BILL ANALYSIS                                                                                                                                                                                                    �




                SENATE ENERGY, UTILITIES AND COMMUNICATIONS COMMITTEE
                                 ALEX PADILLA, CHAIR
          

          SB 1389 -  Hill                                   Hearing Date:   
          April 29, 2014             S
          As Introduced: February 21, 2014        FISCAL           B

                                                                        1
                                                                        3
                                                                        8
                                                                        9

                                      DESCRIPTION
          
          Current law  defines an intrastate transmission pipeline, and  
          directs the California Public Utilities Commission (CPUC) to  
          regulate and enforce intrastate gas pipeline transportation and  
          pipeline facilities pursuant to federal law. (Public Utilities  
          Code � 950, 955)  

          Current federal regulations and general order of the CPUC   
          establish and enforce minimum safety standards for the design,  
          construction, testing, operation, and maintenance of natural gas  
          pipeline facilities, including transmission pipelines. (49 CFR  
          190-193 and General Order 112-E) 

           Current federal regulations  limit the maximum allowable  
          operating pressure (MAOP) of a steel or plastic pipeline  
          installed prior to July 1, 1970 to the lowest of the following  
          four pressures:

             1)   Design pressure of the weakest element in the segment;  
             2)   Pressure obtained by dividing the post-construction  
               pressure by the applicable safety factor; 
             3)   Highest actual operating pressure the segment was  
               subjected to during the five years preceding July 1, 1970  
               [a.k.a. the grandfather clause]; or
             4)   Maximum safe pressure, determined by the operator after  
               considering the history of the segment. (49 CFR 192.619)

           Current federal law  allows states to adopt standards for  
          intrastate transmission pipelines that are more stringent than  
          federal standards. (49 USC 60104)



                                          1








           CPUC Decision  11-06-017 disallowed gas pipeline operators from  
          using method 3/the grandfather clause to determine MAOP.

           Current law  requires each gas corporation to submit to the CPUC  
          a general pipeline safety enhancement plan (PSEP) to either  
          pressure test pipelines or replace segments of pipelines that  
          were not pressure tested or that lack pressure testing  
          performance information. As an interim measure, to allow the gas  
          system to continue to operate until all pipelines have been  
          tested or replaced, engineering-based assumptions may be used to  
          determine MAOP in the absence of complete records. (Public  
          Utilities Code � 958)

           This bill  would require the CPUC to adopt rules for gas  
          corporations to follow when determining the MAOP for an  
          intrastate transmission pipeline installed prior to July 1,  
          1970.


                                      BACKGROUND
           
          Natural Gas Pipelines and Their Regulation - Natural gas travels  
          from the well to consumers through a series of pipelines,  
          including flowlines, gathering lines, transmission lines,  
          distribution lines, and service lines. Transmission pipelines  
          are large (20 - 42" diameter) pipes that operate at high  
          pressures (200 - 1,500 pounds per square inch gauge, psig) to  
          carry gas hundreds or thousands of miles from the producing  
          region to local distribution companies. 

          Federal law establishes minimum safety standards for intrastate  
          gas pipelines. Pursuant to federal law and by agreement with the  
          federal Pipeline and Hazardous Materials Safety Administration  
          (PHMSA), California has voluntarily assumed responsibility for  
          enforcing these minimum standards. In addition, California has  
          adopted additional, more stringent safety standards. To ensure  
          compliance with federal and state standards, the CPUC reviews  









                                          2







          the safety plans, records, and reports of utilities<1>; conducts  
          compliance inspections; responds to inquiries and complaints  
          from the public; and investigates accidents for over 10,000  
          miles of transmission pipeline.

          San Bruno Pipeline Explosion - On September 9, 2010, a 30"  
          diameter natural gas transmission pipeline (Pipeline 132, owned  
          by Pacific Gas and Electric Company, PG&E) ruptured in a  
          residential neighborhood in the City of San Bruno. The rupture  
          caused an explosion and fire that killed eight people and  
          injured dozens more, destroyed 38 homes, and damaged an  
          additional 70. Three hundred customers saw their gas service  
          disrupted. 

          Following the tragedy, the National Transportation Safety Board  
          (NTSB) stated that California natural gas corporations may not  
          be aware of the features of all pipe throughout their systems  
          and, consequently, may not have calculated the pressure for each  
          pipe segment. Specifically, the NTSB determined that Pipeline  
          132 had a longitudinal seam weld, despite PG&E having considered  
          it to be seamless. Such recordkeeping inconsistencies may prove  
          dangerous as pipelines with different specifications or features  
          usually are operated differently, e.g., at different rates of  
          pressure. 

          Maximum Allowable Operating Pressure (MAOP) - Federal law  
          requires that pipeline operators determine MAOP for each  
          pipeline or each distinct segment of a pipeline system. MAOP may  
          differ from design pressure because numerous factors can alter  
          the integrity of a pipeline, including time-dependent threats  
          (stress corrosion cracking, internal or external corrosion,  
          etc.) as well as time-independent threats (third-party damage,  
          etc.). Accurately determining MAOP is important because the  
          threat to life and property increases as pressure increases.

          Federal regulations (49 CFR 192.619(a)) limit the MAOP of a  
          steel or plastic pipeline installed prior to July 1, 1970 to the  
           lowest  of the following four pressures. Method 1/Design pressure  
          is based on the specifications and/or features of the pipe.  
          ---------------------------
          <1> Entities regulated by the CPUC include Pacific Gas and  
          Electric, Southern California Gas, San Diego Gas & Electric,  
          Southwest Gas, and several smaller natural gas utilities. The  
          CPUC also regulates Lodi Gas Storage and Wild Goose Storage,  
          independent/third party storage providers. 


                                          3







          Design pressure is not known or knowable for all currently  
          operating transmission pipelines, especially older ones. In  
          cases of incomplete or missing information, General Order 112-E  
          authorizes utilities to use engineering-based assumptions to  
          determine MAOP until all pipelines have been tested or replaced.  
          Method 2/Test pressure is known or knowable for most pipelines  
          through the use of hydrostatic pressure testing, which subjects  
          a pipeline to pressure much greater than its normal operating  
          pressure in order to assess integrity and identify leaks. Method  
          3/Historical pressure (a.k.a. the grandfather clause) exempts  
          pre-1970 pipelines "in satisfactory condition" from the  
          aforementioned regulations, and instead allows operators to set  
          the MAOP at the highest actual operating pressure to which the  
          segment was subjected during the five years preceding July 1,  
          1970. Method 4/Discretionary pressure is not commonly employed  
          since it likely would be the highest of all the values, not the  
          lowest. 

          Controversy over Method 3/The Grandfather Clause - In its  
          report<2> on the 2010 San Bruno pipeline explosion, the NTSB  
          stated that "there is no safety justification for the  
          grandfather clause exempting pre-1970 pipelines from the  
          requirement for hydrostatic pressure testing." In January 2011,  
          the NTSB issued urgent safety recommendations<3> that MAOP be  
          set at either the design pressure or the test pressure,  
          whichever is lower. The CPUC directed jurisdictional gas  
          utilities to comply with the NTSB safety recommendations through  
          D.11-06-017, which orders an "end to historic exemptions"-that  
          is, Method 3/Historical pressure (a.k.a. the grandfather  
          clause)-and requires "that all gas transmission pipelines  
          constructed before 1970 be subjected to a hydrostatic pressure  
          test."<4>

          In a document dated January 14, 2014, PG&E appears to disregard  
          the 2011 CPUC decision (D.11-06-017) by stating that "a pipeline  
          designed and constructed prior to implementation of the federal  
          regulations may operate at the highest pressure experienced in  
          the five years prior to July 1, 1970 even if that pressure  
          exceeds the design pressure." This statement suggests that PG&E  
          ---------------------------
          <2>  http://www.ntsb.gov/doclib/reports/2011/PAR1101.pdf  
          <3>  http://www.ntsb.gov/doclib/recletters/2010/P-10-002-004.pdf  
          <4> For more information, see R.11-02-019 and slide 48 of CPUC  
          Actions Post San Bruno, a presentation given by staff at the  
          CPUC's September 8, 2011 meeting. 


                                          4







          relies on Method 3/Historical pressure (a.k.a. the grandfather  
          clause) to determine MAOP under certain circumstances, despite  
          the CPUC ordering an end to this. 

          The Office of Ratepayer Advocates (ORA), the City of San Bruno,  
          and the City of San Carlos have questioned PG&E's compliance  
          with the 2011 CPUC decision ending the grandfather clause. ORA  
          is also concerned that PG&E has had off-the-record discussions  
          with CPUC Safety and Enforcement Division staff regarding MAOP,  
          as transcripts from a December 16, 2013 hearing<5> indicate. 

                                       COMMENTS
           
              1.   Author's Statement  . The author writes that several  
               parties have raised concerns that PG&E has been  
               (incorrectly) interpreting rules regarding MAOP "behind  
               closed doors. This bill would require the CPUC to make a  
               public determination on the methodology, as the public  
               deserves."

              2.   Enforcement Needed, Not New Rules  . The bill is calling  
               for rules for determining MAOP. In fact, the CPUC has  
               already adopted policy for determining MAOP, ordering in a  
               2011 decision (D.11-06-017) that Method 3/Historical  
               pressure (a.k.a. the grandfather clause) no longer could be  
               used. Therefore, since the CPUC has already taken the  
               action proposed by this bill which is being ignored by the  
               gas corporation, the author and committee may wish to  
               consider codifying the CPUC's order which supersedes  
               federal law and prohibits California gas corporations from  
               utilizing the grandfather clause (49 CFR 192.619(c)) to  
               determine the maximum allowable operating pressure for any  
               pipeline installed prior to July 1, 1970."

              3.   A Transparent, Public Forum is Appropriate  . Any state  
               action regarding MAOP would apply to all gas corporations  
               operating in California. Thus, it is appropriate that the  
               issue be addressed on-the-record of a transparent, public  
               forum rather than in private meetings between PG&E and the  
               CPUC.
           
             4.   No Direct Financial Impacts  . This bill is not expected  
               to result in rate increases, decreases, or cost shifts for  

             --------------------------
          <5> Evidentiary hearing on R.11-02-019. See pages 3176-3177.


                                          5







               customers. While it requires no ongoing costs for the CPUC,  
               it would require the CPUC to address the methodology for  
               determining MAOP, potentially extending R.11-02-019.


                                       POSITIONS
           
           Sponsor:
           
          Author

           Support:
           
          Office of Ratepayer Advocates, if amended
          The Utility Reform Network

           Oppose:
           
          None on file





          


          Alexis Erwin 
          SB 1389 Analysis
          Hearing Date:  April 29, 2014
          
















                                          6