BILL ANALYSIS                                                                                                                                                                                                    �



                                                                  SB 1433
                                                                  Page  1

          Date of Hearing:   August 13, 2014

                        ASSEMBLY COMMITTEE ON APPROPRIATIONS
                                  Mike Gatto, Chair

                    SB 1433 (Hill) - As Amended:  August 7, 2014 

          Policy Committee:                             Local  
          GovernmentVote:8 - 0 
                       Transportation                                11 -  
          0 

          Urgency:     No                   State Mandated Local Program:  
          Yes    Reimbursable:              No

           SUMMARY  

          This bill extends the sunset date on transit operators'  
          authority to use design-build for transit projects from January  
          1, 2015 to January 1, 2017, for project solicitations that begin  
          before January 1, 2015. For project solicitations that begin on  
          or after January 1, 2015, this bill extends the authority to use  
          design-build to January 1, 2024, and conforms the requirements  
          for using design-build to those being extended to other local  
          agencies in SB 785 (Wolk). Specifically, this bill: 

             1)   Expands the definition of "transit operator" to include  
               any other local or regional agency responsible for the  
               construction of transit projects.

             2)   Repeals a requirement that transit operators report to  
               the Legislative Analyst's Office (LAO) about public works  
               projects financed with public funds and procured through  
               the design-build process. 

             3)   For project solicitations that begin on or after January  
               1, 2015, establishes a uniform threshold of $1 million for  
               projects to use design-build, except for projects for the  
               acquisition and installation of technology applications or  
               surveillance equipment to enhance safety, disaster  
               preparedness and homeland security efforts in which case  
               there is no minimum threshold.  

           FISCAL EFFECT  









                                                                  SB 1433
                                                                  Page  2

          1)Unknown overall contracting costs or savings to transit  
            operators. By extending design-build authority and deleting  
            cost thresholds for which design-build procurement may be  
            used, an increased number of future transit project may be  
            awarded on a "best value" rather than "lowest responsible  
            bidder" basis. Overall contracting costs may increase, to the  
            extent contracts are awarded to bidders who may not have the  
            lowest bid price. On the other hand, overall contracting costs  
            may be lower to the extent that efficiencies are gained by  
            using design-build, such as expedited project delivery.  
            Transit project funding could be from any combination of  
            local, federal, and state funds (Public Transportation Account  
            and potentially bond funds). 

          2)Likely minor costs to the Department of Industrial Relations  
            related to the department's monitoring and enforcement of  
            prevailing wage requirements, reimbursed by transit operators  
            (State Public Works Enforcement Fund). By extending the  
            deposit of funds into this continuously appropriated fund, the  
            bill makes an appropriation. 

          3)Minor cost savings to the LAO by deleting requirements that  
            transit operators submit reports on the use of design-build  
            (GF). 

           COMMENTS  

           1)Purpose  . The author contends this bill is necessary to  
            maintain an innovative and valuable tool transit operators can  
            use to deliver critical capital projects. In 2011, the Santa  
            Clara Valley Transportation Authority awarded a $900 million  
            design-build contract to extend the Bay Area Rapid Transit  
            system toward San Jose. According to bill proponents, this  
            project is currently ten months ahead of schedule and $100  
            million under budget. Projects experiencing results similar to  
            this suggest design-build can be a successful way to deliver  
            important transportation infrastructure within limited means.  
            As transit operators continue to wrestle with the challenge of  
            revenue growth not keeping pace with increasing costs, the  
            author believes this tool could help maintain transit  
            ridership and presence in the state. 

           2)Background  . Most public agency capital projects are  
            constructed using the traditional design-bid-build approach,  
            whereby complete plans and specifications are prepared prior  








                                                                  SB 1433
                                                                  Page  3

            to the advertising, bidding, and awarding of any construction  
            contracts to the lowest responsible bidder. Design-build is a  
            procurement process in which both the design and construction  
            of a project are procured from a single entity. The selected  
            firm arranges all architectural, engineering, and construction  
            services. The design-build entity is responsible for  
            delivering the project at a guaranteed price and schedule  
            based upon best value performance criteria set by the public  
            agency. Design-build is intended to expedite project delivery  
            and achieve efficiencies through collaboration between the  
            engineering and construction phases of project delivery. 

           3)Arguments in opposition  .  The Air Conditioning Sheet Metal  
            Association, the Air-conditioning and Refrigeration  
            Contractors Association, the California chapters of the  
            National Electrical Contractors Association, and the  
            California Legislative Conference of the Plumbing, Heating and  
            Piping Industry, in opposition, state, that unlike other  
            design-build statutes which contain protections for  
            contractors, subcontractors and construction industry  
            journeymen and apprentices, current law pertaining to  
            design-build authority for transit operators lacks many of the  
            industry supported boiler plate design-build provisions. 

           4)Amendment Needed  . Amendments agreed to by the author in the  
            Assembly Local Government Committee included, among other  
            things, a minimum cost threshold of $1 million for a project  
            to use design-build. This needs to be added to the article  
            whose sunset is being extended to January 1, 2017.

           5)Related legislation  .  SB 785 (Wolk) repeals various provisions  
            of existing law authorizing the Department of General  
            Services, the California Department of Corrections and  
            Rehabilitation, and local agencies (cities, counties and  
            certain special districts), including transit districts to use  
            the design-build procurement process, and recasts those  
            provisions in uniform statutes within the Public Contract  
            Code. This bill is pending on the Assembly Floor.


           6)Previous legislation  . 

             a)   AB 958 (Scott), Chapter 541, Statutes of 2000,  
               authorized transit operators to use design-build  
               procurement until January 1, 2005. SB 1130 (Scott), Chapter  








                                                                  SB 1433
                                                                  Page  4

               196, Statutes of 2004, extended the sunset date until  
               January 1, 2007. 

             b)   AB 372 (Nation), Chapter 262, Statutes of 2006, extended  
               the sunset again, to January 1, 2011, and made other  
               modifications to the authority, including requiring a  
               transit operator to establish a labor compliance program  
               for a design-build contract if the transit operator does  
               not already have such a program. 

             c)   AB 729 (Evans), Chapter 466, Statutes of 2009, extended  
               the sunset date once again until January 1, 2015. 


           Analysis Prepared by  :    Jennifer Swenson / APPR. / (916)  
          319-2081