BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  SB 1433
                                                                  Page  1

          Date of Hearing:  June 18, 2014

                       ASSEMBLY COMMITTEE ON LOCAL GOVERNMENT
                           K.H. "Katcho" Achadjian, Chair
                  SB 1433 (Hill) - As Introduced:  February 21, 2014

          SENATE VOTE  :  35-0
           
          SUBJECT  :  Local Agency Public Construction Act: transit  
          design-build contracts.

           SUMMARY  :  Repeals the sunset date on transit operators'  
          authority to use design-build for transit projects, expands the  
          number of entities eligible to exercise this authority,  
          eliminates minimum cost thresholds, and deletes reporting  
          requirements.  Specifically,  this bill  :   

          1)Changes the definition of "transit operator" to include any  
            other local or regional agency responsible for the  
            construction of transit projects, as specified.

          2)Eliminates cost thresholds in current law limiting the use of  
            design-build (DB) to: 

             a)   Contracts for capital maintenance or capacity-enhancing  
               rail projects that cost more than $25 million; and, 

             b)   Contracts for non-rail transit projects that cost more  
               than $2.5 million.

          3)Repeals a requirement that transit operators report to the  
            Legislative Analyst's Office (LAO) specified information about  
            public works projects financed with public funds and procured  
            through the DB process.

          4)Repeals the existing sunset date of January 1, 2015, on  
            transit operators' authority to use DB, thereby making this  
            authorization permanent.

           EXISTING LAW  :

          1)Requires local officials, under the Local Agency Public  
            Construction Act (LAPC Act), to invite bids for construction  
            projects and then award contracts to the lowest responsible  
            bidder under the traditional design-bid-build project delivery  








                                                                  SB 1433
                                                                  Page  2

            system.

          2)Authorizes, as an alternative to the LAPC Act, transit  
            operators to enter into a DB contract for both the design and  
            construction of a project, and prescribes the process to be  
            used by transit operators when developing and procuring a DB  
            project.

          3)Requires transit operators who use DB contracting to: 

             a)   Prepare documents describing the project and its  
               specifications; 

             b)   Prepare a detailed request for proposals that invites  
               competitive bids; 

             c)   Establish a detailed procedure to pre-qualify DB  
               entities; and, 

             d)   Establish the procedures to select the DB entity.

          4)Requires a transit operator to establish a procedure for final  
            selection of the DB entity, subject to the following  
            conditions:

             a)   In no case shall the transit operator award a contract  
               to a DB entity for a capital maintenance or  
               capacity-enhancing rail project unless that project exceeds  
               $25 million in cost;

             b)   For non-rail transit projects that exceed $2.5 million,  
               the transit operator may award the project to the lowest  
               responsible bidder or by using the best value method; and,

             c)   For the acquisition and installation of technology  
               applications or surveillance equipment designed to enhance  
               safety, disaster preparedness, and homeland security  
               efforts, there shall be no cost threshold and the transit  
               operator may award the contract to the lowest responsible  
               bidder or by using the best value method.

          5)Requires, for DB contracts awarded prior to the effective date  
            of specified regulations adopted by the Department of  
            Industrial Relations (DIR), a transit operator to establish  
            and enforce a labor compliance program or contract with a  








                                                                  SB 1433
                                                                  Page  3

            third party to operate such a program, as specified.  This  
            requirement does not apply to DB projects if the operator or  
            the DB entity has entered into a collective bargaining  
            agreement that binds all contractors performing work on the  
            contract, or to any other project of the transit operator that  
            is not DB.

          6)Requires, for DB contracts awarded on or after the effective  
            date of specified regulations adopted by DIR, the transit  
            operator to reimburse DIR for its reasonable and directly  
            related costs of performing prevailing wage monitoring and  
            enforcement on public works projects, as specified.  All  
            moneys collected pursuant to this requirement shall be  
            deposited in the State Public Works Enforcement Fund to be  
            used only for enforcement of prevailing wage requirements on  
            those projects, as specified.

          7)Allows a transit operator, in lieu of reimbursing DIR for its  
            reasonable and directly-related costs of performing monitoring  
            and enforcement on public works projects, to continue  
            operating an existing previously approved labor compliance  
            program to monitor and enforce prevailing wage requirements on  
            the project if: 

             a)   It has not contracted with a third party to conduct its  
               labor compliance program and requests and receives approval  
               from DIR to continue its existing program; or, 

             b)   It enters into a collective bargaining agreement that  
               binds all of the contractors performing work on the project  
               and that includes a mechanism for resolving disputes about  
               the payment of wages.

          8)Requires a transit operator that uses DB contracting to submit  
            a report to the LAO within certain timeframes that contains  
            specified information about all of its public works projects  
            financed with public funds and procured through the DB  
            process.

          9)Excludes construction projects on state highways or local  
            streets and roads from transit operators' authority to use DB.
          10)Defines "transit operator" to mean any transit district,  
            included transit district, municipal operator, included  
            municipal operator, transit development board, or a  
            consolidated agency, as specified, or any joint powers  








                                                                  SB 1433
                                                                  Page  4

            authority formed to provide transit service.

          11)Defines "design-build" as a procurement process in which both  
            the design and construction of a project are procured from a  
            single entity.

          12)Defines "best-value" as a value determined by objective  
            criteria related to price, features, functions, and life cycle  
            costs.

          13)Sunsets the DB authority for transit operators on January 1,  
            2015.

           FISCAL EFFECT  :   According to the Senate Appropriations  
          Committee:

          1)Unknown overall contracting costs or savings to transit  
            operators.  By extending DB authority indefinitely and  
            deleting cost thresholds for which DB procurement may be used,  
            any future transit project may be awarded on a "best value"  
            rather than "lowest responsible bidder" basis.  Overall  
            contracting costs may increase, to the extent contracts are  
            awarded to bidders who may not have the lowest bid price.  On  
            the other hand, overall contracting costs may be lower to the  
            extent that efficiencies are gained by using DB, such as  
            expedited project delivery.  Transit project funding could be  
            from any combination of local, federal, and state funds  
            (Public Transportation Account and potentially bond funds).  

          2)Likely minor fiscal impacts on DIR related to the department's  
            monitoring and enforcement of prevailing wage requirements,  
            reimbursed by transit operators (State Public Works  
            Enforcement Fund).  Staff notes that by extending the deposit  
            of funds into this continuously appropriated fund, the bill  
            makes an appropriation.

          3)Minor cost savings to the LAO by deleting requirements that  
            transit operators submit reports on the use of DB (General  
            Fund).

           COMMENTS  :   

           1)Purpose of this bill  .  This bill repeals the sunset date on  
            transit operators' authority to use DB for transit projects,  
            expands the number of entities eligible to exercise this  








                                                                  SB 1433
                                                                  Page  5

            authority, eliminates minimum cost thresholds, and deletes  
            reporting requirements.  This bill is sponsored by the  
            California Transit Association.

           2)Author's statement  .  According to the author, "SB 1433 would  
            eliminate the sunset date on the design-build authority for  
            transit operators, thereby maintaining an innovative and  
            valuable tool transit operators can use to deliver critical  
            capital projects and removing the need to come back to the  
            Legislature periodically to extend the date.  Additionally, SB  
            1433 would clarify that a county transportation commission or  
            a regional transportation planning agency, not generally  
            considered a "transit operator," can utilize design-build to  
            construct a transit project, as well as remove cost thresholds  
            for the use of design-build."

           3)Background  .  The LAPC Act generally requires local officials  
            to invite bids for construction projects and then award  
            contracts to the lowest responsible bidder.  This  
            design-bid-build method is the traditional approach to public  
            works construction.  
            Under the DB method, a single contract covers the design and  
            construction of a project with a single company or consortium  
            that acts as both the project designer and builder.  The DB  
            entity arranges all architectural, engineering, and  
            construction services, and is responsible for delivering the  
            project at a guaranteed price and schedule based upon  
            performance criteria set by the public agency.  The DB method  
            can be set by the public agency.  The DB method can be faster  
            and, therefore, cheaper, than the design-bid-build method, but  
            it requires a higher level of management sophistication since  
            design and construction may occur simultaneously.

            Advocates for the DB method of contracting for public works  
            contend that project schedule savings can be realized because  
            only a single request for proposals is needed to select the  
            project's designer and builder.  The more traditional  
            design-bid-build project approach requires the separate  
            selection of the design consultant or contractor, completion  
            of design, and then advertising for bids and selection of the  
            construction contractor.  Proponents add that DB allows the  
            overlap of design and construction activities, resulting in  
            additional time savings and lower project costs.  By avoiding  
            the delays and change orders that result from the traditional  
            design-bid-build method of contracting, proponents argue that  








                                                                  SB 1433
                                                                  Page  6

            DB can deliver public works faster and cheaper.

            Detractors of DB contend that it eliminates competitive  
            bidding, allows the private contractor or consortium to  
            inspect and sign off on their own work, and increases project  
            delivery costs.

           4)Transit operators' DB authority  .  AB 958 (Scott), Chapter 541,  
            Statutes of 2000, authorized transit operators to use DB  
            procurement until January 1, 2005.  SB 1130 (Scott), Chapter  
            196, Statutes of 2004, extended the sunset date until January  
            1, 2007.  AB 372 (Nation), Chapter 262, Statutes of 2006,  
            extended the sunset again, to January 1, 2011, and made other  
            modifications to the authority, including requiring a transit  
            operator to establish a labor compliance program for a DB  
            contract if the transit operator does not already have such a  
            program.  AB 729 (Evans), Chapter 466, Statutes of 2009,  
            extended the sunset date until January 1, 2015.

           5)LAO reports and recommendations  .  The LAO issued a report to  
            the Legislature on February 3, 2005, titled "Design-Build: An  
            Alternative Construction System," which reported on all DB  
            authorities granted to various types of government entities  
            (not just transit operators' authority).  After analyzing the  
            claims of proponents and opponents and reviewing the  
            experience of local agencies that were authorized to use DB at  
            the time, the LAO recommended that "the Legislature grant  
            design-build authority only to buildings and directly related  
            infrastructure.  There are more complex issues associated with  
            other public works projects such as transportation, public  
            transit, and water resources facilities.  Evaluation of  
            design-build as a construction delivery option for these other  
            infrastructure facilities is beyond the scope of this report."  


            In January of 2010 the LAO issued a second report, this time  
            updating the Legislature on the use of DB by counties in  
            California, based on data received from counties that utilized  
            this methodology.  In the report, LAO states that "although it  
            was difficult to draw conclusions from the reports received  
            about the effectiveness of design-build compared to other  
            project delivery methods, we do not think that the reports  
            provide any evidence that would discourage the Legislature  
            from granting design-build authority to local agencies on an  
            ongoing basis.  In doing so, however, we recommend the  








                                                                  SB 1433
                                                                  Page  7

            Legislature consider some changes such as creating a uniform  
            design-build statute, eliminating cost limitations, and  
            requiring project cost to be a larger factor in awarding the  
            design-build contract."

           6)Related legislation  .  SB 785 (Wolk) repeals existing law  
            authorizing the Department of General Services (DGS), the  
            Department of Corrections and Rehabilitation (CDCR), and local  
            agencies to use the design-build procurement process, and  
            enacts uniform provisions authorizing DGS, CDCR, and local  
            agencies to utilize the design-build procurement process for  
            specified public works projects.  SB 785 is pending in this  
            committee.

           7)Policy considerations  .  The Committee may wish to consider the  
            following:
           
             a)   Elimination of cost thresholds  ?  This bill eliminates  
               all cost thresholds limiting the use of DB by transit  
               operators, which means a transit operator could elect to  
               use DB for projects of any size or cost.  The LAO has  
               recommended eliminating cost limitations in prior reports  
               on DB.  However, the LAO has also noted, "There are more  
               complex issues associated with other public works projects  
               such as transportation, public transit, and water resources  
               facilities.  Evaluation of design-build as a construction  
               delivery option for these other infrastructure facilities  
               is beyond the scope of this report."  Detractors of DB have  
               noted that it can disadvantage smaller companies that do  
               not have the financial resources or expertise to handle  
               both design and construction.  

               The sponsor of this bill has not provided any examples of  
               projects costing less than the current law threshold of $25  
               million for rail and $2.5 million for non-rail projects.   
               On the contrary, examples of successful DB projects have  
               far exceeded these cost limitations.  The Committee may  
               wish to consider if elimination of cost limitations is  
               justified and 
               if it achieves policy objectives the Committee wishes to  
               endorse.

              b)   Continued LAO reporting  ?  AB 958 required transit  
               operators to report to the LAO on their experience using DB  
               procurement.  According to the LAO, only one report has  








                                                                  SB 1433
                                                                  Page  8

               been submitted to date.  It is not clear if local transit  
               operators are not complying with this current-law  
               requirement, or if they are citing different statutory  
               authorizations to use DB.  The Committee may wish to  
               consider whether LAO reporting requirements should remain  
               in statute, especially considering this bill's expansion of  
               DB authority to "any other local or regional agency  
               responsible for the construction of transit projects" and  
               the bill's elimination of cost thresholds. 

              c)   Elimination of sunset  ?  While the authority to use DB  
               has been available to transit operators for more than a  
               decade, as noted above, there is little data on how this is  
               working and whether DB is achieving its intended goals.   
               The Committee may wish to consider whether it is time to  
               make this authority permanent, or whether the Legislature  
               should retain oversight by extending the sunset until more  
               data is available.

           8)Arguments in support  . The California Transit Association,  
            sponsor of this bill, states, "Design-build is one of several  
            innovative alternative procurement methods to the traditional  
            design-bid-build approach.  Design-build is the most commonly  
            used alternative for the delivery of public works  
            projects?Here in California, the Santa Clara Valley  
            Transportation Authority (VTA) is relying on the authority  
            provided by this authorization by using design-build  
            contracting for the first phase of its BART Silicon Valley  
            Project.  Additionally, VTA plans to use design-build for the  
            second phase of the BART Silicon Valley Project through  
            downtown San Jose, scheduled to begin in 2017.  In addition to  
            VTA's BART Silicon Valley Project, the Peninsula Corridor  
            Joint Powers Board (Caltrain) is currently utilizing  
            design-build for its advanced signaling system (positive train  
            control) on the corridor and plans to use design-build for the  
            electrification of the Caltrain system."

           9)Arguments in opposition  .  The Air Conditioning Sheet Metal  
            Association, the Air-conditioning and Refrigeration  
            Contractors Association, the California chapters of the  
            National Electrical Contractors Association, and the  
            California Legislative Conference of the Plumbing, Heating and  
            Piping Industry, in opposition, state, "Unlike other  
            design-build statutes which contain protections for  
            contractors, subcontractors and construction industry  








                                                                  SB 1433
                                                                  Page  9

            journeymen and apprentices, current law pertaining to  
            design-build authority for transit operators lacks many of the  
            industry supported boiler plate design-build provisions.   
            Further, the conversation regarding design-build as a whole is  
            happening on a wider scale in SB 785 (Wolk).  That measure is  
            aimed at providing uniformity throughout the design-build  
            statutes?We believe it is imprudent at this time to completely  
            delete the sunset provision within this section of law while  
            larger conversations on uniformity for design-build  
            procurement are ongoing."

           10)Double-referral  .  This bill is double-referred to the  
            Transportation Committee.

           REGISTERED SUPPORT / OPPOSITION  :

           Support 
           
          California Transit Association [SPONSOR]
          Associated General Contractors
          California Concrete Contractors Association
          California Special Districts Association
          Monterey-Salinas Transit
          Orange County Transportation Authority
          Peninsula Corridor Joint Powers Board (Caltrain)
          San Mateo County Transit District
          San Mateo County Transportation Authority
          Santa Clara Valley Transportation Authority
           
            Opposition 
           
          Air Conditioning Sheet Metal Association
          Air Conditioning Trade Association
          Air-conditioning and Refrigeration Contractors Association
          Associated Builders and Contractors - San Diego Chapter
          California chapters of the National Electrical Contractors  
          Association
          California Legislative Conference of the Plumbing, Heating and  
          Piping Industry
          Plumbing-Heating-Cooling Contractors Association of California
          State Building and Construction Trades Council of California,  
          AFL-CIO
          Western Electrical Contractors Association

           Analysis Prepared by  :    Angela Mapp / L. GOV. / (916) 319-3958 








                                                                  SB 1433
                                                                  Page  10