
24board including, but not limited to, an equitable balance of costs
25and benefits, and shall define the transmission facility costs, if
26any, which shall be
rolled in to the transmission service rate and
27spread equally among all Independent System Operator
28transmission users, and those transmission facility costs, if any,
29which should be specifically assigned to a specific utility’s service
30area.
31(B) If there is no governing board decision, the rate methodology
32shall be determined following a decision by the alternative dispute
33resolution method set forth in the Independent System Operator
34bylaws.
35(C) If no alternative dispute resolution decision is rendered,
36then a default rate methodology shall be a uniform regional
37transmission access charge and a utility specific local transmission
38access charge, provided that the default rate methodology shall be
39recommended for implementation upon termination of the cost
40recovery planbegin delete set forth in Section 368end delete or
no later than two years
P24 1after the initial operation of the Independent System Operator,
2whichever is later. For purposes of this paragraph, regional
3transmission facilities are defined to be transmission facilities
4operating at or above 230 kilovolts plus an appropriate percentage
5of transmission facilities operating below 230 kilovolts; all other
6transmission facilities shall be considered local. The appropriate
7percentage of transmission facilities described above shall be
8consistent with the guidelines in Federal Energy Regulatory
9Commission Order No. 888 and any exception approved by that
10commission.
11(3) If the rate methodology implemented as a result of a decision
12by the Independent System Operator governing board or resulting
13from the independent system operator alternative dispute resolution
14process results in rates different than those in effect prior to the
15decision for any transmission facility owner, the amount of any
16differences
between the new rates and the prior rates shall be
17recorded in a tracking account to be recovered from customers and
18paid to the appropriate transmission owners by the transmission
19facility owner after termination of the cost recovery plan set forth
20in Section 368. The recovery and payments shall be based on an
21amortization period not to exceed three years in the case of the
22electrical corporations or five years in the case of the local publicly
23owned electric utilities.
24(4) The costs of transmission facilities placed in service after
25the date of initial implementation of the Independent System
26Operator shall be recovered using the rate methodology in effect
27at the time the facilities go into operation.
28(5) The electrical corporations and the local publicly owned
29electric utilities shall jointly develop language for implementation
30proposals to the Federal Energy Regulatory
Commission based on
31these principles.
32(6) Nothing in this section shall compel any party to violate
33restrictions applicable to facilities financed with tax-exempt bonds
34or contractual restrictions and covenants regarding use of
35transmission facilities existing as of December 20, 1995.
36(b) Following a final Federal Energy Regulatory Commission
37decision approving the Independent System Operator, no California
38electrical corporation or local publicly owned electric utility shall
39be authorized to collect any competition transition charge
40authorized pursuant to this division and Chapter 2.3 (commencing
P25 1with Section 330) of Part 1 of Division 1 unless it commits control
2of its transmission facilities to the Independent System Operator.
Section 9607 of the Public Utilities Code is amended
4to read:
(a) The intent of this section is to avoid cost-shifting to
6customers of an electrical corporation resulting from the transfer
7of distribution services from an electrical corporation to an
8irrigation district.
9(b) Except as otherwise provided in this section and Section
109608, and notwithstanding any other provision of law, an irrigation
11district that offered electric service to retail customers as of January
121, 1999, may not construct, lease, acquire, install, or operate
13facilities for the distribution or transmission of electricity to retail
14customers located in the service territory of an electrical
15corporation providing electric distribution services, unless the
16district has first applied for and received the approval of
the
17commission and implements its service consistent with the
18commission’s order. The commission shall find that service to be
19in the public interest and shall approve the request of a district to
20provide distribution or transmission of electricity to retail customers
21located in the service territory of an electrical corporation providing
22electric distribution service if, after notice and hearing, the
23commission determines all of the following:
24(1) The district will provide universal service to all retail
25customers who request service within the area to be served, at
26published tariff rates and on a just, reasonable, and
27nondiscriminatory basis, comparable to that provided by the current
28retail service provider.
29(2) If the area the district is proposing to serve is either of the
30following:
31(A) Is within the district’s
boundaries but less than the entire
32district, the area to be served includes a percentage of residential
33customers and small customers, based on load, comparable to the
34percentage of residential and small customers in the district, based
35on load.
36(B) Includes territory outside the district’s boundaries, in which
37case the territory outside the district’s boundaries must include a
38percentage of residential customers and small customers, based
39on load, comparable to the percentage of residential and small
P26 1customers in the county or counties where service is to be provided,
2based on load.
3(3) Service by the district will be consistent with the intent of
4the state to avoid economic waste caused by duplication of facilities
5as set forth in Section 8101.
6(4) Service by the district will include reasonable mitigation of
7any
adverse effects on the reliability of an existing service by the
8electrical corporation.
9(5) The district has established, funded, and is carrying out
10public purpose and low-income programs comparable to those
11provided by the current electric retail service provider.
12(6) That district’s tariffed electric rates, exclusive of commodity
13costs, will be at least 15 percent below the tariffed electric rates,
14exclusive of commodity costs and nonbypassable charges under
15Sections 367,begin delete 368, 375,end delete 376, and 379, of the electrical corporation
16for comparable services.
17(7) Service by the district is in the public interest.
18(c) An irrigation district that obtains the approval of the
19
commission under this section to serve an area shall prepare an
20annual report available to the public on the total load and number
21of accounts of residential, low-income, agricultural, commercial,
22and industrial customers served by the irrigation district in the
23approved service area.
24(d) The commission shall have jurisdiction to resolve and
25adjudicate complaint cases brought against an irrigation district
26that offered electric service to retail customers as of January 1,
271999, by an interested party where the complaint concerns retail
28electric service outside the boundaries of the district and within
29the service territory of an electrical corporation. Nothing in this
30section grants the commission jurisdiction to adjudicate complaint
31cases involving retail electric service by an irrigation district inside
32its boundaries or inside an irrigation district’s exclusive service
33territory.
34(e) Any project involving electric transmission or distribution
35facilities to be constructed or installed by an irrigation district to
36serve retail customers located in the service territory of an electrical
37corporation providing electric distribution services shall comply
38with the California Environmental Quality Act, (Division 13
39(commencing with Section 21000)) of the Public Resources Code.
40The county in which the construction or installation is to occur
P27 1shall act as the lead agency. If a project involves the construction
2or installation of electric transmission or distribution facilities in
3more than one county, the county where the majority of the
4construction is anticipated to occur shall act as the lead agency.
5(f) An irrigation district may not offer service to customers
6outside of its district boundaries before offering service to all
7customers within its district boundaries.
8(g) This section does not apply to electric distribution service
9provided by Modesto Irrigation District to those customers or
10within those areas described in subdivisions (a), (b), and (c) of
11Section 9610.
12(h) The provisions of this section shall not apply to (1) a
13cumulative 90 megawatts of load served by the Merced Irrigation
14District that is located within the boundaries of Merced Irrigation
15District, as those boundaries existed on December 20, 1995,
16together with the territory of Castle Air Force Base which was
17located outside thebegin delete Districtend deletebegin insert districtend insert on that date, or (2) electric load
18served by thebegin delete Districtend deletebegin insert
districtend insert which was not previously served by
19an electric corporation that is located within the boundaries of
20Merced Irrigation District, as those boundaries existed on
21December 20, 1995, together with the territory of Castle Air Force
22Base which was located outside thebegin delete Districtend deletebegin insert districtend insert on that date.
23(i) For purposes of this section, a megawatt of load shall be
24calculated in accordance with the methodology established by the
25California Energy Resource Conservation and Development
26Commission in its Docket No. 96-IRR-1890, but the 90 megawatts
27shall not include electrical usage by customers that move to the
28areas described in paragraph (1) after December 31, 2000.
29(j) Subdivision (a) of this section shall not apply to the
30construction, modification, lease, acquisition, installation, or
31operation of facilities for the distribution or transmission of
32electricity to customers electrically connected to a district as of
33December 31, 2000, or to other customers who subsequently locate
34at the same premises.
35(k) In recognition of contractual arrangements and settlements
36existing as of June 1, 2000, this section does not apply to the
37acquisition or operation of the electric distribution facilities that
38are the subject of the Settlement Agreement dated May 1, 2000,
39between Pacific Gas and Electric Company and the San Joaquin
40Irrigation District.
P28 1(l) For purposes of this section, retail customers do not include
2an irrigation district’s own electric load being served of retail by
3an electrical
corporation.
O
99